All Schemes

2017-18 SCHEMES

1 Name of the Scheme and Year : MLA Fund 2017-18
2 Name of the Work : Drilling of bore wells and Water supply works
3 No. of works takenup : 9 Nos
4 Administrative Sanction Details : 1)      District Collector, Tiruppur in Roc.No. 1691 / 2017 / A6, dt. 17.07.2017

2)      District Collector, Tiruppur in Roc.No. 1691 / 2017 / A6, dt. 24.08.2017

3)      District Collector, Tiruppur in Roc.No. 1691 / 2017 / A6, dt. 22.12.2017

5 Estimate Cost (Rs. in lakhs) : Rs. 13.60 /- lakhs
6 Date of Tender : 11.08.2017, 19.09.2017 and 12.01.2018
7 Date of Work Order : 11.08.2017, 26.09.2017 and 12.01.2018
8 Present stage of work : Work completed
9 Expenditure so far : Rs. 13.60 /- lakhs
1 Name of the Scheme and Year : MP Fund 2017-18
2 Name of the Work : Providing High Mast lights
3 No. of works takenup : 1 No
4 Administrative Sanction Details : District Collector, Tiruppur in

Roc.No.1310 / 2017 / A6, dt. 11.07.2017

5 Estimate Cost (Rs. in lakhs) : Rs. 4.00 /- lakhs
6 Date of Tender : 04.08.2017
7 Date of Work Order : 18.08.2017
8 Present stage of work : Work completed
9 Expenditure so far : Rs. 4.00 /- lakhs
1 Name of the Scheme and Year : TURIP 2017-18
2 Name of the Work : Restoration of BT surface
3 No. of works takenup : 2 Nos
4 Administrative Sanction Details : CMA Proceeding Roc.No. 21422 / 2017 / P3, dated. 03.10.2017
5 Estimate Cost (Rs. in lakhs) : Rs. 300.00 /- lakhs

a) Govt. grant – Rs. 180.00 /- lakhs

b) CGF grant – Rs. 36.00 /- lakhs

c) CFC grant – Rs. 54.00 /- lakhs

d) ULB share – Rs. 30.00 /- lakhs

6 Date of Tender : 29.11.2017
7 Date of Work Order : 29.12.2017
8 Present stage of work : Work completed
9 Expenditure so far : Rs. 300.00 /- lakhs
1 Name of the Scheme and Year : 14th Finance Commission grant 2017-18
2 Name of the Work : Restoration of BT surface and Storm water drain
3 No. of works takenup : 4 Nos
4 Administrative Sanction Details : CMA Roc.No.14989 / P1 / 2016-2,

dated. 22.09.2017

5 Estimate Cost (Rs. in lakhs) : Rs. 93.00 /- lakhs
6 Date of Tender : 15.12.2017
7 Date of Work Order : 29.12.2017
8 Present stage of work : Work completed
9 Expenditure so far : Rs. 93.00 /- lakhs
1 Name of the Scheme and Year : SBM – Solid Waste Management 2017-18

(4th SHPC)

2 Name of the Work : SWM improvement works
3 No. of works takenup : 5 Nos
4 Administrative Sanction Details : CMA Pro. Roc.No. 24629 / P3 /2016,

dated. 22.11.2016

5 Estimate Cost (Rs. in lakhs) : Rs. 183.00 /- lakhs

a) GOI share – Rs. 64.05 /- lakhs

b) GOTN share – Rs. 100.65 /- lakhs

c) ULB share – Rs. 18.30 /- lakhs

6 Date of Tender : 30.12.2016, 28.06.2017, 10.02.2017
7 Date of Work Order : 01.02.2017, 27.01.2017, 27.07.2017

and 17.02.2017

8 Present stage of work : Work completed
9 Expenditure so far : Rs. 155.51 /- lakhs

2018-19 SCHEMES

1 Name of the Scheme and Year : TURIP 2018-19
2 Name of the Work : Restoration of BT surface and Providing BT surface
3 No. of works takenup : 3 Nos
4 Administrative Sanction Details : CMA Proceeding Roc.No. 12981 / 2018 / E3, dated. 17.07.2018
5 Estimate Cost (Rs. in lakhs) : Rs. 500.00 /- lakhs

a) Govt. grant – Rs. 230.00 /- lakhs

b) SF / CF grant – Rs. 150.00 /- lakhs

c) SFC incentive fund – Rs. 70.00 /- lakhs

d) ULB share – Rs. 50.00 /- lakhs

6 Date of Tender : 28.08.2018
7 Date of Work Order : 31.08.2018
8 Present stage of work : Works completed
9 Expenditure so far : Rs. 500.00 /- lakhs
1 Name of the Scheme and Year : SBM – MCC-I 2018-19 (7th SHPC)
2 Name of the Work : Construction of MCC’s and Supply of BOV’s
3 No. of works takenup : 3 Nos
4 Administrative Sanction Details : CMA proceedings Roc No. 22866 / P2 / 2018, dated. 23.08.2018
5 Estimate Cost (Rs. in lakhs) : Rs. 76.20 /- lakhs

a) GOI share – Rs. 26.67 /- lakhs

b) GOTN share – Rs. 41.91 /- lakhs

c) ULB share – Rs. 7.62 /- lakhs

6 Date of Tender : 18.09.2018 and 07.09.2018
7 Date of Work Order : 18.09.2018 and 07.09.2018
8 Present stage of work : Works completed
9 Expenditure so far : Rs. 76.15 /- lakhs
1 Name of the Scheme and Year : SBM – MCC-II 2018-19 (8th SHPC)
2 Name of the Work : Bio mining, Supply of LCV’s and BOV’s
3 No. of works takenup : 3 Nos
4 Administrative Sanction Details : CMA proceedings Roc No. 1191 / P3 / 2019, dated. 21.01.2019
5 Estimate Cost (Rs. in lakhs) : Rs. 103.40 /- lakhs

a) GOI share – Rs. 36.19 /- lakhs

b) GOTN share – Rs. 56.87 /- lakhs

c) ULB share – Rs. 10.34 /- lakhs

6 Date of Tender : 12.02.2019
7 Date of Work Order : 15.02.2019
8 Present stage of work : 2 Works completed and 1 work under progress
9 Expenditure so far : Rs. 98.77 /- lakhs
1 Name of the Scheme and Year : MLA Fund 2018-19
2 Name of the Work : Water supply, Lights and BT road works
3 No. of works takenup : 5 Nos
4 Administrative Sanction Details : District Collector, Tiruppur in

Roc.No. 3772/2018/A6, dt. 26-02-2019

5 Estimate Cost (Rs. in lakhs) : Rs. 13.97 /- lakhs
6 Date of Tender : 27.02.2019
7 Date of Work Order : 31.05.2019
8 Present stage of work : Work completed
9 Expenditure so far : Rs. 9.94 /- lakhs
1 Name of the Scheme and Year : MP Fund 2018-19
2 Name of the Work : Water supply and Light works
3 No. of works takenup : 2 Nos
4 Administrative Sanction Details : District Collector, Tiruppur in

Roc.No. 2520 / 2018 / A6, dt. 21.08.2018

5 Estimate Cost (Rs. in lakhs) : Rs. 7.50 /- lakhs
6 Date of Tender : 18.09.2018
7 Date of Work Order : 01.10.2018
8 Present stage of work : Work completed
9 Expenditure so far : Rs. 7.50 /- lakhs
1 Name of the Scheme and Year : GF Fund 2018-19
2 Name of the Work : Water ATM
3 No. of works takenup : 21 Nos
4 Administrative Sanction Details : MCR No. 186 / 2018, dated. 28.09.2018
5 Estimate Cost (Rs. in lakhs) : Rs. 378.00 /- lakhs
6 Date of Tender : 23.10.2018 and 23.11.2018
7 Date of Work Order : 31.10.2018 and 30.11.2018
8 Present stage of work : 1) 3 no of ATM works completed

2) 16 nos earth work under progress

3) 2 no of works only for work order issued stage

9 Expenditure so far : Nil

2019-20 SCHEMES

1 Name of the Scheme and Year : TURIP 2019-20
2 Name of the Work : Road works
3 No. of works takenup : 4 Nos
4 Administrative Sanction Details : CMA Proceeding Roc.No. 17349 / 2019 / E3, dated. 24.09.2019
5 Estimate Cost (Rs. in lakhs) : Rs. 700.00 /- lakhs
6 Date of Tender : 12.11.2019
7 Date of Work Order : 09.12.2019
8 Present stage of work : Works completed
9 Expenditure so far : Rs. 619.59 /- lakhs
1 Name of the Scheme and Year : 14th Central Finance Commission 2019-20
2 Name of the Work : Road works
3 No. of works takenup : 15 Nos
4 Administrative Sanction Details : MCR No. 1 / 2020, dated. 06.01.2020
5 Estimate Cost (Rs. in lakhs) : Rs. 225.00 /- lakhs

a) GOTN share – Rs. 223.34 /- lakhs

b) ULB share – Rs. 1.66 /- lakhs

6 Date of Tender : 07.01.2020
7 Date of Work Order : 31.01.2020
8 Present stage of work : Works completed
9 Expenditure so far : Rs. 199.96 /- lakhs
1 Name of the Scheme and Year : IUDM 2020-21
2 Name of the Work : Road works
3 No. of works takenup : 2 Nos
4 Administrative Sanction Details : MAWS dept GO.No. 303, dated. 09.09.2020
5 Estimate Cost (Rs. in lakhs) : Rs. 300.00 /- lakhs

a) GOTN share – Rs. 240.00 /- lakhs

b) ULB share – Rs. 60.00 /- lakhs

6 Date of Tender : 14.10.2020
7 Date of Work Order : 27.10.2020
8 Present stage of work : Work is in progress
9 Expenditure so far : Rs. 170.00 /- lakhs
1 Name of the Scheme and Year : SRP 2020-21
2 Name of the Work : Road works
3 No. of works takenup : 13 Nos
4 Administrative Sanction Details : CMA Proc. Roc.No. 20557 / 2020 / E3, dt. 15.12.20
5 Estimate Cost (Rs. in lakhs) : Rs. 2400.00 /- lakhs

a) GOTN share – Rs. 2040.00 /- lakhs

b) ULB share – Rs. 360.00 /- lakhs

6 Date of Tender : 21.01.2021
7 Date of Work Order : 01.02.2021
8 Present stage of work : Completed works – (9 Packages, 59 works)
Progress works – (4 packages, 17 works)
9 Expenditure so far : Nil
1 Name of the Scheme and Year : 15th CFC 2020-21
2 Name of the Work : General works
3 No. of works takenup : 7 Nos
4 Administrative Sanction Details : MCR No. 271 / 2020, dated. 30.12.2020
5 Estimate Cost (Rs. in lakhs) : Rs. 97.50 /- lakhs

a) GOI share – Rs. 97.50 /- lakhs

6 Date of Tender : 26.02.2021
7 Date of Work Order : 07.06.2021
8 Present stage of work : 6 Work is in progress, 1 work awaiting for AS
9 Expenditure so far : Nil
1 Name of the Scheme and Year : KNMT 2021-22
2 Name of the Work : Earthen road to BT road
3 No. of works takenup : 1 Package (21 Nos)
4 Administrative Sanction Details : DMA Proc. Roc.No. 20543 / 2021 / B2, dt. 16.11.21
5 Estimate Cost (Rs. in lakhs) : Rs. 270.50 /- lakhs
6 Date of Tender : 08.12.2021
7 Date of Work Order : 15.12.2021
8 Present stage of work : Work order issued
9 Expenditure so far : Nil