SEWERAGE EXISTING SITUATION
UNDER GROUND DRAINAGE SYSTEM IS OPERATIONAL IN ALL THE 27 WARDS OF TIRUVALLUR MUNICIPALITY
| DATE OF INAUGURATION |
– | 26-06-2014 |
| TECHNOLOGY USED AND CAPACITY OF STP | – | MBBR AND 6.20 MLD |
| NUMBER OF LIFTING STATION | – | 5 |
| NUMBER OF PUMPING STATION | – | 4 |
| LENGTH OF SEWER MAINS | – | 85.542 KM |
| TOTAL NUMBER OF MANHOLES | – | 10387 |
| LENGTH OF PUMPING MAINS | – | 8.760 KM |
| TOTAL NUMBER OF CONNECTIONS AS PER DPR | – |
8618 |