Re-development of Old Bus Stand
Project Cost : Rs.38.81Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work: Completed on 31-10-2022
Expenditure So far : 38.78 Crores.
Construction of Multi Level Car Parking near Old Bus Stand
Project Cost : Rs.19.98 Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work: Completed on 31-08-2022
Expenditure So far : 19.32 Crores
Construction of Convention Centre
Project Cost : Rs.53.48.00Crores
Date of Tender :14.12.2018
Date of Work Order : 29.01.2019
Present Stage of Work: Completed on 28-02-2024
Expenditure So far :51.94 Crores
Re-development of New Bus Stand.
Project Cost : Rs. 29.48 Crores
Date of Tender :11.02.2019
Date of Work Order : 22.02.2019
Present Stage of Work: Completed on 30-04-2023
Expenditure So far : 29.41 Crores
Development of Multi-Level Car Parking near Town Hall
Project Cost : Rs12.02 Crores
Date of Tender :25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: Completed on 31-03-2023.
Expenditure So far : 11.23 CRORES.
Re-development of Fish Market
Project Cost : Rs.2.34 Crores
Date of Tender : 25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: work completed on 31-12-2022.
Expenditure So far : 2.33 CRORES
Re-development of Thennampalayam Weekly Shandy Market
Project Cost : Rs.12.81 Crores
Date of Tender : 28.02.2019
Date of Work Order: 03.06.2016
Present Stage of Work: work completed on 31-03-2022.
Expenditure So far : 12.48 CRORES
Re-development of Daily Market
Project Cost : Rs.31.88 Crores
Date of Tender :28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: Completed on 30-11-2023.
Expenditure So far : 30.70 CRORES
Re-development of Flower Market
Project Cost : Rs.4.80 Crores
Date of Tender : 28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: Completed on 30-10-2022.
Expenditure So far : 4.68 CRORES
Roof Top Solar.
Project Cost : Rs.2.39 Crores
Date of Tender :14.12.2018
Date of Work Order : 25.02.2019
Present Stage of Work :Work Completed on 31.12.2020
Expenditure So far :2.39CRORES
Solar Power Plant 4.80MW
Project Cost : Rs.29.24 Crores
Date of Tender : 25.02.2019
Date of Work Order : 24.06.2019
Present Stage of Work :Work Completed on 28.02.2021
Expenditure So far : 27.51 CRORES
Solar Power Plant 2.00MW
Project Cost : Rs.13.00 Crores
Date of Tender : 24.07.2019
Date of Work Order : 03.10.2019
Present Stage of Work: Completed on 28.02.2021.
Expenditure So far :11.79 CRORES
Green Space Parks
Project Cost : Rs.3.95 Crores
Date of Work Order : 23.08.2018
Present Stage of Work: Completed on 31.10.2019.
Expenditure So far :3.88 CRORES
Water Supply Improvement Scheme AMRUT (2015-2016)
Project Cost : Rs.75.00 Crores
Date of Work Order : 16.07.2017
Present Stage of Work : Work Completed on 31.12.2020
Expenditure So far :75.00 CRORES
New Water Supply Scheme AMRUT (2017-2020)
Project Cost : Rs.114.15Crores
Date of Work Order : 04.02.2019 & 28.08.2019 01.,03.2019, 03.06.2019 & 28.06.2019
Present Stage of Work : Work Completed on 31.08.2022
Expenditure So far : 114.15 CRORES
UGSS (AMRUT)-2017-2020
Project Cost : Rs.64.84Crores
Date of Work Order : 04.02.2019, 28.07.2019 & 10.07.2019
Present Stage of Work : Work Completed on 31.08.2022
Expenditure So far : 64.84 Crores.
Internal Plumbing for Water Supply System (Package No.1)
Project Cost : Rs.15.47 Crores
Date of Tender : 27.12.2019
Date of Work Order : 20.04.2020
Present Stage of Work : (99 % Completed) 40956 Numbers of Connections completed out of 41226 Connections.
Probable Date of Completion: 30.06.2025
Expenditure so far: 13.47 crores
Internal Plumbing for Water Supply System (Package No.2)
Project Cost : Rs.14.90 Crores
Date of Tender : 27.12.2019
Date of Work Order : 12.03.2020
Present Stage of Work : (100 % Completed) 39698 Numbers of Connections completed out of 39698 Connections.
Date of Completion:31-10-2024.
Expenditure so far: 14.90 crores
Installation of Signage’s
Project Cost : Rs. 6.37 Crores
Date of Tender : 10.12.2019
Date of Work Order : 30.03.2020
Date of Completion:28.02.2023.
Expenditure So far : 6.37 Crores.
Macro Drainage (Package-I)
Project Cost : Rs.15.72 Crores
Date of Tender : 17.09.2019
Date of Work Order : 13.03.2020
Present Stage of Work: work completed on 31-03-2022.
Expenditure so far: 15.72 crores
Macro Drainage (Package-II)
Project Cost : Rs.25.60 Crores
Date of Tender : 11.02.2020
Date of Work Order : 22.05.2020
Present Stage of Work: work completed on 31-01-2022.
Expenditure so far: 25.60 Crores
Smart Road (Phase-I)
Project Cost : Rs.88.24 Crores
Date of Tender :27.12.2019
Date of Work Order : 20.03.2020, 24.03.2020, 07.04.2020
Present Stage of Work: Completed on 28-02-2023.
Expenditure so far: 88.24 crores.
Smart Road (Phase-II)
Project Cost : Rs. 59.69 Crores
Date of Tender :10.03.2020
Date of Work Order : 25.06.2020. & 15.07.2020
Present Stage of Work: Completed on 28-02-2023.
Expenditure so far: 59.69 crores
River front Development (Package-I)
Project Cost : Rs.32.87 Crores
Date of Tender : 24.12.2019
Date of Work Order : 09.06.2020
Present Stage of Work: 1) Baby Channel works 6.308 Km Completed out of 6.382 Km
Expenditure so far:30.68 crores.
Date of Completion:31.05.2025
River front Development (Package-II)
Project Cost : Rs.31.70 Crores
Date of Tender : 24.12.2019
Date of Work Order : 26.03.2020
Present Stage of Work: 1) Baby Channel works 6.536 Km Completed out of 6.595 Km
Expenditure so far: 31.03 crores.
Probable Date of Completion:31.07.2025
River front Development (Package-III)
Project Cost : 29.15 Crores
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work :
DBM Laying :-11.85 Km completed out of 12.48 Km. Balance 0.630Km
BC Laying :- 6.09 Km completed out of 12.48 Km. Balance 6.39 Km.
Street Light:-
360 Nos completed out of 448 Nos. Balance – 88 Nos.
Fencing work:-11.66 Km completed out of 12.06 Km. Balance – 0.40 Km.
Jammanai Odai Bridge structure work 100 % completed.
Expenditure so far: 15.54 Crores
Probable Date of Completion:31.07.2025
River front Development (Package-IV)
Project Cost : 32.71 Crores
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work:
1) Toe Wall 5.162 Km Completed out of 5.182 Km
2) Retaining wall (kerb) 4.416 Km Completed out of 4.476 Km
3) Bund Lining 5.112 Km Completed out of 5.182 Km
4) 4m Retaining wall with Counter Fort 0.830 Km Completed out of 0.830 Km
5) Jammanai Odai Bridge structure work 100% completed.
Expenditure so far: 32.20 crores.
Date of Completion:31.03.2025
River front Development (Package-V)
Project Cost : 29.89 Crores
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work:
1) Toe Wall 5.974 Km Completed out of 5.974 Km
2) Retaining wall (Kerb) 5.974 Km Completed out of 5.974 Km
3) Bund Lining 5.974 Km Completed out of 5.974 Km
4) Retaining wall with Counter Fort 1.006 Km Completed out of 1.006 Km.
5) Culverts 16 Nos Completed out of 16 Nos.
Expenditure so far: 29.29Crores.
Date of Completion:31.03.2025
River front Development (Package-VI)
Project Cost : 9.40 Crores
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work:-
- A) 2 MLD – Mullukaadu (Near Electric Crematorium)
1) All components – Finishing work to be started.
2) Mechanical All Component Erection work to be started.
3) % of Completion – 85%
B) 3 MLD – Alangadu
1) All components – Finishing work to be started.
2) Mechanical All Component Erection work to be started.
3) % of Completion -85%
Expenditure so far: 7.44 Crore.
Probable Date of Completion:31.08.2025
LED STREET LIGHT (Package 1-New Light 3262 Nos & Package 2-Conversion Light-6604Nos)
Project Cost : Rs.15.60 Crores
Date of Tender : 31.01.2019
Date of Work Order : 02.08.2019
Present Stage of Work: Work Completed on 28.02.2021.
Expenditure so far: 15.60 CRORES
Solid Waste Management
Project Cost : Rs.22.19 Crores
Date of Tender : 04.02.2019, 11.02.2019, 31.01.2019.
Date of Work Order : 11.02.2019, 18.02.2019, 08.02.2019, 19.02.2019.
Present Stage of Work: Work Completed on 31.12.2020.
Expenditure so far: 21.47CRORES
Knowledge Centre cum Library
Project Cost : Rs.2.59 Crores
Date of Tender : 14.02.2022
Date of Work Order : 21.03.2022.
Present Stage of Work: Work Completed on 28.02.2023.
Expenditure so far: 2.52 CRORES
Design and Construction of Sewage Treatment Plants of capacity 4MLD (2 Nos of each 2 MLD ) including 5 years of operation and maintenance on DBOT basis.
Project Cost : Rs.5.99 Crores
Date of Tender : 15.03.2022
Date of Work Order : 30.03.2022.
A) 2 MLD – Kasipalayam Road:-
All Components – Finishing, Mechanical, Electrical and Plumbing works are Completed.
EB Demand received, Payment under process.
% of Completion –98 %
- B) 2 MLD – Chinnan Nagar :-
All Components –Finishing, Mechanical, Electrical and Plumbing works are Completed.
EB Demand paid, Transformer erection work completed. Awaiting for EB Meter.
% of Completion –98 %
Probable Date of Completion:31.07.2025
Expenditure so far: 4.67 CRORES