SMART CITY

 Smart City Mission

  1. Re-development of Old Bus Stand
    Estimate Amount : Rs.38.81Crores
    Date of Tender : 13.12.2018
    Date of Work Order : 23.01.2019
    Present Stage of Work: Completed on 31-10-2022

Expenditure So far : 38.78 Crores.

 

  1. Construction of Multi Level Car Parking near Old Bus Stand
    Estimate Amount : Rs.18.17 Crores
    Date of Tender : 13.12.2018
    Date of Work Order : 23.01.2019
    Present Stage of Work: Completed on 31-08-2022

Expenditure So far : 19.32 Crores

 

  1. Construction of Convention Centre
    Estimate Amount :Rs.52.00Crores
    Date of Tender :14.12.2018
    Date of Work Order : 29.01.2019
    Present Stage of Work:

1) Portico Ramp Granite work is in progress.

2) Basement & Ground Floor Internal Paining work is Progress

3) Common Area – False ceiling work is in progress.

4) GFRC works in progress at Terrace Floor.

5) Transformer Yard work is in progress

6) Front Arch & Compound Wall work is in progress.

Expenditure So far :44.50 Crores

  1. Re-development of New Bus Stand.
    Estimate Amount :Rs. 29.79 Crores
    Date of Tender :11.02.2019
    Date of Work Order : 22.02.2019
    Present Stage of Work: Completed on 30-04-2023
    Expenditure So far : 29.41 CRORES
  2. Development of Multi-Level Car Parking near Town Hall
    Estimate Amount :Rs12.02 Crores
    Date of Tender :25.02.2019
    Date of Work Order : 03.06.2019
    Present Stage of Work: Completed on 31-03-2023.
    Expenditure So far : 11.23 CRORES.
  3. Re-development of Fish Market
    Estimate Amount : Rs.2.175 Crores
    Date of Tender : 25.02.2019
    Date of Work Order : 03.06.2019
    Present Stage of Work: work completed on 28-02-2022.
    Expenditure So far : 2.33 CRORES
  4. Re-development of Thennampalayam Weekly Shandy Market
    Estimate Amount : Rs.12.86 Crores
    Date of Tender : 28.02.2019
    Date of Work Order: 03.06.2016
    Present Stage of Work: work completed on 31-03-2022.
    Expenditure So far : 12.48 CRORES
  5. Re-development of Daily Market
    Estimate Amount : Rs.28.99 Crores
    Date of Tender :28.02.2019
    Date of Work Order : 03.06.2019
    Present Stage of Work: Completed on 30-11-2023.
    Expenditure So far : 26.71 CRORES
  6. Re-development of Flower Market
    Estimate Amount : Rs.4.47 Crores
    Date of Tender : 28.02.2019
    Date of Work Order : 03.06.2019
    Present Stage of Work: Completed on 30-10-2022.
    Expenditure So far : 4.68 CRORES
  7. Roof Top Solar.
    Estimate Amount : Rs.2.34 Crores
    Date of Tender :14.12.2018
    Date of Work Order : 25.02.2019
    Present Stage of Work :Work Completed on 31.12.2020
    Expenditure So far :2.39CRORES
  8. Solar Power Plant 4.80MW
    Estimate Amount : Rs.27.16 Crores
    Date of Tender : 25.02.2019
    Date of Work Order : 24.06.2019
    Present Stage of Work :Work Completed on 28.02.2021
    Expenditure So far : 27.51 CRORES

 

 

 

  1. Solar Power Plant 2.00MW
    Estimate Amount : Rs.11.85 Crores
    Date of Tender : 24.07.2019
    Date of Work Order : 03.10.2019
    Present Stage of Work: Completed on 28.02.2021.
    Expenditure So far :11.79 CRORES
  2. Green Space Parks
    Estimate Amount : Rs.3.86 Crores
    Date of Work Order : 23.08.2018
    Present Stage of Work: Completed on 31.10.2019.
    Expenditure So far :3.88 CRORES

14.Water Supply Improvement Scheme Amrut (2015-2016)
Estimate Amount : Rs.75 Crores
Date of Work Order : 16.07.2017
Present Stage of Work : Work Completed on 31.12.2020
Expenditure So far :75.00CRORES

  1. New Water Supply Scheme AMRUT (2017-2020)
    Estimate Amount : Rs.114.15Crores
    Date of Work Order : 04.02.2019 & 28.08.2019 01.,03.2019, 03.06.2019 & 28.06.2019
    Present Stage of Work : Work Completed on 31.08.2022
    Expenditure So far : 114.15CRORES
  2. UGSS (AMRUT)-2017-2020
    Estimate Amount : Rs.64.84Crores
    Date of Work Order : 04.02.2019, 28.07.2019 & 10.07.2019
    Present Stage of Work : Work Completed on 31.08.2022
    Expenditure So far : 64.84Crores.
  3. Internal Plumbing for Water Supply System (Package No.1)
    Estimate Amount : Rs.14.38 Crores
    Date of Tender : 27.12.2019
    Date of Work Order : 20.04.2020
    Present Stage of Work : 1) 23536 Numbers of Connections completed out of 41226 Connections.
    Expenditure so far: 6.70 crores
  4. Internal Plumbing for Water Supply System (Package No.2)
    Estimate Amount : Rs.14.38 Crores
    Date of Tender : 27.12.2019
    Date of Work Order : 12.03.2020
    Present Stage of Work : 1) 30702 Numbers of Connections completed out of 40756 Connections.
    Expenditure so far: 10.73 crores
  5. Signage’s
    Estimate Amount : Rs. 6.33 Crores
    Date of Tender : 10.12.2019
    Date of Work Order : 30.03.2020
    Present Stage of Work : Completed on 28-02-2023
    Expenditure So far : 6.38 Crores.
  6. Macro Drainage (Package-I)
    Estimate Amount : Rs.15.61 Crores
    Date of Tender : 17.09.2019
    Date of Work Order : 13.03.2020
    Present Stage of Work: work completed on 31-03-2022.
    Expenditure so far: 15.72 crores
  7. Macro Drainage (Package-II)
    Estimate Amount : Rs.27.63 Crores
    Date of Tender : 11.02.2020
    Date of Work Order : 22.05.2020
    Present Stage of Work: work completed on 31-01-2022.
    Expenditure so far: 25.49 Crores
  8. Smart Road (Phase-I)
    Estimate Amount : Rs.88.24 Crores
    Date of Tender :27.12.2019
    Date of Work Order : 20.03.2020, 24.03.2020, 07.04.2020
    Present Stage of Work: Completed on 28-02-2023.
    Expenditure so far: 87.70 crores.

Smart Road (Phase-II)
Estimate Amount :Rs. 71.79 Crores
Date of Tender :10.03.2020
Date of Work Order : 25.06.2020. & 15.07.2020
Present Stage of Work: Completed on 28-02-2023.
Expenditure so far: 59.69 crores

  1. . River front Development (Package-I)
    Estimate Amount : Rs.30.50 Crores
    Date of Tender : 24.12.2019
    Date of Work Order : 09.06.2020
    Present Stage of Work: 1) Baby Channel works 6.253 Km Completed out of 6.448 Km

Expenditure so far:30.61 crores.

 

River front Development (Package-II)
Estimate Amount : Rs.29.00 Crores
Date of Tender : 24.12.2019
Date of Work Order : 26.03.2020
Present Stage of Work: 1) Baby Channel works 6.458 Km Completed out of 6.595 Km
Expenditure so far: 30.46 crores.

River front Development (Package-III)
Estimate Amount : 29.00
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work :

1)Renewal BT – DBM 1.80 Km Completed out of 1.80 Km.

2) Laying of DBM 5.704 Km completed out of 11.60 Km.

3) Street Light 98 Nos Completed out of 448 Nos

4) Fencing work 3126 Km Completed out of 13.40 km
Expenditure so far: 6.31 Crores

River front Development (Package-IV)
Estimate Amount : 30.00
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work:

1) Toe Wall 4.232 Km Completed out of 5.182 Km

2) Retaining wall (kerb) 3.266 Km Completed out of 4.476 Km

3) Bund Lining 3.872 Km Completed out of 5.182 Km

4) Retaining wall with Counter Fort 0.600 Km Completed out of 0.830 Km

5) Jammanai Odai Bridge structure work 90% completed.
Expenditure so far: 20.07 crores.

 

River front Development (Package-V)
Estimate Amount : 28.76
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work:

1) Toe Wall 5.946 Km Completed out of 5.974 Km

2) Retaining wall (Kerb) 5.946 Km Completed out of 5.974 Km

3) Bund Lining 5.946 Km Completed out of 5.974 Km

4) Retaining wall with Counter Fort 0.529 Km Completed out of 0.626 Km

5) Culverts 16 Nos Completed out of 18 Nos.
Expenditure so far: 30.84 Crores.

 

River front Development (Package-VI)
Estimate Amount : 9.40
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work:

  1. A) 2 MLD – Near Electric Crematorium.

1) Plate Filtrate House, Admin Block, Blower Room, Chlorination House, Chemical House  – Roof Packing work is in progress.

  1. B) 3 MLD – Alangadu

1) MBBR Tank – Pathway slab work in progress.

2) Secondary Clarifier tank, – Wall work in progress.

3) Admin Block – Roof packing work is in progress

4) Sludge Thickener Tank – Raft work is in progress.

5) Chlorination House & Chemical House – Above Lintel Brickwork is in progress.

Expenditure so far: 3.91 Crore.

  1. LED STREET LIGHT
    Estimate Amount : Rs.16.92 Crores
    Date of Tender : 31.01.2019
    Date of Work Order : 02.08.2019
    Present Stage of Work: Work Completed on 28.02.2021.
    Expenditure so far: 14.64CRORES
  2. Solid Waste Management
    Estimate Amount : Rs.22.19 Crores
    Date of Tender : 04.02.2019, 11.02.2019, 31.01.2019.
    Date of Work Order : 11.02.2019, 18.02.2019, 08.02.2019, 19.02.2019.
    Present Stage of Work:Work Completed on 31.12.2020.
    Expenditure so far: 21.47CRORES