SMART CITY

 Smart City Mission

1. Re-development of Old Bus Stand
Estimate Amount : Rs.36.50Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work: 1) Main Building entrance portion Art work in progress.
2) Shops External Painting work in Progress.
3) Tensile Roof Fixing work in Progress at Main Building and Foot over Bridge.
Expenditure So far : 30.03 Crores.

2. Construction of Multi Level Car Parking near Old Bus Stand
Estimate Amount : Rs.18.17 Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work: 1) Lift Eraction work in progress
2) Fire fighting External Pipe fitting work in Progress.
Expenditure So far : 18.52 Crores

3. Construction of Convention Centre
Estimate Amount :Rs.52.00Crores
Date of Tender :14.12.2018
Date of Work Order : 29.01.2019
Present Stage of Work: 1) Basement floor ceiling plastering work in progress.
2) Second floor Roof Slab bay 1 shuttering & Reinforcement work in progress.
Expenditure So far : 18.11 Crores

4. Re-development of New Bus Stand.
Estimate Amount :Rs. 29.79 Crores
Date of Tender :11.02.2019
Date of Work Order : 22.02.2019
Present Stage of Work: 1) Internal Wall Putty work in progress.
2) External & Internal Plastering work in progress.
3) Internal floor tile laying work in progress.
4) Shops Rolling shutter fixing work in progress.
5) Rain Water pipe fixing work in progress.
6) Internal Granite Laying work in Progress.
Expenditure So far : 19.30 CRORES

5. Development of Multi Level Car Parking near Town Hall
Estimate Amount :Rs12.02 Crores
Date of Tender :25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: 1) 3rd & 4th floor Ellis pattern flooring concrete work in progress.
Expenditure So far : 8.45 CRORES

6. Re-development of Fish Market
Estimate Amount : Rs.2.175 Crores
Date of Tender : 25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: work completed on 28-02-2022.
Expenditure So far : 2.04 CRORES

7. Re-development of Thennampalayam Weekly Shandy Market
Estimate Amount : Rs.12.86 Crores
Date of Tender : 28.02.2019
Date of Work Order: 03.06.2016
Present Stage of Work: work completed on 31-03-2022.
Expenditure So far : 12.10 CRORES

8. Re-development of Daily Market
Estimate Amount : Rs.28.99 Crores
Date of Tender :28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: 1) Bay 1 Ground floor brick work in progress.
2) Bay 3 First floor Shuttering & Reinforcement work in Progress.
3) Bay 3 Basement floor Ceiling Plastering work in Progress.
4) Bay 1 Terrace floor Parapet column concrete work in Progress.
Expenditure So far : 18.26 CRORES

9. Re-development of Flower Market
Estimate Amount : Rs.4.47 Crores
Date of Tender : 28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: 1) Exit Ramp ceiling & wall Plastering work in Progress.
2) Entry ramp column Plastering work in Progress.
Expenditure So far : 3.37 CRORES

10. Roof Top Solar.
Estimate Amount : Rs.2.34 Crores
Date of Tender :14.12.2018
Date of Work Order : 25.02.2019
Present Stage of Work :Work Completed
Expenditure So far :1.92 Crores

11. Solar Power Plant 4.80MW
Estimate Amount : Rs.27.16 Crores
Date of Tender : 25.02.2019
Date of Work Order : 24.06.2019
Present Stage of Work :Work Completed
Expenditure So far : 27.44 CRORES

12. Solar Power Plant 2.00MW
Estimate Amount : Rs.11.85 Crores
Date of Tender : 24.07.2019
Date of Work Order : 03.10.2019
Present Stage of Work :Work Completed.
Expenditure So far : 11.82 Crore

13. Green Space Parks
Estimate Amount : Rs.3.86 Crores
Date of Work Order : 23.08.2018
Present Stage of Work : Work Completed. Trial run in progress.
Expenditure So far : 3.88 Crores

14.Water Supply Improvement Scheme Amrut (2015-2016)
Estimate Amount : Rs.75 Crores
Date of Work Order : 16.07.2017
Present Stage of Work : 99.5% Work completed.
Expenditure So far :75.00

15. New Water Supply Scheme AMRUT (2017-2020)
Estimate Amount : Rs.106.35 Crores
Date of Work Order : 04.02.2019 & 28.08.2019 01.,03.2019, 03.06.2019 & 28.06.2019
Present Stage of Work : Overall 73% of work completed.
PDC 08/2022.
Expenditure So far : 106.35 Crores.

16. UGSS (AMRUT)-2017-2020
Estimate Amount : Rs.60.41 Crores
Date of Work Order : 04.02.2019, 28.07.2019 & 10.07.2019
Present Stage of Work : Overall 71% of work completed.
PDC 07/2023.
Expenditure So far : 60.40Crores.

17. Internal Plumbing for Water Supply System (Package No.1)
Estimate Amount : Rs.14.38 Crores
Date of Tender : 27.12.2019
Date of Work Order : 20.04.2020
Present Stage of Work : 1) 9897 Numbers of Connection completed within ABD Area.
Expenditure so far:2.77 crores

18. Internal Plumbing for Water Supply System (Package No.2)
Estimate Amount : Rs.14.38 Crores
Date of Tender : 27.12.2019
Date of Work Order : 12.03.2020
Present Stage of Work : 1) 12029 Numbers of Connection completed within ABD Area.
Expenditure so far: 2.26 crores

19. Signage’s
Estimate Amount : Rs. 6.33 Crores
Date of Tender : 10.12.2019
Date of Work Order : 30.03.2020
Present Stage of Work : 1) Main Junction Area Boards are installed (75%)
2) Single arrow & double arrow sign board fixing work in progress.
Expenditure So far :2.63Crores.

20. Macro Drainage (Package-I)
Estimate Amount : Rs.15.61 Crores
Date of Tender : 17.09.2019
Date of Work Order : 13.03.2020
Present Stage of Work: work completed on 31-03-2022.
Expenditure so far: 15.44 crores

21. Macro Drainage (Package-II)
Estimate Amount : Rs.27.63 Crores
Date of Tender : 11.02.2020
Date of Work Order : 22.05.2020
Present Stage of Work: work completed on 31-01-2022.
Expenditure so far: 25.49 Crores

22. Smart Road (Phase-I)
Estimate Amount : Rs.88.24 Crores
Date of Tender :27.12.2019
Date of Work Order : 20.03.2020, 24.03.2020, 07.04.2020
Present Stage of Work: 1) Concrete Road Works 8.522 Km Completed out of 11.264 Km
Expenditure so far:57.39 crores.

Smart Road (Phase-II)
Estimate Amount :Rs. 71.79 Crores
Date of Tender :10.03.2020
Date of Work Order : 25.06.2020. & 15.07.2020
Present Stage of Work: 1) Concrete Road Works 8.842 Km Completed out of 12.342 km
Expenditure so far:51.86 crores

23. . River front Development (Package-I)
Estimate Amount : Rs.30.50 Crores
Date of Tender : 24.12.2019
Date of Work Order : 09.06.2020
Present Stage of Work: 1) Baby Channel works 3.42 Km Completed out of 6.70 Km
Expenditure so far:14.33crores.

River front Development (Package-II)
Estimate Amount : Rs.29.00 Crores
Date of Tender : 24.12.2019
Date of Work Order : 26.03.2020
Present Stage of Work: 1) Baby Channel works 5.09 Km Completed out of 6.70 Km
Expenditure so far: 23.42 crores.

River front Development (Package-III)
Estimate Amount : 29.00
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work : 1) Bund Survey work in progress
2) Bitumen road Road Picking work 250 m completed.
3) Bitumen road sub base (GSB) 200 m completed.
4) Bitumen road sub base (WMM) 200 m completed.
Expenditure so far: 0.44

River front Development (Package-IV)
Estimate Amount : 30.00
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work: 1) Toe Wall 2.65 Km Completed out of 6.70 Km
2) Retaining wall 1.83 Km Completed out of 6.70 Km
3) Bund Lining 1.47 Km Completed out of 6.70 Km
4) Jammanai Odai Bridge structure work 16% completed.
Expenditure so far:9.40 crores.

River front Development (Package-V)
Estimate Amount : 28.76
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work: 1) Toe Wall 5.60 Km Completed out of 6.70 Km
2) Retaining wall 5.60 Km Completed out of 6.70 Km
3) Bund Lining 5.60 Km Completed out of 6.70 Km
4) 2 Nos culver concrete in Progress & Culverts 11 Nos Completed out of 20 Nos.
Expenditure so far: 20.15 Crore.

River front Development (Package-VI)
Estimate Amount : 9.40
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work: 1) 2 MLD Designing work under process.
Expenditure so far: 2.45Crore.

24. LED STREET LIGHT
Estimate Amount : Rs.16.92 Crores
Date of Tender : 31.01.2019
Date of Work Order : 02.08.2019
Present Stage of Work: work completed.
Expenditure so far: 14.62Crores

25. Solid Waste Management
Estimate Amount : Rs.22.19 Crores
Date of Tender : 04.02.2019, 11.02.2019, 31.01.2019.
Date of Work Order : 11.02.2019, 18.02.2019, 08.02.2019, 19.02.2019.
Present Stage of Work: work completed.
Expenditure so far: 20.50 Crores.