SMART CITY

Re-development of Old Bus Stand
Project Cost : Rs.38.81Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work: Completed on 31-10-2022

Expenditure So far : 38.78 Crores. 

 

Construction of Multi Level Car Parking near Old Bus Stand
Project Cost : Rs.19.98 Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work: Completed on 31-08-2022

  Expenditure So far : 19.32 Crores 

 

Construction of Convention Centre
Project Cost : Rs.53.48.00Crores
Date of Tender :14.12.2018
Date of Work Order : 29.01.2019
Present Stage of Work: Completed on 28-02-2024

Expenditure So far :51.94 Crores

 

Re-development of New Bus Stand.
Project Cost : Rs. 29.48 Crores
Date of Tender :11.02.2019
Date of Work Order : 22.02.2019
Present Stage of Work: Completed on 30-04-2023
Expenditure So far : 29.41 Crores

 

Development of Multi-Level Car Parking near Town Hall
Project Cost :  Rs12.02 Crores
Date of Tender :25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: Completed on 31-03-2023.
Expenditure So far : 11.23 CRORES.

 

Re-development of Fish Market
Project Cost : Rs.2.34 Crores
Date of Tender : 25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: work completed on 31-12-2022.
Expenditure So far : 2.33 CRORES

 

Re-development of Thennampalayam Weekly Shandy Market
Project Cost : Rs.12.81 Crores
Date of Tender : 28.02.2019
Date of Work Order: 03.06.2016
Present Stage of Work: work completed on 31-03-2022.
Expenditure So far : 12.48 CRORES

 

Re-development of Daily Market
Project Cost : Rs.31.88 Crores
Date of Tender :28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: Completed on 30-11-2023.
Expenditure So far : 30.70 CRORES

 

Re-development of Flower Market
Project Cost : Rs.4.80 Crores
Date of Tender : 28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work: Completed on 30-10-2022.
Expenditure So far : 4.68 CRORES

 

Roof Top Solar.
Project Cost : Rs.2.39 Crores
Date of Tender :14.12.2018

Date of Work Order : 25.02.2019
Present Stage of Work :Work Completed on 31.12.2020
Expenditure So far :2.39CRORES

 

Solar Power Plant 4.80MW
Project Cost : Rs.29.24 Crores
Date of Tender : 25.02.2019
Date of Work Order : 24.06.2019
Present Stage of Work :Work Completed on 28.02.2021
Expenditure So far : 27.51 CRORES

 

Solar Power Plant 2.00MW
Project Cost : Rs.13.00 Crores
Date of Tender : 24.07.2019
Date of Work Order : 03.10.2019
Present Stage of Work: Completed on 28.02.2021.
Expenditure So far :11.79 CRORES

 

Green Space Parks
Project Cost : Rs.3.95 Crores
Date of Work Order : 23.08.2018
Present Stage of Work: Completed on 31.10.2019.
Expenditure So far :3.88 CRORES

 

Water Supply Improvement Scheme AMRUT (2015-2016)
Project Cost : Rs.75.00 Crores
Date of Work Order : 16.07.2017
Present Stage of Work : Work Completed on 31.12.2020
Expenditure So far :75.00 CRORES

 

New Water Supply Scheme AMRUT (2017-2020)
Project Cost : Rs.114.15Crores
Date of Work Order : 04.02.2019 & 28.08.2019 01.,03.2019, 03.06.2019 & 28.06.2019
Present Stage of Work : Work Completed on 31.08.2022
Expenditure So far : 114.15 CRORES

 

UGSS (AMRUT)-2017-2020
Project Cost : Rs.64.84Crores
Date of Work Order : 04.02.2019, 28.07.2019 & 10.07.2019
Present Stage of Work : Work Completed on 31.08.2022
Expenditure So far : 64.84 Crores.

 

Internal Plumbing for Water Supply System (Package No.1)
Project Cost : Rs.15.47 Crores
Date of Tender : 27.12.2019
Date of Work Order : 20.04.2020
Present Stage of Work : (99 % Completed) 40956 Numbers of Connections completed out of 41226 Connections.

Probable Date of Completion: 30.06.2025

Expenditure so far: 13.47 crores

 

Internal Plumbing for Water Supply System (Package No.2)
Project Cost : Rs.14.90 Crores
Date of Tender : 27.12.2019
Date of Work Order : 12.03.2020
Present Stage of Work : (100 % Completed) 39698 Numbers of Connections completed out of 39698 Connections.

Date of Completion:31-10-2024.

Expenditure so far: 14.90 crores

 

Installation of  Signage’s
Project Cost : Rs. 6.37 Crores
Date of Tender : 10.12.2019
Date of Work Order : 30.03.2020

Date of Completion:28.02.2023.

Expenditure So far : 6.37 Crores.

 

Macro Drainage (Package-I)
Project Cost : Rs.15.72 Crores
Date of Tender : 17.09.2019
Date of Work Order : 13.03.2020
Present Stage of Work: work completed on 31-03-2022.
Expenditure so far: 15.72 crores

 

Macro Drainage (Package-II)
Project Cost : Rs.25.60 Crores
Date of Tender : 11.02.2020
Date of Work Order : 22.05.2020
Present Stage of Work: work completed on 31-01-2022.
Expenditure so far: 25.60 Crores

 

Smart Road (Phase-I)
Project Cost : Rs.88.24 Crores
Date of Tender :27.12.2019
Date of Work Order : 20.03.2020, 24.03.2020, 07.04.2020
Present Stage of Work: Completed on 28-02-2023.
Expenditure so far: 88.24 crores.

 

Smart Road (Phase-II)
Project Cost :  Rs. 59.69 Crores

Date of Tender :10.03.2020
Date of Work Order : 25.06.2020. & 15.07.2020
Present Stage of Work: Completed on 28-02-2023.
Expenditure so far: 59.69 crores

 

River front Development (Package-I)
Project Cost : Rs.32.87 Crores

Date of Tender : 24.12.2019
Date of Work Order : 09.06.2020
Present Stage of Work: 1) Baby Channel works 6.308 Km Completed out of 6.382 Km

Expenditure so far:30.68 crores. 

Date of Completion:31.05.2025

 

River front Development (Package-II)
Project Cost : Rs.31.70 Crores

Date of Tender : 24.12.2019
Date of Work Order : 26.03.2020
Present Stage of Work: 1) Baby Channel works 6.536 Km Completed out of 6.595 Km

Expenditure so far: 31.03 crores.

Probable Date of Completion:31.07.2025

 

River front Development (Package-III)
Project Cost : 29.15 Crores

Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work :

DBM Laying :-11.85 Km completed out of 12.48  Km. Balance 0.630Km

BC Laying :- 6.09 Km completed out of 12.48  Km. Balance 6.39 Km.
Street Light:-
360 Nos completed out of  448 Nos. Balance – 88 Nos.
Fencing work:-
11.66 Km completed out of 12.06 Km. Balance – 0.40 Km.

Jammanai Odai Bridge structure work  100 % completed.

Expenditure so far: 15.54 Crores

Probable Date of Completion:31.07.2025

 

River front Development (Package-IV)
Project Cost : 32.71 Crores

Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work:

1) Toe Wall 5.162 Km Completed out of 5.182 Km
2) Retaining wall (kerb) 4.416 Km Completed out of 4.476 Km
3) Bund Lining 5.112 Km Completed out of 5.182 Km
4) 4m Retaining wall with Counter Fort 0.830 Km Completed out of 0.830 Km
5) Jammanai Odai Bridge structure work 100% completed.

Expenditure so far: 32.20 crores.

Date of Completion:31.03.2025

 

River front Development (Package-V)
Project Cost : 29.89 Crores

Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work:

1) Toe Wall 5.974 Km Completed out of 5.974 Km
2) Retaining wall (Kerb) 5.974 Km Completed out of 5.974 Km
3) Bund Lining 5.974 Km Completed out of 5.974 Km
4) Retaining wall with Counter Fort 1.006 Km Completed out of 1.006 Km.
5) Culverts 16 Nos Completed out of 16 Nos.

Expenditure so far: 29.29Crores.

Date of Completion:31.03.2025

 

River front Development (Package-VI)
Project Cost : 9.40 Crores

Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work:-

  1. A) 2 MLD – Mullukaadu (Near Electric Crematorium)
    1) All components – Finishing work to be started.
    2) Mechanical All Component Erection work to be started.
    3) % of Completion – 85%
    B) 3 MLD – Alangadu
    1) All components – Finishing work to be started.
    2) Mechanical All Component Erection work to be started.
    3) % of Completion -85%

Expenditure so far: 7.44 Crore.

Probable Date of Completion:31.08.2025

 

LED STREET LIGHT (Package 1-New Light 3262 Nos & Package 2-Conversion Light-6604Nos)
Project Cost : Rs.15.60 Crores
Date of Tender : 31.01.2019
Date of Work Order : 02.08.2019
Present Stage of Work: Work Completed on 28.02.2021.
Expenditure so far: 15.60 CRORES

 

Solid Waste Management
Project Cost : Rs.22.19 Crores
Date of Tender : 04.02.2019, 11.02.2019, 31.01.2019.
Date of Work Order : 11.02.2019, 18.02.2019, 08.02.2019, 19.02.2019.
Present Stage of Work: Work Completed on 31.12.2020.
Expenditure so far: 21.47CRORES

 

Knowledge  Centre cum  Library

Project Cost : Rs.2.59 Crores
Date of Tender : 14.02.2022
Date of Work Order : 21.03.2022.
Present Stage of Work:  Work Completed on 28.02.2023.
Expenditure so far: 2.52 CRORES

 

Design and Construction of Sewage Treatment Plants of capacity 4MLD (2 Nos of each 2 MLD )  including 5 years of operation and maintenance on DBOT basis.

Project Cost : Rs.5.99 Crores
Date of Tender : 15.03.2022
Date of Work Order : 30.03.2022.
A) 2 MLD – Kasipalayam Road:-

All Components – Finishing, Mechanical, Electrical and Plumbing works are Completed.

EB Demand received, Payment under process.

 % of Completion –98 %

  1. B) 2 MLD – Chinnan Nagar :-

All Components –Finishing, Mechanical, Electrical and Plumbing works are Completed.

EB Demand paid, Transformer erection work completed. Awaiting for EB Meter.

 % of Completion –98 %

Probable Date of Completion:31.07.2025

Expenditure so far: 4.67 CRORES