Smart City Mission
- Re-development of Old Bus Stand in Tiruppur City Municipal Corporation.
Estimate Amount : Rs.36.50Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work : Main Building: Ground floor & First floor brick work and plastering completed. Terrace head room brick completed. Terrace screed completed. Ground floor granite flooring, Internal and external Putty work, Ground floor plumbing work, FRP door frame fixing work are in progress. OHT cover slab shuttering work Completed.
West Side: All Civil Works Completed Except Flooring Work. Further Planned for Plumbing & Electrical Works. South Side: All Civil Works Completed Except Toilet Area. North Side: All Civil Works Completed.Pavement for Bus Bays revised design is being finalized.
Expenditure So far :13.22Crores
- Construction of Multi Level Car Parking near Old Bus Stand in Tiruppur City Municipal Corporation.
Estimate Amount : Rs.18.17 Crores
Date of Tender : 13.12.2018
Date of Work Order : 23.01.2019
Present Stage of Work :Ground to terrace Floor plastering completed Terrace floor screed concrete completed. Ramp cover slab shuttering work completed. Terrace cool roof tiling work is in progress.
Expenditure So far :14.25Crores
- Construction of Convention Centre in Tiruppur City Municipal Corporation under Tiruppur Smart City Limited.
Estimate Amount :Rs.52.00Crores
Date of Tender :14.12.2018
Date of Work Order : 29.01.2019
Present Stage of Work : Retaining wall at basement floor completed. Basement floor column Completed. Basement floor ramp completed.Basement floor roof slab work 95% completed. Ground floor column – 60 % completed and work is in progress. Ground floor roof slab work is in progress.
Expenditure So far :8.63.Crores.
- Re-development of New Bus Stand.
Estimate Amount :Rs. 29.79 Crores
Date of Tender :11.02.2019
Date of Work Order : 22.02.2019
Present Stage of Work :Basement Floor : Roof Slab Completed. Ceiling Plastering Work completed..Ground Floor :West Bay Roof Slab Completed. East bay Roof slab completed.Ceiling Plastering Work is in Progress.
Shops.Parapet wall brick work in 50% completed Road and drain :South, West and North Side Road Work and Drain work are completed. All Bus bay concrete completed.
Expenditure So far :12.69.Crores.
- Development of Multi Level Car Parking near Town Hall in Tiruppur City Municipal Corporation.
Estimate Amount :Rs12.02 Crores
Date of Tender :25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work :Ground Floor to Second Floor Brick work completed. 1st and 2nd floor plastering work completed.Roof slab concrete completed up to Third Floor. Fourth Floor Roof Slab Work is in Progress3rd Floor brick Work and Plastering Work is in Progress
Expenditure So far :6.66Crores
- Re-development of Fish Market in Tiruppur City Municipal Corporation.
Estimate Amount : Rs.2.175 Crores
Date of Tender : 25.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work :Main Building : Kota stone laying work is completed. Entrance and exit area steps completed. Wall tile laying work is completed. Step tiles laying work completed. Electrical work is in progress(70%). White wash is completed . Plumbing work is completed
Fish Cleaning Building: Plumbing work is completed. Floor and wall tile is completed. White wash is completed.
Toilet Area: Wall and floor tiles is completed. White wash completed. Paver block laying completed.
Expenditure So far :1.63.Crores.
- Re-development of Thennampalayam Weekly Shandy Market in Tiruppur City Municipal Corporation
Estimate Amount : Rs.12.86 Crores
Date of Tender : 28.02.2019
Date of Work Order: 03.06.2016
Present Stage of Work :
Whole Sale Market Roof Truss work completed. Flooring concrete work completed. Works handed over.
Retail Market.All shops 128 nos. roof slab completed. Plastering work completed. Passage earth work and sectioning work completed. Flooring concrete completed and Paver block works completed. Poly Carbonate roof work completed. Painting work completed. Electrical works completed and handed over.
Onion Market Ground floor roof for all shops (18shops) hotel and toilet area is completed Ground floor brick work is in progress (50%).Plastering work is in progress (40%). First floor short column (1m) is in progress (80%). Parapet wall brick work is in progress (80%).
Expenditure So far :10.70.Crores.
- Re-development of Daily Market in Tiruppur City Municipal Corporation.
Estimate Amount : Rs.28.99 Crores
Date of Tender :28.02.2019
Date of Work Order : 03.06.2019
Present Stage of Work : Basement Raft for Foundation Completed (For all 4 Bays). RC Wall and Column works are 95% Completed for Bay 1,2,3,4. Basement Floor Entry & Exit Ramp Completed.Roof Beam Centering Work is in Progress.
Expenditure So far : 10.67.Crores.
- Re-development of Flower Market in Tiruppur City Municipal Corporation
Estimate Amount : Rs.4.47 Crores
Date of Tender : 28.02.2019
Date of Work Order : 03.06.2019Present Stage of Work :Roof slab for basement floor work completed. Ground floor roof completed. Ground floor to terrace floor staircase completed. Head room work is in progress(10%). Pedastal column in terrace floor is in progress (30%).
Expenditure So far : 2.91.Crores.
- Roof Top Solar.
Estimate Amount : Rs.2.34 Crores
Date of Tender :14.12.2018
Date of Work Order : 25.02.2019
Present Stage of Work :Work Completed
Expenditure So far : 1.57.Crores
- Solar Power Plant 4.80MW
Estimate Amount : Rs.27.16 Crores
Date of Tender : 25.02.2019
Date of Work Order : 24.06.2019
Present Stage of Work :Work Completed
Expenditure So far :25.74Crores
- Solar Power Plant 2.00MW
Estimate Amount : Rs.11.85 Crores
Date of Tender : 24.07.2019
Date of Work Order : 03.10.2019
Present Stage of Work :Work Completed.
Expenditure So far : 10.60Crore
13. Green Space Parks
Estimate Amount : Rs.3.86 Crores
Date of Work Order : 23.08.2018
Present Stage of Work : Work Completed. Trial run in progress.
Expenditure So far : 3.82Crores
14.Water Supply Improvement Scheme Amrut (2015-2016)
Estimate Amount : Rs.75 Crores
Date of Work Order : 16.07.2017
Present Stage of Work : 99.5% Works completed.
Expenditure So far :75.00
- New Water Supply Scheme AMRUT (2017-2020)
Estimate Amount : Rs.106.35 Crores
Date of Work Order : 04.02.2019 & 28.08.2019 01.,03.2019, 03.06.2019 & 28.06.2019
Present Stage of Work :60 % progress.
Expenditure So far : 106.35 Crores
- UGSS (AMRUT)-2017-2020
Estimate Amount : Rs.60.41 Crores
Date of Work Order : 04.02.2019, 28.07.2019 & 10.07.2019
Present Stage of Work :58% Completed.
Expenditure So far : 60.41Crores.
- Internal Plumbing for Water Supply System (Package No.1)
Estimate Amount : Rs.14.50 Crores
Date of Tender : 27.12.2019
Date of Work Order : 20.04.2020
Present Stage of Work :TotalNos of HSC -41,226 Nos HSC Laid -5132Connection completed (without Meter Fixing).
- Internal Plumbing for Water Supply System (Package No.2)
Estimate Amount : Rs.14.25 Crores
Date of Tender : 27.12.2019
Date of Work Order : 12.03.2020
Present Stage of Work :TotalNos of HSC –40756 Nos HSC Laid – 4167Connections completed . 2800 – Meters fixed)
Expenditure Bill is being prepare.
- Signage’s
Estimate Amount : Rs. 7.24 Crores
Date of Tender : 10.12.2019
Date of Work Order : 30.03.2020
Present Stage of Work :
Sl.No | Description | Quantity | Supplied/ Foundation laid | InstalledI |
1 | Gantry Signage – 2 Pole | 3 | 2 | 1 |
2 | Cantilever/Butterfly | 15 | 12 | 12 |
Cantilever – Single Pole | ||||
3 | city guide / map information | 5 | – | – |
4 | single arrow (road name) | 845 | – | – |
5 | Double Arrow (Road name) | 643 | – | – |
6 | Hazard Marker | 780 | 780 | – |
7 | Delineator | 885 | 885 | – |
8 | Median Marker | 832 | – | – |
9 | Cautionary /Mandatory | 935 | 320 | – |
Expenditure So far :1.14Crores.
20. Macro Drainage (Package-I)
Estimate Amount : Rs.15.61 Crores
Date of Tender : 17.09.2019
Date of Work Order : 13.03.2020
Present Stage of Work : Flood Alleviation Measure in ward No.8,9,12,24,25,47 & 48 in ABD area of Tiruppur Smart City Mission (Package-I) Total Length (in m) – 6605. Complete –5300m .Balance – 1305m.
Expenditure So far : 9.83.Crores.
- Macro Drainage (Package-II)
Estimate Amount : Rs.27.63 Crores
Date of Tender : 11.02.2020
Date of Work Order : 22.05.2020
Present Stage of Work : Flood Alleviation Measure in ward No.42,45,50 & 51 in ABD area of Tiruppur Smart City Mission (Package-II). Total Length (in m) – 11350. Complete –10380m.Balance – 970m.
Expenditure So far: 21.21.Crores.
- Smart Road (Phase-I)
Estimate Amount : Rs.88.22 Crores
Date of Tender :27.12.2019
Date of Work Order : 20.03.2020, 24.03.2020, 07.04.2020
Present Stage of Work :The work has to be carried out according to the UGSS and WSS pipe laying works simultaneously.
Sl. No |
Length of road in M | Length of Drain in M | Drain | Road | ||
So far Completed (in M) | Balance (in M) | So far Completed (in M) | Balance (in M) | |||
1 | 11833 | 16437 | 13896 | 2451 | 2944 | 8889 |
Expenditure So far :27.30Crores.
Smart Road (Phase-II)
Estimate Amount :Rs. 71.78 Crores
Date of Tender :10.03.2020
Date of Work Order : 25.06.2020. & 15.07.2020
Present Stage of Work :The work has to be carried out according to the UGSS and WSS pipe laying works simultaneously.
Sl. No |
Length of road in M | Length of Drain in M | Drain | Road | ||
So far Completed (in M) | Balance (in M) | So far Completed (in M) | Balance (in M) | |||
1 | 12249 | 11588 | 8806 | 2782 | 5936 | 6313 |
Expenditure So far :32.67Crores.
- . River front Development (Package-I)
Estimate Amount : Rs.30.50 Crores
Date of Tender : 24.12.2019
Date of Work Order : 09.06.2020
Present Stage of Work : Providing Baby Channel for Noyyal River (North Side) for collecting waste water from corporation outlets in Tiruppur City Municipal Corporation ( Package-1) Total Length (in m) – 6700. Completed –2600m.Balance – 4100m.
Expenditure So far :7.31Crores.
River front Development (Package-II)
Estimate Amount : Rs.29.00 Crores
Date of Tender : 24.12.2019
Date of Work Order : 26.03.2020
Present Stage of Work : Providing Baby Channel for Noyyal River (South Side) for collecting waste water from Corporation outlets (Package-2). Total Length (in m) – 6700m. Completed –3100m.Balance – 3600m.
Expenditure So far :12.77. Crores.
River front Development (Package-III)
Estimate Amount : 29.00
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work :Road Formation Preliminary works are in Progress.
River front Development (Package-IV)
Estimate Amount : 30.00
Date of Tender : 24.12.2019
Date of Work Order : 17.03.2020
Present Stage of Work : Providing Concrete lining for bund protection on North side of Noyyal river and construction of minor bridge across Jamunai odai & Construction of Food court with landscaping arrangements @ Anaikadu area on North bank of Noyyal River (Package-4) Total Length (in m) – 6700m. Complete – 420m.Balance – 6280m.
Expenditure So far :1.96Crores.
River front Development (Package-V)
Estimate Amount : 28.76
Date of Tender :24.12.2019
Date of Work Order : 26.05.2020
Present Stage of Work : Providing Concrete lining for bund protection on South side of Noyyal river and Construction of Ampthi theatre with park arrangements on North bank of Noyyal river near Maniyakarpalayam bridge in Tiruppur City Municipal Corporation ( Package-5). Total Length (in m) – 6700. Complete –3900.Balance – 2800.
Expenditure So far :11.68Crores.
- LED STREET LIGHT
Estimate Amount : Rs.16.92 Crores
Date of Tender : 31.01.2019
Date of Work Order : 02.08.2019
Present Stage of Work: Works Completed.
Expenditure So far :14.20.Crores.
- Solid Waste Management
Estimate Amount : Rs.22.19 Crores
Date of Tender : 04.02.2019, 11.02.2019, 31.01.2019.
Date of Work Order : 11.02.2019, 18.02.2019, 08.02.2019, 19.02.2019.
Present Stage of Work : Works Completed.
Expenditure So far :20.26.Crores.