அம்ருட் திட்டம்

AMRUT Scheme -2017-2020

New Water Supply Scheme -2017-2020

  1. Construction of Raw Water Intake well, Pump House with Surge Protection Tank, Supply and installation of Pump set and motors with all electrical works in Bhavani River bank at Mettupalayam and Supplying, Laying and Jointing of Pumping Main from Raw Water Intake  to  Water Treatment Plant near Annur including Pipe Carrying Bridges wherever necessary(Package– 1).

Estimate Amount: Rs.101.00 Crores

Date of Tender: 05.10.2018

Date of Work Order: 28.02.2019

Present Stage of Work  – PHYSICAL PROGRESS – 61%

Sl.No Name of the component Qty Current Status
I Head Works
Raw Water Intake Well 1 No. Roof slab laid. Further work is under progress.
River bank Protection works 150 m To be started
Connecting Pipe 1800 mm MS Pipe between Intake well to Sump 26 M X 2 Connecting pipe works completed
Construction of Dyke wall 65 m PWD has denied permission
Raw Water Sump cum pump house 1 No. One Compartment – East side coverslab      completed        and      other compartment roof slab centring work under progress.
2 Electro mechanical Items To be started
Supply, delivery and erection of raw water Vertical Turbine pump sets 6 Nos. Raw water Motors and pump sets – 6Nos Received
Electrical installations 1 No. To be started
3 Surge Protection Tank 1 No. Surge analysis being done
4 Raw water main
1422 mm dia x 12 mm MS Pipe 19.27 KM Supply Laid Hydraulic  Test
18.702 Km 17.00Km 15.612Km

Expenditure So far :84.16Crores

 

 

  1. Construction of Water treatment Plant of Capacity 196 MLD expandable to 270 MLD with  complete  SCADA system for the entire Project on Design Build, Operate and Transfer basis for new water supply scheme In Tiruppur City Municipal Corporation. Period of Completion 24 Months followed by 6 Months trail run and commissioning. (Package – 2).

Estimate Amount : Rs.82.94 Crores

Date of Tender :05.10.2018, 18.01.2019.

Date of Work Order : 28.06.2019

Present Stage of Work : PHYSICALPROGRESS -53%

 

Sl.No Name of the component Qty Current Status
1 Collection System(Km)
uPVC Pipes 200mm Dia 85.391Km 54.0 Km supplied and53.17KmLaid.
DWC Pipes 350mm Dia to 200mm Dia 13.405Km 5.835kmsuppliedand1.78kmlaid
CI Pipes LA class 1200mm Dia to350mm Dia 4.927Km 3.47 km Supplied and 1.337 Km Laid.
 2  Manholes (Nos) 4374Nos 3650NosCastedand3579erected.
3 House Service connection 17803No’s 4050No’s upto BoundaryCompleted.
4 Lifting Station 5 1.    Vanjipalayam Main Road(Zone8) completed, Pump room under progress2.    Bharani Nagar 4th Street (Zone13) Side wall1st Lift completed.

3.    TVK Nagar College Road(Zone 14)Sidewall1st Lift

completed

5 Sewage Pumping stations 2 1.  Kattabomman Nagar earth work 4Mtr depth completed.2.  Anaipalayam, Jayalalitha Nagar-

Earth work 5 Mtr completed.

 

Expenditure So far :57.99Crores.

 

  1. Supplying, Laying and Jointing Clear Water Gravity Main from Water Treatment Plant to OHTs  in Tiruppur Corporation including Pipe Carrying Bridges wherever necessary.(Package – 3).

Estimate Amount : Rs.356.00 Crores

Date of Tender :05.10.2018

Date of Work Order: 03.06.2019

Present Stage of Work: PHYSICAL PROGRESS–53 %

Name of the component Qty (km) Current Status
Clear water Gravity Transmission main
MS Pipes1829 mm Dia to 610 mm Dia

Total-78.820Km

Pipe Size Estimate (Km) Supply Laid Hydraulic  Test
1829 mm dia MS pipe 20.00 13.697Km 13.650Km 11.89Km
1626mm dia MS Pipe 18.210 13.688Km 13.325Km 12.643Km
1118mm dia MS Pipe 4.720 4.719Km 4.236Km 4.236Km
914mm dia MS Pipe 4.310 6.198Km 2.499Km 2.026Km
813mm dia MS Pipe 13.190 9.033Km
711mm dia MS Pipe 9.410
610mm dia MS pipe 8.980
Total 78.820 47.335 33.71 30.795
DI – K7 Pipes500 mm Dia to 150 mm Dia

Total-69.486Km

Pipe Size Estimate (Km) Supply Laid Hydraulic  Test
500mm dia DI Pipe 8.596 8.593Km 6.310Km 3.843Km
450mm dia DI Pipe 2.970 2.970Km 1.789Km
400mm dia DI Pipe 14.179 13.791Km 5.350Km 2.958Km
350mm dia DI Pipe 9.038 9.537Km 6.237Km 5.961Km
300mm dia DI Pipe 14.497 12.507Km 9.223Km 5.544Km
250mm dia DI Pipe 11.097 4.996Km 4.514Km 3.852Km
200mm dia DI Pipe 7.184 5.514Km 3.210Km 1.181Km
150mm dia DI Pipe 1.925 1.925Km 1.622Km 1.587Km
Total 69.486 59.833 38.255 24.926
Construction of Pipe Carrying Bridges 10 Site inspection under progress.
Road Restoration work (km) 74.153

Expenditure So far :230.08 Crores

 

  1. Construction of 12 Nos (W.S Zones- 2, 3, 4, 8, 22, 23, 26,28, 29, 30, 31, 32) Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zones-I & II area. (Package – 4).

Estimate Amount: Rs.185.00 Crores

Date of Tender   : 05.10.2018

Date of Work Order : 01.03.2019

Present Stage of Work :PHYSICAL PROGRESS-52%

S No. Location of Tank Capacity Present Stage of Work
1 Pandian Nagar 10.00LL 2nd brace under progress
2 MatheswaranKoil 1 20.00LL 3rd brace completed.
3 MatheswaranKoil 2 20.00LL 2nd brace column under progress
4 Thiru vi kanagar 10.00LL Roof slab completed.
5 G.N Garden 5.00LL Roof slab completed.
6 Sneha Nagar 10.00LL Footing under progress
7 NRK Puram 12.50LL Roof slab completed
8 Kumar Nagar 10.00 LL 1 No EB Pole to be shifted.
9 Kumar Nagar 20.00LL Existing 20LL GLSR being dismantled by TCMC.
10 Bharatiyar Complex 20.00LL Earth work completed.
11 Palayakadu 15.00LL 2nd brace completed.
12 Gate Thottam 5.0 LL Work to be started.

Expenditure So far :73.02Crores.

 

  1. Construction of 17 Nos (W.S Zones- 34, 35, 36, 37, 38, 39,40, 43, 44, 48, 50, 52, 54, 56, 57, 60, 70) of Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zone-III& IV area. (Package-5).

Estimate Amount : Rs.195.00 Crores

Date of Tender : 05.10.2018

Date of Work Order : 04.02.2019

Present Stage of Work :Physical Progress: 50 %

S No. Location of Tank Capacity Present Stage of Work
1 KovilVazhi 5.00LL Roof slab completed.
2 Kalipalayam 5.00LL GL Brace completed.
3 Chennimalaipalayam 5.00LL Roof slab completed.
4 Mahalakshmi Nagar (Vijayapuram) 7.50LL 2nd brace completed.
5 Karthik Nagar 7.50LL Court Case pending.
6 Krishna Nagar 7.50LL 2nd brace completed.
7 Noyyal Burial  Ground 10.00LL 2nd Brace work under progress.
8 Dharapuram Road OHT 10.00 LL Footing work under progress.
9 PudhuPalayam 12.50LL 2nd Brace work under progress.
10 Thiru Nagar 15.00LL floor slab work under progress.
11 Kaliappa Nagar 20.00LL 1st Brace completed.
12 Santhapettai 7.50LL Site to be cleared by TCMC.
13 TSK Maragathammal 7.50LL 1st brace work under progress.
14 Cattle Shed 10.00LL PCC completed.
15 State Bank colony 15.00LL PCC completed.

Expenditure So far :71.32Crores

 

 

Under Ground Sewerage  Scheme -2017-2020

 

  1. Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains  in  sewer  Zones  5,  6  and  7 (Package – 1).

Estimate Amount : Rs.256.00 Crores

Date of Tender  : 03.10.2018

Present Stage of Work :PHYSICALPROGRESS-18%

 

Sl.No. Name of the component Qty Current Status
1 Collection System(Km)
uPVCPipes200mmDia 216.381Km 100.026 km supplied and 73.452 Km Laid.
DWCPipes350mmDiato200mmDia 33.886Km 20.248 km Supplied and 3.677 km laid
CI Pipes LA class 1200mm Dia to350mmDia 20.135Km 8.5955 km supplied and 1.925 Km laid
 2  Manholes (Nos) 11380Nos 4671 Nos Casted and 3864 Nos erected
3 House Service connection 42008Nos 3688 No’s up to Boundary Completed.
4 Lifting Station 14 Work yet to be started.
5 Sewage Pumping stations 5 1. Nanjarayan Nagar-Earth work Completed.2. IndiraNagarSPS-7-Earthwork Under progress.
6 Pumping Mains CI Pipes 200 mm Dia&750mmDia 21.258Km 20.74km supplied 14.58km laid.

 

Expenditure So far :104.61Crores

 

 

 

  1. Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer zones 8, 13 and 14 and Expansion of the existing STP at Sarkar- periyapalayam and Rejuvenation of Existing SPS & MPS (Package – 2).

Estimate Amount : Rs.101.55 Crores

Date of Tender : 03.10.2018

Date of Work Order : 04.02.2019

Present Stage of Work :PHYSICAL PROGRESS -53%

 

Sl.No. Name of the component Qty Current Status
1 Collection System(Km)
uPVC Pipes 200mm Dia 85.391Km 54.0 Km supplied and53.17KmLaid.
DWC Pipes 350mm Dia to 200mm Dia 13.405Km 5.835kmsuppliedand1.78kmlaid
CI Pipes LA class 1200mm Dia to 350mm Dia 4.927Km 3.47 km Supplied and 1.337 Km Laid.
 2  Manholes (Nos) 4374Nos 3650NosCastedand3579erected.
3 House Service connection 17803No’s 4050No’s upto BoundaryCompleted.
4 Lifting Station 5 4.    Vanjipalayam Main Road(Zone8) completed, Pump room under progress5.    Bharani Nagar 4th Street (Zone13) Sidewall1st Lift completed.

6.    TVK Nagar College Road(Zone 14)Sidewall1st Lift completed

5 Sewage Pumping stations 2 3.  Kattabomman Nagar earth work 4Mtr depth completed.4.  Anaipalayam, Jayalalitha Nagar-

Earthwork 5Mtr completed.

 

Expenditure So far :44.37Crores

 

 

  1. Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 9, 15, 16 and 17 (Package – 3)

Estimate Amount : Rs.115.80 Crores

Date of Tender  : 03.10.2018

Date of Work Order : 04.02.2019

Present Stage of Work : PHYSICAL PROGRESS -55%

 

Sl.No. Name of the component Qty Current Status
1 Collection System(Km)
uPVCPipes200mmDia 132.672Km 76.00 Km supplied and 74.50 KmLaid.
DWC Pipes 350mm Dia to 200mmDia 19.948Km 10.589 Km Supplied, 3.923 KmLaid.
CI Pipes LA class 1200mm Dia to350mmDia 9.078Km 8.069 Km Supplied. 3.492 KmLaid.
 2  Manholes (Nos) 5758Nos 4950 Nos Casted and 4899 Nos.erected.
3 HouseServiceconnection 17032No’s 3650 Nos. upto Boundary Completed.
4 LiftingStation 8 1.      Civil Work Completed at Idumban Nagar (Zone 9.1)and Pump room roof slab completed.2.      Civil work completed at Vinayagapuram (Zone 15.1)and Pump room roof slab completed.

3.      Muthunagar – Civil Work completed and Pump room completed.

4.      Kulathupudur Main Road (Zone9.1)1stliftcompleted.

5.      Kullegoundanpudur cross street (Zone 9.1) Civil work completed.

6.      North Thottam (Zone 15.2)Civil work completed and Pump room roof slab completed

7.      Sugumar Nagar (Zone 17.1)Civil work completed and

Pump room roof slab completed

Expenditure So far :59.08Crores

  1. Design and Construction of Sewage Treatment Plant of capacity 36 MLD in Sarkarperiyapalayam and 20 MLD in Chinnandipalayam including 10 years of operation and maintenance on DBOT basis for UGSS in Tiruppur City Municipal Corporation (Package – 4)

Estimate Amount: Rs.61.72 Crores

Date of Tender: 03.10.2018

Date of Work Order: 28.02.2019

Present Stage of Work: At 36 MLD: 

SBR Side Wall: Inlet channel top slab shuttering work under progress.

 CCT: Structure Completed. Hydro test completed.

 Tonner Room: chlorine tonner & EOT crane erection completed.

 Gravity Thickener: Mechanical erection work completed. Hydro test Completed. Final Finishing work in progress.

 Air blower House: Mechanical erection work completed. Brick work is in progress.

 Sludge Sump with pump House: Structure Completed.

 Admin Building & MCC Building: Structure work completed. Cable trench raft concrete completed, wall shuttering work under progress.

 Centrifuge Building: Mechanical erection work completed. Internal Plastering work under progress

Expenditure So far: 54.91Crores