AMRUT Scheme -2017-2020
New Water Supply Scheme -2017-2020
- Construction of Raw Water Intake well, Pump House with Surge Protection Tank, Supply and installation of Pump set and motors with all electrical works in Bhavani River bank at Mettupalayam and Supplying, Laying and Jointing of Pumping Main from Raw Water Intake to Water Treatment Plant near Annur including Pipe Carrying Bridges wherever necessary(Package– 1).
Estimate Amount: Rs.101.00 Crores
Date of Tender: 05.10.2018
Date of Work Order: 28.02.2019
Present Stage of Work – PHYSICAL PROGRESS – 61%
Sl.No | Name of the component | Qty | Current Status | ||
I | Head Works | ||||
Raw Water Intake Well | 1 No. | Roof slab laid. Further work is under progress. | |||
River bank Protection works | 150 m | To be started | |||
Connecting Pipe 1800 mm MS Pipe between Intake well to Sump | 26 M X 2 | Connecting pipe works completed | |||
Construction of Dyke wall | 65 m | PWD has denied permission | |||
Raw Water Sump cum pump house | 1 No. | One Compartment – East side coverslab completed and other compartment roof slab centring work under progress. | |||
2 | Electro mechanical Items | To be started | |||
Supply, delivery and erection of raw water Vertical Turbine pump sets | 6 Nos. | Raw water Motors and pump sets – 6Nos Received | |||
Electrical installations | 1 No. | To be started | |||
3 | Surge Protection Tank | 1 No. | Surge analysis being done | ||
4 | Raw water main | ||||
1422 mm dia x 12 mm MS Pipe | 19.27 KM | Supply | Laid | Hydraulic Test | |
18.702 Km | 17.00Km | 15.612Km |
Expenditure So far :84.16Crores
- Construction of Water treatment Plant of Capacity 196 MLD expandable to 270 MLD with complete SCADA system for the entire Project on Design Build, Operate and Transfer basis for new water supply scheme In Tiruppur City Municipal Corporation. Period of Completion 24 Months followed by 6 Months trail run and commissioning. (Package – 2).
Estimate Amount : Rs.82.94 Crores
Date of Tender :05.10.2018, 18.01.2019.
Date of Work Order : 28.06.2019
Present Stage of Work : PHYSICALPROGRESS -53%
Sl.No | Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVC Pipes 200mm Dia | 85.391Km | 54.0 Km supplied and53.17KmLaid. | |
DWC Pipes 350mm Dia to 200mm Dia | 13.405Km | 5.835kmsuppliedand1.78kmlaid | |
CI Pipes LA class 1200mm Dia to350mm Dia | 4.927Km | 3.47 km Supplied and 1.337 Km Laid. | |
2 | Manholes (Nos) | 4374Nos | 3650NosCastedand3579erected. |
3 | House Service connection | 17803No’s | 4050No’s upto BoundaryCompleted. |
4 | Lifting Station | 5 | 1. Vanjipalayam Main Road(Zone8) completed, Pump room under progress2. Bharani Nagar 4th Street (Zone13) Side wall1st Lift completed.
3. TVK Nagar College Road(Zone 14)Sidewall1st Lift completed |
5 | Sewage Pumping stations | 2 | 1. Kattabomman Nagar earth work 4Mtr depth completed.2. Anaipalayam, Jayalalitha Nagar-
Earth work 5 Mtr completed. |
Expenditure So far :57.99Crores.
- Supplying, Laying and Jointing Clear Water Gravity Main from Water Treatment Plant to OHTs in Tiruppur Corporation including Pipe Carrying Bridges wherever necessary.(Package – 3).
Estimate Amount : Rs.356.00 Crores
Date of Tender :05.10.2018
Date of Work Order: 03.06.2019
Present Stage of Work: PHYSICAL PROGRESS–53 %
Name of the component | Qty (km) | Current Status | |||
Clear water Gravity Transmission main | |||||
MS Pipes1829 mm Dia to 610 mm Dia
Total-78.820Km |
Pipe Size | Estimate (Km) | Supply | Laid | Hydraulic Test |
1829 mm dia MS pipe | 20.00 | 13.697Km | 13.650Km | 11.89Km | |
1626mm dia MS Pipe | 18.210 | 13.688Km | 13.325Km | 12.643Km | |
1118mm dia MS Pipe | 4.720 | 4.719Km | 4.236Km | 4.236Km | |
914mm dia MS Pipe | 4.310 | 6.198Km | 2.499Km | 2.026Km | |
813mm dia MS Pipe | 13.190 | 9.033Km | – | – | |
711mm dia MS Pipe | 9.410 | – | – | – | |
610mm dia MS pipe | 8.980 | – | – | – | |
Total | 78.820 | 47.335 | 33.71 | 30.795 | |
DI – K7 Pipes500 mm Dia to 150 mm Dia
Total-69.486Km |
Pipe Size | Estimate (Km) | Supply | Laid | Hydraulic Test |
500mm dia DI Pipe | 8.596 | 8.593Km | 6.310Km | 3.843Km | |
450mm dia DI Pipe | 2.970 | 2.970Km | 1.789Km | – | |
400mm dia DI Pipe | 14.179 | 13.791Km | 5.350Km | 2.958Km | |
350mm dia DI Pipe | 9.038 | 9.537Km | 6.237Km | 5.961Km | |
300mm dia DI Pipe | 14.497 | 12.507Km | 9.223Km | 5.544Km | |
250mm dia DI Pipe | 11.097 | 4.996Km | 4.514Km | 3.852Km | |
200mm dia DI Pipe | 7.184 | 5.514Km | 3.210Km | 1.181Km | |
150mm dia DI Pipe | 1.925 | 1.925Km | 1.622Km | 1.587Km | |
Total | 69.486 | 59.833 | 38.255 | 24.926 | |
Construction of Pipe Carrying Bridges | 10 | Site inspection under progress. | |||
Road Restoration work (km) | 74.153 | – |
Expenditure So far :230.08 Crores
- Construction of 12 Nos (W.S Zones- 2, 3, 4, 8, 22, 23, 26,28, 29, 30, 31, 32) Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zones-I & II area. (Package – 4).
Estimate Amount: Rs.185.00 Crores
Date of Tender : 05.10.2018
Date of Work Order : 01.03.2019
Present Stage of Work :PHYSICAL PROGRESS-52%
S No. | Location of Tank | Capacity | Present Stage of Work |
1 | Pandian Nagar | 10.00LL | 2nd brace under progress |
2 | MatheswaranKoil 1 | 20.00LL | 3rd brace completed. |
3 | MatheswaranKoil 2 | 20.00LL | 2nd brace column under progress |
4 | Thiru vi kanagar | 10.00LL | Roof slab completed. |
5 | G.N Garden | 5.00LL | Roof slab completed. |
6 | Sneha Nagar | 10.00LL | Footing under progress |
7 | NRK Puram | 12.50LL | Roof slab completed |
8 | Kumar Nagar | 10.00 LL | 1 No EB Pole to be shifted. |
9 | Kumar Nagar | 20.00LL | Existing 20LL GLSR being dismantled by TCMC. |
10 | Bharatiyar Complex | 20.00LL | Earth work completed. |
11 | Palayakadu | 15.00LL | 2nd brace completed. |
12 | Gate Thottam | 5.0 LL | Work to be started. |
Expenditure So far :73.02Crores.
- Construction of 17 Nos (W.S Zones- 34, 35, 36, 37, 38, 39,40, 43, 44, 48, 50, 52, 54, 56, 57, 60, 70) of Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zone-III& IV area. (Package-5).
Estimate Amount : Rs.195.00 Crores
Date of Tender : 05.10.2018
Date of Work Order : 04.02.2019
Present Stage of Work :Physical Progress: 50 %
S No. | Location of Tank | Capacity | Present Stage of Work |
1 | KovilVazhi | 5.00LL | Roof slab completed. |
2 | Kalipalayam | 5.00LL | GL Brace completed. |
3 | Chennimalaipalayam | 5.00LL | Roof slab completed. |
4 | Mahalakshmi Nagar (Vijayapuram) | 7.50LL | 2nd brace completed. |
5 | Karthik Nagar | 7.50LL | Court Case pending. |
6 | Krishna Nagar | 7.50LL | 2nd brace completed. |
7 | Noyyal Burial Ground | 10.00LL | 2nd Brace work under progress. |
8 | Dharapuram Road OHT | 10.00 LL | Footing work under progress. |
9 | PudhuPalayam | 12.50LL | 2nd Brace work under progress. |
10 | Thiru Nagar | 15.00LL | floor slab work under progress. |
11 | Kaliappa Nagar | 20.00LL | 1st Brace completed. |
12 | Santhapettai | 7.50LL | Site to be cleared by TCMC. |
13 | TSK Maragathammal | 7.50LL | 1st brace work under progress. |
14 | Cattle Shed | 10.00LL | PCC completed. |
15 | State Bank colony | 15.00LL | PCC completed. |
Expenditure So far :71.32Crores
Under Ground Sewerage Scheme -2017-2020
- Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 5, 6 and 7 (Package – 1).
Estimate Amount : Rs.256.00 Crores
Date of Tender : 03.10.2018
Present Stage of Work :PHYSICALPROGRESS-18%
Sl.No. | Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVCPipes200mmDia | 216.381Km | 100.026 km supplied and 73.452 Km Laid. | |
DWCPipes350mmDiato200mmDia | 33.886Km | 20.248 km Supplied and 3.677 km laid | |
CI Pipes LA class 1200mm Dia to350mmDia | 20.135Km | 8.5955 km supplied and 1.925 Km laid | |
2 | Manholes (Nos) | 11380Nos | 4671 Nos Casted and 3864 Nos erected |
3 | House Service connection | 42008Nos | 3688 No’s up to Boundary Completed. |
4 | Lifting Station | 14 | Work yet to be started. |
5 | Sewage Pumping stations | 5 | 1. Nanjarayan Nagar-Earth work Completed.2. IndiraNagarSPS-7-Earthwork Under progress. |
6 | Pumping Mains CI Pipes 200 mm Dia&750mmDia | 21.258Km | 20.74km supplied 14.58km laid. |
Expenditure So far :104.61Crores
- Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer zones 8, 13 and 14 and Expansion of the existing STP at Sarkar- periyapalayam and Rejuvenation of Existing SPS & MPS (Package – 2).
Estimate Amount : Rs.101.55 Crores
Date of Tender : 03.10.2018
Date of Work Order : 04.02.2019
Present Stage of Work :PHYSICAL PROGRESS -53%
Sl.No. | Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVC Pipes 200mm Dia | 85.391Km | 54.0 Km supplied and53.17KmLaid. | |
DWC Pipes 350mm Dia to 200mm Dia | 13.405Km | 5.835kmsuppliedand1.78kmlaid | |
CI Pipes LA class 1200mm Dia to 350mm Dia | 4.927Km | 3.47 km Supplied and 1.337 Km Laid. | |
2 | Manholes (Nos) | 4374Nos | 3650NosCastedand3579erected. |
3 | House Service connection | 17803No’s | 4050No’s upto BoundaryCompleted. |
4 | Lifting Station | 5 | 4. Vanjipalayam Main Road(Zone8) completed, Pump room under progress5. Bharani Nagar 4th Street (Zone13) Sidewall1st Lift completed.
6. TVK Nagar College Road(Zone 14)Sidewall1st Lift completed |
5 | Sewage Pumping stations | 2 | 3. Kattabomman Nagar earth work 4Mtr depth completed.4. Anaipalayam, Jayalalitha Nagar-
Earthwork 5Mtr completed. |
Expenditure So far :44.37Crores
- Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 9, 15, 16 and 17 (Package – 3)
Estimate Amount : Rs.115.80 Crores
Date of Tender : 03.10.2018
Date of Work Order : 04.02.2019
Present Stage of Work : PHYSICAL PROGRESS -55%
Sl.No. | Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVCPipes200mmDia | 132.672Km | 76.00 Km supplied and 74.50 KmLaid. | |
DWC Pipes 350mm Dia to 200mmDia | 19.948Km | 10.589 Km Supplied, 3.923 KmLaid. | |
CI Pipes LA class 1200mm Dia to350mmDia | 9.078Km | 8.069 Km Supplied. 3.492 KmLaid. | |
2 | Manholes (Nos) | 5758Nos | 4950 Nos Casted and 4899 Nos.erected. |
3 | HouseServiceconnection | 17032No’s | 3650 Nos. upto Boundary Completed. |
4 | LiftingStation | 8 | 1. Civil Work Completed at Idumban Nagar (Zone 9.1)and Pump room roof slab completed.2. Civil work completed at Vinayagapuram (Zone 15.1)and Pump room roof slab completed.
3. Muthunagar – Civil Work completed and Pump room completed. 4. Kulathupudur Main Road (Zone9.1)1stliftcompleted. 5. Kullegoundanpudur cross street (Zone 9.1) Civil work completed. 6. North Thottam (Zone 15.2)Civil work completed and Pump room roof slab completed 7. Sugumar Nagar (Zone 17.1)Civil work completed and Pump room roof slab completed |
Expenditure So far :59.08Crores
- Design and Construction of Sewage Treatment Plant of capacity 36 MLD in Sarkarperiyapalayam and 20 MLD in Chinnandipalayam including 10 years of operation and maintenance on DBOT basis for UGSS in Tiruppur City Municipal Corporation (Package – 4)
Estimate Amount: Rs.61.72 Crores
Date of Tender: 03.10.2018
Date of Work Order: 28.02.2019
Present Stage of Work: At 36 MLD:
SBR Side Wall: Inlet channel top slab shuttering work under progress.
CCT: Structure Completed. Hydro test completed.
Tonner Room: chlorine tonner & EOT crane erection completed.
Gravity Thickener: Mechanical erection work completed. Hydro test Completed. Final Finishing work in progress.
Air blower House: Mechanical erection work completed. Brick work is in progress.
Sludge Sump with pump House: Structure Completed.
Admin Building & MCC Building: Structure work completed. Cable trench raft concrete completed, wall shuttering work under progress.
Centrifuge Building: Mechanical erection work completed. Internal Plastering work under progress
Expenditure So far: 54.91Crores