AMRUT

AMRUT Scheme

New Water Supply Scheme

1.Construction of Raw Water Intake well, Pump House with Surge Protection Tank, Supply and installation of Pump set and motors with all electrical works in Bhavani River bank at Mettupalayam and Supplying, Laying and Jointing of Pumping Main from Raw Water Intake  to  Water Treatment Plant near Annur including Pipe Carrying Bridges wherever necessary(Package– 1).

Project Cost : Rs.132.36.00 Crores

Date of Tender: 05.10.2018

Date of Work Order: 28.02.2019

Contract Value: 109.17 Cr

Contractor: M/S Keyem Infra Projects Limited, Chennai.

Present Stage of Work – 100%

Date of completion: 27.02.2023

Expenditure So far : 130.96 Crores

 

Sl.No. Name of the component Qty Current Status
I Head Works
Raw Water Intake Well 1 No. Completed.
River bank Protection works 150 m Completed.
Connecting Pipe 1800 mm MS Pipe

between Intake well to Sump

26 M X 2 Completed
Raw Water Sump cum pumphouse 1 No. Completed.
2 Electro mechanical Items Completed
Supply, delivery and erection of raw water Vertical Turbine pump sets 6 Nos. Completed
Electrical installations 1 No. completed
3 Surge Protection Tank 1 No. completed.
4 Flow Meter 2 No. completed.
5 Raw water main Completed
1422 mm dia x 12 mm MS Pipe 19.27 KM Revised Qty (Km) Supply Qty (Km) Laid Qty (Km)
19.82 km 19.97 Km 19.83Km
Trail Run Pumping from Headworks to WTP 2330.71 ML Total Raw water Pumped in 1st Apr to 31st May 2025.

 

52769.35 ML Total Raw water pumped from 01.01.2023 to 31.05.2025

  1. Construction of Water treatment Plant of Capacity 196 MLD expandable to 270 MLD with  complete  SCADA system for the entire Project on Design Build, Operate and Transfer basis for new water supply scheme In Tiruppur City Municipal Corporation. Period of Completion 24 Months followed by 6 Months trail run and commissioning.(Package – 2).

 

Project Cost : Rs.95.02 Crores

Date of Tender :05.10.2018, 18.01.2019.

Date of Work Order : 28.06.2019

Contract Value: Rs.85.44 Cr.

Contractor: M/S Eco Protection Engineers Pvt Ltd.

Present Stage of Work :100 % Completed

Date of completion: 30.09.2022

Expenditure So far :94.25Crores.

 

 

 

Sl.No. Name of the component Qty Current Status
1 Basic Engineering package 1 No. Approved
2 Hydraulic design 1 No. Approved
3 Structural  design  for    Clear                    Water reservoir 1 No. Approved.
4 Clear Water Reservoir 1 No. Completed.
5 Flocculator & Inclined plate settler 1No. Completed.
6 Sludge Conditioner tank 1No. Completed.
7 Sludge Thickener Unit 1No. Completed.
8 Chlorination Building 1No. Completed.
9 MCC Room 1No. Completed.
10 Chemical House 1 No Completed.
11 Filter House 1 No Completed.
12 Back wash water Recirculation sump 1 No Completed.
13 Aerator 1 No Completed
14 Raw Water Channel 1 No Completed
15 Back Wash Water Pump Room 1 No Completed
16 Administration Building 1 No Completed
17 Centrifuge Building 1 No Completed
18 Internal Drainage, Compound wall and Road formation 1 No Completed
19 Clear Water Discharge from WTP (Trail Run) 2284.26 ML Total Clear water Discharged from WTP in 1st Apr to 31st May 2025.

51847.39 ML Total Clear water Discharged from 01.01.2023 to 31.05.2025

 

 

 

 

 

 

 

 

 

 

3.Supplying, Laying and Jointing Clear Water Gravity Main from Water Treatment Plant to OHTs  in Tiruppur Corporation including Pipe Carrying Bridges wherever necessary.(Package – 3).

Project Cost : Rs.405.00 Crores

Date of Tender :05.10.2018

Date of Work Order: 03.06.2019

Contract Value: Rs.383.82 Cr

Contractor: M/s. Koya & Company Construction Limited,

Present Stage of Work: –100 % Completed ,

Date of completion: 15.11.2022

Expenditure So far :405.00 Crores

 

Name of the component Qty (km) Current Status
Clear water Gravity Transmission main
Pipe Size Estimate Qty Revised Qty Supply Laid
(Km) (Km) (Km) (Km)
1829 mm dia MS pipe 20.02 20.018 20.018 20.00
1626mm dia MS Pipe 18.210 17.180 17.180 17.180
1118mm dia MS Pipe 4.720 4.720 4.720 4.706
MS Pipes 914mm dia MS Pipe 4.310 7.857 7.857 7.855
813mm dia MS Pipe 13.190 9.526 9.526 9.489
1829 mm Dia to 610 mm
Dia
711mm dia MS Pipe 9.410 9.367 9.367 9.366
Total-78.840Km 610mm dia MS pipe 8.980 8.910 8.910 8.870
Total 78.84 77.578 77.578 77.466
Pipe Size Estimate Qty Revised Qty Supply Laid
(Km) (Km) (Km) (Km)
500mm dia DI Pipe 8.596 10.347 10.347 10.347
450mm dia DI Pipe 2.970 2.970 2.970 2.970
DI – K7 Pipes 400mm dia DI Pipe 14.179 13.791 13.791 13.491
500 mm Dia to 150 mm
350mm dia DI Pipe 9.966 9.966 9.966 9.946
Dia
300mm dia DI Pipe 15.119 15.119 15.119 15.087
Total-71.036Km
250mm dia DI Pipe 11.097 6.993 6.993 6.949
200mm dia DI Pipe 7.184 6.064 6.064 6.064
150mm dia DI Pipe 1.925 1.925 1.925 1.888
Total 71.036 67.175 67.175 66.742
Grand Total 149.876 144.753 144.753 144.208
Construction of Pipe Carrying Bridges 10/9 9 No. completed.
Existing OHT Inlet pipe connection Water filling Existing OHTs- 39 nos. Water filling New OHTs- 25 Nos.

04   Nos New OHTs – Trail run completed upto ground level.

 

 

  1. Construction of 12 Nos (W.S Zones- 2, 3, 4, 8, 22, 23, 26,28, 29, 30, 31, 32) Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zones-I & II area. (Package – 4).

 Project Cost : Rs.203.06 Crores

Date of Tender   : 05.10.2018

Date of Work Order : 01.03.2019

Contract Value: Rs. 194.74 Cr.

Contractor: M/S R P P Infra Projects Ltd JV with M/S Annai Infra Developers limited

Present Stage of Work :-97% Work Completed.

Probable Date of completion: 31.07.2025.

Expenditure So far :177.54 Crores.

 

S No. Location of Tank Capacity Present Stage of Work Current Status
1 Pandian Nagar 10.00LL Completed. Commissioned and supply effected.
2 Matheswaran Koil 1 20.00LL Completed. Trail run work under progress. Water tightness test to be done
3 Matheswaran Koil 2 20.00LL Completed. Water tightness work under progress & Trail run under

progress

4 Thiru vee ka nagar 10.00LL Completed. Trail run work under progress
5 G.N Garden 5.00LL Completed. Commissioned and supply effected.
6 Sneha Nagar 10.00LL Completed. Trail run work under progress
7 NRK Puram 12.50LL Completed. Trail run work under progress
8 Kumar Nagar 10.00 LL Completed. Finishing work under progress.
9 Kumar Nagar 20.00LL Completed. Finishing work under progress.
10 Bharatiyar Complex 20.00LL Completed. DMA Zone (24×7) Water

tightness work to be done.

11 Palayakadu 15.00LL Completed Trail run work under progress
12 Gate Thottam 5.0 LL Completed. Trail run under progress.

 

Sl.No. Name of the component Qty   D-System Current Status
13  

 

 

HDPE Pipe 225mm dia to 110mm dia

 

 

 

 

330.788 /

497.556Km

Pipe Size Estimate (Km) Revised (Km) Supply (Km) Laid (Km) Balance (Km)
110mm HDPE 317.408 485.636 487.500 483.902 1.735
160mm HDPE 10.008 10.029 10.200 10.029
225mm HDPE 3.372 1.617 2.004 1.617
Total 330.788 497.282 499.704 495.548 1.735

 

Sl.No. Name of the component Qty D-System Current Status
DI – K7 Pipes 700mm dia to 200mm dia 171.869 /

117.244Km

Pipe

Size

Estimate

(Km)

Revised

(Km)

Supply

(Km)

Laid

(Km)

Balance

(Km)

200mm DI 37.745 24.574 29.581 24.247 0.326
250mm

DI

6.043 6.040 6.043 6.040 0
300mm DI 51.733 30.737 33.365 30.470 0.267
350mm

DI

9.452 7.907 8.5085 7.852 0.055
400mm DI 28.611 19.954 25.126 19.799 0.155
450mm

DI

0.104 0.095 0.104 0.095 0
500mm DI 25.457 17.517 17.964 16.730 0.787
600mm DI 12.558 11.633 11.6385 10.887 0.746
700mm DI 0.166 0
Total 171.869 118.459 132.330 116.12 2.336
  502.657/614.80 Grand Total 502.657 615.741 632.034 611.548 4.071
14 Chlorination Plants 12Nos 12 Nos of Shed work completed.
15 House Service Connections 57553/

 42123 Nos

42123 No’s completed.

HSC Water Meter 40000 No’s Completed.

 

5.Construction of 17 Nos (W.S Zones- 34, 35, 36, 37, 38, 39,40, 43, 44, 48, 50, 52, 54, 56, 57, 60, 70) of Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zone-III& IV area. (Package-5).

Project Cost : Rs.184.37 Crores

Date of Tender : 05.10.2018

Date of Work Order : 04.02.2019

Contract Value: Rs. 207.15 Cr.

Contractor: M/S Annai Infra Developers limited

Present Stage of Work :-95% Work Completed.

Probable Date of completion: 31.07.2025.

Expenditure So far :142.41 Crores.

 

S No. Location of Tank Capacity Present Stage of Work Current Status
1 Kovil Vazhi 5.00LL Completed. Water supplied through the existing & new line.
2 Kalipalayam 5.00LL Completed. Trail Run under progress.
3 Chennimalaipalayam 5.00LL Completed. Water supplied through the new pipe line.
4 Mahalakshmi Nagar (Vijayapuram) 7.50LL Completed. Water supplied through the new pipe line.
5 Karthik Nagar 7.50LL Completed. Trail Run under progress.
6 Krishna Nagar 7.50LL Completed. Trail Run under progress.
7 Noyyal Burial Ground 10.00LL Completed. Trail Run under progress.
8 Dharapuram Road OHT 10.00 LL Completed. DMA Zone (24×7)
9 Pudhu Palayam 12.50LL Completed. Trail Run under progress.
10 Thiru Nagar 15.00LL Completed. Trail Run under progress.
11 Kaliappa Nagar 20.00LL Completed. Trail Run to be started.
12 Santhapettai 7.50LL Completed. Water tightness to be started.
13 TSK Maragathammal 7.50LL Completed. Trial run under progress.
14 Cattle Shed 10.00LL Completed. Trail Run under progress.
15 State Bank colony 15.00LL Completed. Valve chamber work to be started
16 Masaniyamman Koil 15.00LL Completed. Valve chamber work under progress.
17 Andipalayam (SR Nagar) 12.50LL Completed. Inter connection work under progress.

 

 

 

Sl.No. Name of the component Qty Current Status
18 Distribution System Km
 

 

HDPE Pipe 225mm dia to 110mm dia

 

 

344.184/435.88

Km

Pipe Size Estimate (Km) Revised (Km) Supply (Km) Laid (Km) Balance (Km)
110mm HDPE 289.136 371.96 366.45 365.01 6.95
160mm HDPE 51.676 61.80 58.40 56.83 4.96
225mm HDPE 3.372 2.12 3.37 2.12
Total 344.184 435.88 428.22 423.97 11.91
 

 

 

 

 

 

 

 

DI – K7 Pipes 700mm dia to 200mm dia

 

 

 

 

 

 

 

 

215.588/140.70

km

Pipe Size Estimate (Km) Revised (Km) Supply (Km) Laid (Km) Balance (Km)
200mm DI 74.501 52.21 51.27 48.44 3.77
250mm DI 15.795 14.46 13.81 13.80 0.65
300mm DI 45.790 23.47 24.45 23.40 0.07
350mm DI 9.594 7.59 8.00 7.59
400mm DI 38.627 23.22 23.89 22.22 1.00
450mm DI 2.895 2.82 2.75 2.69 0.12
500mm DI 27.410 16.92 17.70 15.71 1.21
600mm DI 0.810
700mm DI 0.166
Total 215.588 140.70 141.87 133.86 6.83
Grand Total 559.772/

576.59 Km

  559.772 576.59 570.10 557.84 18.75
19 Chlorination Plants 17 Nos 17 Nos Shed work completed.
20 House Service Connections 59883/25020 24566 No’s Completed.

HSC Water Meter 13228 No’s Completed.

 

  1. 6. Transforming the existing intermittent water supply to continuous 24×7 water supply distribution system for the water zone 30 & 50 in Tiruppur City Municipal Corporation – Period of Completion 12 months followed by 3 months Trial Run and Commissioning. (Package-6)

Project Cost : Rs. 53.57 Cr

Date of Tender : 18.01.2023

Date of Work Order : 07.07.2023

Contract Value: Rs.37.29 Cr. 

Contractor: M/S Eco Protection Engineers Pvt Ltd. 

Date of agreement: 07.07.2023 

Probable Date of completion: 30.09.2025.

Present Stage of Work : 80 % Work Completed.

Expenditure So far :34.69 Crores

 

Sl.N

o.

Name of the component Qty Current Status
 

 

 

 

1

 

 

 

HDPE Pipe 225mm Dia to 110mm Dia

 

 

 

 

56.991

Km

Pipe Size Estimate (Km) Revised (Km) Supply (Km) Laid (Km) Balance ( km) Hydra ulic Tested in

(Km)

110mm HDPE 49.265 54.766 50.86 50.86 3.906 4.862
160mm HDPE 5.056 5.32 5.32 5.32 0.314
225mm HDPE 2.67 2.67 2.67 2.67
Total 56.991 62.75 58.85 58.85 3.906 5.176
 

 

 

 

 

2

 

 

 

 

 

DI pipe 300 mm Dia to 500 mm Dia

 

 

 

 

 

3.997 Km

200 mm DI 0.397 0.397 0.396 0.391 0.06
250 mm DI 0.538 0.640 0.640 0.620 0.02
300 mm DI 0.633 0.649 0.649 0.649
350 mm DI 1.670 1.683 1.683 1.651 0.082 0.684
450 mm DI 0.596 0.605 0.605 0.605
500 mm DI 0.163 0.240 0.240 0.240
Total 3.997 4.21 4.21 4.156 0.054 0.684
Grand Total 60.988

Km

60.988 66.96 63.06 63.006 3.96 5.86
3 House service connection 8400 Nos 9887 8630 Nos completed
4 AMR water meter 8400 Nos 9887 8390 Nos completed.

 

 

S.NO NAME OF THE COMPONENT QTY CURRENT STATUS
NO OF DMA ZONES – 10
1 DMA Entry point – Inside DMA:
a) Electromagnetic flow meter. 10 Nos 9 Nos completed.
b) Sluice valve / for isolation & scouring. 75 Nos 61 Nos completed
c) Pressure Transmitter & solar PLC control panel with data logger. 20 Nos 18 Nos completed.
d) Water Quality sensor for monitoring chlorine level, PH, conductivity with control panel. 20 Nos 14 Nos completed.
e) Pressure reducing valve (PRV) 4 Nos
f) PLC control panel with ups with DMA entry & inside DMA. 38 Nos 38 completed.
G Flow Control Valve 12 Nos P.O placed.
2 ESR OUTLET – 2:
a) Electromagnetic flow meter. 2 Nos Completed
b) Sluice valve / for isolation control. 4 Nos Completed
c) Pressure Transmitter. 2 Nos Completed
d) Water Quality sensor for monitoring chlorine level, PH, conductivity with control panel.  

2 Nos

Completed
e) PLC control panel with ups. 2 Nos Completed
3 Monitoring centre infrastructure
a) Split Air conditioner 1 Nos Completed
b) PC hardware 2 Nos Completed
c) Software-pc operating system. 2 Nos Completed
d) PC rack panel 1 Nos Completed
e) Laser projector with high brightness screen. 1 Nos Commissioning completed
f) LED – TV – 40-inch display unit 1 Nos Commissioning completed
4 Information retrieval system
a) PC – client 2 Nos  

 

b) PC- application software 2 Nos
5 Mobile hand-held display unit
a) Android application software 3 Nos

 

S.no Description Zone Pipeline status SEMI status Hsc status Amr water meter status Remarks
1 DMA -1 Z-50 &

w- 42,43,45

completed completed completed completed Trial run under progress
2 DMA -2 completed completed completed completed
3 DMA – 3 completed completed completed completed
4 DMA -4  

 

Z-30 &

w- 24,25,26,

9, 47

completed completed completed completed Trial run under progress
5 DMA -5 completed completed completed completed
6 DMA -6 completed completed completed completed
7 DMA -7 completed completed completed completed  

valve erection under progress completed as on 30-05-25

8 DMA -8 completed completed completed completed
9 DMA – 9 completed completed completed completed
10 DMA -10 completed completed completed completed
11 OHT compound
wall
Head works Under supplemental
compound wall, item, work started,
12 Road works,

street lights and

Materials Procument

in progress.

land scapping
works

 

 

 

AMRUT-2017-20

 

 Under Ground Sewerage  Scheme

 1.Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains  in  sewer  Zones  5,  6  and  7 (Package – 1).

Project Cost : Rs.381.22 Crores

Date of Tender : 05.10.2018

Date of Work Order : 10.07.2020

Contract Value: Rs.320.22 cr.

Contractor: M/S Eco Protection Engineers Pvt Ltd. 

Date of agreement: 10.07.2020

Probable Date of Completion: 31.0.2025

Present Stage of Work : 98% Work Completed.

Expenditure So far : 346.95Crores

 

Sl.

No.

Name of the component Agreement/Revised Qty Current Status
1 Collection System (Km) Estimated Qty Revised Qty Supply Qty Laid Qty Balance Qty
uPVC Pipes 200mm Dia 216.381/214.404 Km 216.381

Km

214.404

Km

214.404

Km

214.404

Km

DWC Pipes 350mm Dia to 200mm Dia 33.886/30.627 Km 33.886

Km

30.627

Km

30.627

Km

30.627

Km

CI Pipes LA class 1200mm Dia to 350mm Dia 20.135/25.393 Km 20.135

Km

25.393

Km

25.393

Km

25.393

Km

Total 270.402/270.424 Km 270.402

Km

270.424

Km

270.424

Km

270.424

Km

2 Manholes (Nos) 11380/11024 Nos 11380 Nos 11024 11024 11024
3 House Service connection No’s up to Outside Boundary completed 42008 Nos 28000Nos 27907Nos 93 Nos
No’s up to inside Boundary completed 42008 Nos 28000Nos 26590Nos 1410 Nos
No’s inter connection completed 42008 Nos 28000Nos 25758Nos 2242 Nos
4 Lifting Station 14/16 Revised 1.       Nettikattipalayam (Zone 5.2) Completed.

2.       Srinagar (Zone 5.1) Completed.

3.       M.G.R colony (Zone 6.2) Completed.

4.       C.B.N.Palayam(Zone 6)Completed.

5.       Palanisamy Nagar (Zone 5) Completed.

6.       Thottathupalayam(zone5.1) Completed.

7.      Bommainaickenpalayam (Zone 6.2) Completed.

8.      Thanner Panthal (Zone 7.6) completed.

9.      Avinashi Nagar (Zone 6.1) Completed.

10.  Poondi Road (Zone 7.2) Completed.

11.  Sirupuluvapatti (Zone 7.6) Completed.

12.  Sandaipettai (Zone 7.4) Completed.

13.  Angeripalayam Sugam Nagar (Zone 7.4) Civil work completed. Pumpset erection inprogress.

14.  Kavitha Lakshmi nagar Extn (Zone 7.4) To be started.

15.  Ambedkar Street (Zone 5.1) Completed.

16.  Nallappa Nagar (Zone 7.1) Completed

5 Sewage Pumping stations 4 1.Nanjarayan Nagar MPS 5 –Sewage Pumping under progress.

2.Indira Nagar SPS-6– Sewage Pumping under progress.

3.Madheswaran Kovil SPS-7– Sewage Pumping under progress.

4.Sakthinagar MPS 7.5– Sewage Pumping under progress.

6 Pumping Mains CI Pipes 200 mm Dia to 750 mm Dia 21.258/26.56 Km 26.56 km supplied 26.56 km laid.
7 Road Restoration work (Km) 50.857/41.050

Km

41.050 Km Completed.

 

 

 

 

2.Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer zones 8, 13 and 14 and Expansion of the existing STP at Sarkar- periyapalayam and Rejuvenation of Existing SPS & MPS (Package – 2).

Project Cost : Rs.132.95 Crores

Date of Tender : 03.10.2018

Date of Work Order : 04.02.2019

Contract Value: Rs.103.01 Cr. 

Contractor: M/S Keyem Infra Project Private Limited

Date of agreement: 04.02.2019 

Probable Date of Completion: 31.07.2025

Present Stage of Work : 95 % Work Completed.

Expenditure So far :116.30 Crores

 

 

Sl.No. Name of the component Agreement/Revised Qty Current Status
1 Collection System (Km) Estimated Qty Revised Qty Supply Qty Laid Qty Balance Qty
uPVC Pipes 200mm Dia 85.39/91.25 Km 85.39 Km 91.25Km 91.25Km 91.25

Km

DWC Pipes 350mm Dia to

200mm Dia

13.405/10.64 Km 13.405 km 10.64 km 10.64 km 10.64

km

CI Pipes LA class 1200mm Dia to 350mm

Dia

4.927/6.17 Km 4.927 Km 6.17km 6.17km 6.17

Km

Total 102.93/108.06 Km 102.93Km 108.06Km 108.06Km 108.06Km
2 Manholes (Nos) 4374/4381 Nos 4374 Nos 4381 Nos 4381

Nos

3 House Service connection No’s up to Outside Boundary completed 17803 Nos 17803

Nos

17803

Nos

No’s up to inside Boundary completed 17803 Nos 17803

Nos

17803

Nos

No’s inter connection completed 17803 Nos 17803

Nos

10595

Nos.

7208

Nos

4 Lifting Station 5/9 Revised 1. Vanjipalayam Main Road (Zone8) Completed all works. EB power supply obtained. Commissioning started.
2. Bhavani Nagar 4th Street (Zone 13) Completed all works. EB power supply obtained. Commissioning started.
3. TVK Nagar College Road (Zone 14) Completed all works. EB power supply obtained. Commissioning started.
4. Sanjay Nagar- Completed all works. EB power supply obtained. Commissioning started.
5.    Chikanna College- Completed all works. EB power supply obtained. Commissioning started.

6.    Kattabomman Nagar- Completed all works. EB power supply obtained. Commissioning started.

7.    Jeeva Nagar- Completed all works. EB power supply obtained. Commissioning started.

8.    Perumal Koil Street- Completed all works. Awaiting for EB supply.

9.    Kavilipalayam- Completed all works. EB power supply obtained. Commissioning started.

5 Sewage Pumping stations 2 1.  Kattabomman Nagar– Civil work & Pumpset erection completed. EB power supply obtained. Commissioning started.

2.  Anaipalayam, Jayalalitha Nagar– Civil work & Pumpset erection completed. Awaiting for EB supply. Commisioning started with DG Power Supply

6 Pumping Mains CI Pipes

600mm Dia & 400mm Dia

6.930Km 6 6.930 Km supplied; 6.930 Km Laid. Completed
7 Road Restoration work (Km) 47.816/48.14 Km 48.14Km Completed.
8 Improvement of existing STP 15MLD 1 Aerator and Clarifier civil work completed.

Pump Erection work completed. CEIG Clearance Obtained.

 

 

 

 

3.Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 9, 15, 16 and 17 (Package – 3)

Project Cost : Rs.167.12 Crores

Date of Tender  : 03.10.2018

Date of Work Order : 04.02.2019

Contract Value: Rs.118.35 Cr. 

Contractor: M/S Keyem Infra Project Private Limited

Date of agreement: 04.02.2019 

Probable Date of Completion: 31.07.2025

Present Stage of Work : 95 % Work Completed.

Expenditure So far :117.14 Crores

 

 

Sl.No. Name of the component Agreement/Revised Qty Current Status
1 Collection System (Km) Estimated Qty Revised Qty Supply Qty Laid Qty Balance Qty
uPVC Pipes

200mm Dia

132.672/133.75 Km 132.672

Km

133.75

Km

133.75

Km

133.680

Km

0.07 Km
DWC Pipes 350mm Dia

to 200mm Dia

19.948/19.392 Km 19.948

Km

19.392

Km

19.392

Km

19.392 Km
CI Pipes LA class 1200mm

Dia to 350mm Dia

9.078/12.655 Km 9.078 Km 12.655Km 12.655Km 12.655Km
Total 161.69 /165.797 Km 161.69

Km

165.797

Km

165.797

Km

165.727

Km

0.07 Km
2 Manholes (Nos) 5758/6417 Nos 5758 Nos 6417 Nos 6417 Nos
3 House Service connection No’s up to Outside Boundary completed 17032

Nos

17032 Nos
No’s up to inside Boundary completed 17032

Nos

17032 Nos
No’s inter connection completed 17032

Nos

10817 No’s 6215Nos
4 Lifting Station 8/16 revised 1.       Idumban Nagar (Zone 9.1) Civil work & Pumpset erection completed. Awaiting for EB supply.

2.       Vinayagapuram (Zone 15.1) Civil work & Pumpset erection completed. Electrical work completed. obtained EB supply.

3.       Muthu nagar – All work completed. EB supply obtained.

4.       Kulathu pudur Main Road (Zone 9.1) Civil work & Pumpset erection completed. Electrical completed. Awaiting for EB supply.

5.       Kullegoundan pudur cross street (Zone 9.1) Civil work

completed, Pumpset erection completed. Electrical work completed. Awaiting EB supply.

6.       North Thottam (Zone 15.2) Civil work & Pumpset erection completed. obtained EB supply.

7.       Sugumar Nagar (Zone 17.1) Civil work completed. Pumpset completed. Awaiting EB supply.

8.       Sakthi colony-Palayakadu (one 17.2) Civil work completed. Pumpset erection completed.

9.       Chinnandipalayam STP Site- Civil work & Pumpset erection completed. Electrical work completed. Trail run under progress.

10.   Kallampalayam 207/15-1- Civil work completed. Pumpset erection under progress.

11.   Meenachiamman Koil- Civil work completed. Pumpset erection competed.

12.   Iduvai Road-Sidewall- civil work completed.

13.   Pattukottaiyar Nagar- Civil work completed. Pumpset erection under progress.

14.  Kumarappapuram – Civil work completed. Pumpset erection under progress.

15.  Sivasakthi    Nagar    –    Pumpset   erection   completed. Electrical work completed. Awaiting for EB supply.

Thennampalayam – Civil work completed. Pumpset erection to be started.

5 Sewage Pumping stations 3 1.       Karumarampalayam    Completed all works. Awaiting for EB supply.

2.       SR Nagar North (Zone 9)- Completed all works. Obtained EB supply. Commissioning started.

3.       Pattukottaiyar Nagar – Completed all works. Awaiting for EB supply.

6 Pumping Mains CI Pipes 500mm Dia ,400 &

300mm Dia

10.70Km 10.70 Km supplied; 10.70 Km Laid.
  1. Design and Construction of Sewage Treatment Plant of capacity 36 MLD in Sarkarperiyapalayam and 20 MLD in Chinnandipalayam including 10 years of operation and maintenance on DBOT basis for UGSS in Tiruppur City Municipal Corporation.

Project Cost: Rs.72.57 Crores

Date of Tender: 03.10.2018

Date of Work Order: 28.02.2019

Contract Value: Rs.71.57 Cr. 

Contractor: M/S Eco Protection Engineers Pvt Ltd. 

Date of agreement: 28.02.2019

Date of completion: 30.11.2022

Present Stage of Work : 100 % Work Completed.

Expenditure So far :70.72 Crores

 

Sl.No.

 

Name of the component Qty Current Status
1 Plant and Mandatory spare parts

supplied from within the employer’s country

1No 100 % of equipment’s has been supplied
2 Design Services 1No Completed
3 i) 36MLD STP

Sarkarperiyapalayam

1No 1. SBR: All Works completed

 

2. CCT: All works completed.

 

3. Tonner Room: All works completed.

 

4. Gravity Thickener: All works completed.

 

5. Air blower House: All Works completed.

 

6. Sludge Sump with pump House:

All works completed.

 

7. Admin Building & MCC Building: All works completed.

 

8. Centrifuge Building: All works completed.

9. Pre- Treatment Unit (PTU): All works completed.

 

10.  Internal Road work, drainage work and Gate Arch: Completed

* CTO obtained on 28.11.2022 from TNPCB

 

Fully running up to collected from 25758  of HSC.

Sewage Inlet flow 392.676 ML received and treated

387.285 ML treated out flow in May month. Average of 12.667 MLD Inlet, 12.493

MLD Treated outlet.

 

ii) 20MLD STP

Chinnandipalayam

1.   SBR: Completed

2.   Gravity Thickener: Completed.

3. Centrifuge: Completed.

4. Sludge sump cum pumphouse: Completed.

5. Thickened Sludge Sump& Centrate and Overflow Sump: Completed.

6. CCT: Completed.

7. Tonner Room: Completed.

8. Admin Building & MCC Building: Completed.

9. Air Blower Building: Completed.

 

10.   Pre- Treatment Unit (PTU): Completed.

 

11.  Internal Road work with Drainage and Gate Arch: Completed.

 

* CTO obtained on 12.12.2023 from TNPCB.

 

Fully running up to collected from 9457   HSC.

Sewage Inlet flow 36.16 ML received and treated

35.51 ML treated out flow in May month. Average of 1.166 MLD Inlet, 1.145 MLD Treated outlet.

4 Operation & Maintenance 1No

 

 

AMRUT-2.O (2023-24)

 

 Under Ground Sewerage  Scheme

 Providing Comprehensive Underground Sewerage Scheme to Added areas (zone -11, 11.1 & 11.3) in Tiruppur City Municipal Corporation including 60 months of Operation and Maintenance

Project Cost : Rs.192.95 Crores

Date of Tender : 18.03.2024

Date of Work Order : 17.10.2024

Contract Value: Rs.190.19 cr.

Contractor: M/S Eco Protection Engineers Pvt Ltd. 

Date of agreement: 11.11.2024

Probable Date of Completion: 16.10.2027

Present Stage of Work : 28% Work Completed.

Expenditure So far : 23.01 Crores

 

Components As per Agreement Progress
Main & Sub pumping station (Nos) 3 1 Station- RCC Wall 4th lift Shuttering Work under progress. 1 Station CETP Pipe line Shifting work under progress.1 Station  Public Objection.
Lift Manholes (Nos) 7 3 Station  Civil work Completed. 2 Station work under progress. 1 Stations to be started. 1 Station Private Land issue.
Sewer Line in KM 109.87 106.20Km pipe supplied and  30.54Km Laid. Balance 79.33 Km.
Machine holes (Nos) 4177 1360 Nos Erected. Balance 2817 Nos.
No.of HSCs (Nos) 16708 HSC’s – 1080Nos laid. Balance 15628Nos.
Pumping Main in KM 9.72 150mm to 900mm CI Pipes – 5.311 Km Pipe Supplied and 2.21 Km laid. Balance 7.50Km.