AMRUT

AMRUT – UGSS INCENTIVE – CORPORATION STAFF AND ELECTED REPRESENTATIVE’S DETAILS

AMRUT Scheme

Water Supply-Source Improvement & Distribution System

  1. Construction of Raw Water Intake well, Pump House with Surge Protection Tank, Supply and installation of Pump set and motors with all electrical works in Bhavani River bank at Mettupalayam and Supplying, Laying and Jointing of Pumping Main from Raw Water Intake  to  Water Treatment Plant near Annur including Pipe Carrying Bridges wherever necessary(Package– 1).

Estimate Amount: Rs.101.00 Crores

Date of Tender: 05.10.2018

Date of Work Order: 28.02.2019

Present Stage of Work – 100%

Date of completion: 27.02.2023

Sl.No Name of the component Qty Current Status
I Head Works
Raw Water Intake Well 1 No. Completed.
River bank Protection works 150 m Completed.
Connecting Pipe 1800 mm MS Pipe  between Intake well to Sump 26 M X 2 Completed.
Raw Water Sump cum pump house 1 No. Completed.
2 Electro mechanical Items Trail Run under progress.
Supply, delivery and erection of raw water Vertical Turbine pump sets 6 Nos. Trail Run under progress.
Electrical installations 1 No. Completed.
3 Surge Protection Tank 1 No. Completed.
4 Raw water main Completed.
1422 mm dia x 12 mm MS Pipe 19.27 KM Supply Laid Hydraulic  Test
19.82 Km 19.97Km 19.83 Km
Trail Run Pumping from Headworks to  WTP 16345.00 ML Total Raw water pumped  from 01.01.2023 to 29.11.2023

Expenditure So far :126.31Crores

  Construction of Water treatment Plant of Capacity 196 MLD expandable to 270 MLD with  complete  SCADA system for the entire Project on Design Build, Operate and Transfer basis for new water supply scheme In Tiruppur City Municipal Corporation. Period of Completion 24 Months followed by 6 Months trail run and commissioning.(Package – 2).

Estimate Amount : Rs.82.94 Crores

Date of Tender :05.10.2018, 18.01.2019.

Date of Work Order : 28.06.2019

Present Stage of Work :100 %

Date of completion: 30.09.2022

 Sl.No Name of the component Qty Current Status
1 Basic Engineering package 1 No. Approved
Hydraulic design 1 No. Approved
Structural design for Clear Water  reservoir 1 No. Approved
Clear Water Reservoir 1 No. Completed.
 

2

Flocculator& Inclined plate settler 1 No. Completed.
3 Sludge Conditioner tank 1 No. Completed.
4 Sludge Thickener Unit 1 No. Completed.
5 Chlorination Building 1 No. Completed.
MCC Room 1 No. Completed.
 

 

Chemical House 1 No. Completed.
Filter House 1 No Completed.
Back wash water Recirculation sump 1 No Completed.
Aerator 1 No Completed.
Raw Water Channel 1 No Completed.
Back Wash Water Pump Room 1 No Completed.
Administration Building 1 No Completed.
Centrifuge Building 1 No Completed.
Internal Drainage, Compound wall and  Road formation 1 No Completed.
Clear Water Discharge from WTP (Trail  Run) 16253 ML Total Clear water Discharged   WTP from  01.01.2023 to 29.11.2023

 Expenditure So far :91.41Crores.

 

  1. Supplying, Laying and Jointing Clear Water Gravity Main from Water Treatment Plant to OHTs  in Tiruppur Corporation including Pipe Carrying Bridges wherever necessary.(Package – 3).

Estimate Amount : Rs.356.00 Crores

Date of Tender :05.10.2018

Date of Work Order: 03.06.2019

Present Stage of Work: PHYSICAL PROGRESS–100 %, Date of completion: 15.11.2022

Name of the component Qty (km) Current Status
Clear water Gravity Transmission main
MS Pipes

1829 mm Dia to 610 mm Dia

Total-78.820Km

Pipe Size Estimate 

(Km)

Supply Laid Hydraulic  Test
1829 mm dia MS pipe 20.02 20.018 20.018 20.00
1626mm dia MS Pipe 18.210 17.180 17.180 17.180
1118mm dia MS Pipe 4.720 4.720 4.720 4.706
914mm dia MS Pipe 4.310 7.857 7.857 7.855
813mm dia MS Pipe 13.190 9.526 9.526 9.489
711mm dia MS Pipe 9.410 9.367 9.367 9.366
610mm dia MS pipe 8.980 8.910 8.910 8.870
Total 78.84 77.578 77.578 77.466
DI – K7 Pipes

500 mm Dia to 150 mm Dia

Total-69.486Km

Pipe Size Estimate 

(Km)

Supply Laid Hydraulic  Test
500mm dia DI Pipe 8.596 10.347 10.347 10.347
450mm dia DI Pipe 2.970 2.970 2.970 2.970
400mm dia DI Pipe 14.179 13.791 13.791 13.491
350mm dia DI Pipe 9.966 9.966 9.966 9.946
300mm dia DI Pipe 15.119 15.119 15.119 15.087
250mm dia DI Pipe 11.097 6.993 6.993 6.949
200mm dia DI Pipe 7.184 6.064 6.064 6.064
150mm dia DI Pipe 1.925 1.925 1.925 1.888
Total 71.036 67.175 67.175 66.742
Construction of Pipe Carrying Bridges 10/9 9 No. completed.
Existing OHT Inlet pipe  connection 74.153 Water filling Existing OHTs- 39 nos. Water filling New OHTs- 12 Nos. 15 Nos New OHTs – Trail run completed up to ground level.

Expenditure So far :402.11Crores

 Construction of 12 Nos (W.S Zones- 2, 3, 4, 8, 22, 23, 26,28, 29, 30, 31, 32) Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zones-I & II area. (Package – 4).

Estimate Amount: Rs.185.00 Crores

Date of Tender   : 05.10.2018

Date of Work Order : 01.03.2019

Present Stage of Work :PHYSICALPROGRESS-92%

S No. Location of Tank Capacity Present Stage of Work
1 Pandian Nagar Roof slab completed. Colour Washing & Trail run work under progress
2 MatheswaranKoil 1 Roof slab completed. Finishing work & Trail run under progress
3 MatheswaranKoil 2 Roof slab completed. Finishing work under progress
4 Thiru vi kanagar Roof slab completed. Colour Washing work under  progress
5 G.N Garden Roof slab completed. Colour Washing work & Trail  run under progress
6 Sneha Nagar Roof slab Completed. Colour Washing work under  progress
7 NRK Puram Roof slab completed. Colour Washing work under  progress
8 Kumar Nagar 2nd brace work  completed. Above 2nd brace  Steel work Under progress
9 Kumar Nagar 3rd brace completed. Above 3rd Brace Column box fixing  work under  progress.
10 Bharatiyar Complex 1st lift of sidewall Completed 2nd lift of sidewall work under  progress.
11 Palayakadu Roof slab completed. Colour Washing work under  progress
12 Gate Thottam Floor slab work under progress. Floor slab Steel work under progress.

 

Sl.No. Name of the 

component

Qty D-System Current Status
13 HDPE Pipe 

225mm dia to 

110mm dia

330.788Km Pipe Size Estimate

(Km)

Revised  (Km) Supply

(Km)

Laid

(Km)

Remarks
110mm

HDPE

317.408 476.907 456.504 448.852 70.969Km 

Tested

160mm

HDPE

10.008 10.00 10.008 10.00 2.906Km 

Tested

225mm

HDPE

3.372 1.592 2.004 1.592
Total 330.788 488.499 468.516 460.444 73.875Km 

Tested

Sl.No. Name of the 

component

Qty D-System Current Status
DI – K7 Pipes  700mm dia to  200mm dia 171.869Km Pipe 

Size

Estimate 

(Km)

Revised 

(Km)

Supply

(Km)

Laid

(Km)

Remarks
200mm 

DI

37.745 24.028 29.581 22.512 4.258Km 

Tested

250mm 

DI

6.043 6.040 6.043 6.040 0.462Km 

Tested

300mm 

DI

51.733 29.722 33.365 28.731 3.397Km 

Tested

350mm 

DI

9.452 7.819 8.508 7.601 2.043Km 

Tested

400mm 

DI

28.611 18.959 25.126 16.842 4.288Km 

Tested

450mm 

DI

0.104 0.095 0.104 0.095
500mm 

DI

25.457 15.963 17.964 14.454 2.906Km 

Tested

600mm 

DI

12.558 12.589 11.638 9.571 2.423Km 

Tested

700mm 

DI

0.166
Total 171.869 115.215 132.329 105.848 19.78km 

Tested

14 Chlorination 

Plants

12Nos
15 House Service  Connections 57553/41000 40133 No’s completed.

HSC Water Meter 19716 No’s Completed.

 

Expenditure So far :152.54Crores.

 Construction of 17 Nos (W.S Zones- 34, 35, 36, 37, 38, 39,40, 43, 44, 48, 50, 52, 54, 56, 57, 60, 70) of Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zone-III& IV area. (Package-5).

Estimate Amount : Rs.195.00 Crores

Date of Tender : 05.10.2018

Date of Work Order : 04.02.2019

Present Stage of Work :Physical Progress: 91 %

S No. Location of Tank Capacity Present Stage of Work
1 KovilVazhi 5.00LL Completed.
2 Kalipalayam 5.00LL Pipe Connection work under  progress
3 Chennimalaipalayam 5.00LL Trail Run under progress.
4 Mahalakshmi Nagar (Vijayapuram) 7.50LL Trail Run under progress.
5 Karthik Nagar 7.50LL Pipe Connection work under  progress
6 Krishna Nagar 7.50LL Completed.
7 Noyyal Burial  Ground 10.00LL Colour Washing work to be  started.
8 Dharapuram Road OHT 10.00 LL Finishing work & Pipe 

Connection work under Progress

9 PudhuPalayam 12.50LL Pipe Connection work under  Progress
10 Thiru Nagar 15.00LL Colour Wash to be started
11 Kaliappa Nagar 20.00LL Finishing work & Pipe 

Connection work under Progress

12 Santhapettai 7.50LL Above 3rd brace  Columnwork under progress.
13 TSK Maragathammal 7.50LL Finishing work & Pipe 

Connection work under Progress

14 Cattle Shed 10.00LL Finishing work under progress
15 State Bank colony 15.00LL Finishing work & Pipe 

Connection work under Progress

16 MasaniyammanKoil 15.00LL Floor slab work under progress
17 Andipalayam (SR  Nagar) 12.50LL Floor slab work under progress
Sl.No. Name of the 

component

Qty Current Status
18 Distribution System Km
HDPE Pipe 225mm dia to  110mm dia 344.184Km Pipe 

Size

Estimate (Km) Revised 

(Km)

Supply

(Km)

Laid

(Km)

110mm

HDPE

289.136 347.485 337.590 320.555
160mm

HDPE

51.676 58.454 58.43 52.105
225mm

HDPE

3.372 3.372 3.372 2.120
Total 344.184 409.311 399.392 374.78
DI – K7 Pipes 

700mm dia to 200mm dia

215.588km Pipe 

Size

Estimate (Km) Revised 

(Km)

Supply

(Km)

Laid

(Km)

200mm 

DI

74.501 50.32 51.266 50.25
250mm 

DI

15.795 13.868 10.252 10.429
300mm 

DI

45.790 21.440 24.454 20.006
350mm 

DI

9.594 8.002 6.965 6.44
400mm 

DI

38.627 23.890 17.061 17.061
450mm 

DI

2.895 2.895 2.750 2.750
500mm 

DI

27.410 17.699 14.191 12.143
600mm 

DI

0.810
700mm 

DI

0.166
Total 215.588 138.114 126.939 119.079
19 Chlorination Plants 17 Nos
20 House Service 

Connections

59883/27000 24509 No’s Completed.

HSC Water Meter 1420 No’s Completed.

 

Expenditure So far :127.84Crores

 

 

 

TRANSFORMING THE EXISTING INTERMITTENT WATER SUPPLY TO CONTINUOUS 24X7 WATER SUPPLY DISTRIBUTION SYSTEM FOR THE WATER ZONE 30 & 50 IN TIRUPPUR CITY MUNICIPAL (Package – 6)

CORPORATION – Period of Completion 12 months followed by 3 months Trial Run and commissioning.

Estimate cost: Rs. 41.00 Cr Contract Value: Rs.37.29 Cr. 

Contractor: M/S Eco Protection Engineers Pvt Ltd. 

Date of agreement: 07.07.2023                                        Date of completion: 06.07.2024

PHYSICAL PROGRESS – 30 %

 

Sl.   No.

Name of the components Total Qty

 as per  Agreement

Progress

As  on 30.11.2023

Scheduled date of completion
1 Establishment of DMAs for Water distribution network for 24×7 water supply for the wards inside Pilot zones 30 &50    Zone -30-7 DMAs

Zone -50- 3 DMAS

Total : 10 DMAs     

Work  under progress 06.07.2024
2 Rehabilitation of water mains for Distribution system including Sluice valves for Isolating the sub-district including all civil works.

DI K-7 & HDPE PN -6 Pipes       

41 Km for Zone 30

19 Km for Zone 50 Total : 60 Km         

Ø    Distribution Main :- 110mm HDPE Pipe -49.266 Km Pipe Supplied and 26.29 Km Laid.

 

Ø    160mm HDPE Pipe -5.058Km Pipe Supplied and 2.19 Km Laid.

 

Ø    225mm HDPE Pipe -2.67Km Pipe Supplied and 0.15 Km Laid.

3 Renewal of House service connections with AMR water meters– including Water meter Protection Box 20 Points of Pressure & Quality

sensors –  

Total : 8400

HSC – 876 No’s Outside Boundary Completed out of 8400Nos
4 Design, Supply and Installation of SCADA system required for effective management of the water supply system based on the continuous data, its analysis and  management.      1Job Work to be Started.
5 Providing leak detection equipment for carrying out active leakage control 1Set Work to be Started.

 

Expenditure So far :11.62Crores

 

 

 

 

 

 

Under Ground Sewerage  Scheme -2017-2020

 

  1. Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains  in  sewer  Zones  5,  6  and  7 (Package – 1).

Estimate Amount : Rs.246.30 Crores

Date of Tender  : 03.10.2018

Present Stage of Work :PHYSICALPROGRESS-95%

 Sl.

No.

Name of the component Qty Current Status
1 Collection System(Km)
uPVCPipes200mmDia 216.381/214.404Km 214.404kmsuppliedand214.404Km Laid.
DWCPipes350mmDiato200mmDia 33.886/30.627Km 30.627kmSuppliedand30.627km laid
CI Pipes LA class 1200mm Dia to350mmDia 20.135/25.393Km 25.393kmsuppliedand25.393Kmlaid
 

2

 

Manholes (Nos)

11380/11024Nos 11024NosCastedand11024Noserected
3 House Service connection 23000

42008Nos

21599 No’s up to Boundary Completed.

12607 No’s up to inside Boundary completed.

5773N o’s inter connection completed.

4 Lifting Station 14/16 Revised 1.     Nettikattipalayam(Zone5.2)Completed.

2.     Srinagar(Zone5.1)Completed

3.     M.G.Rcolony(Zone6.2)Completed.

4.     C.B.N.Palyam(Zone6)Completed.

5.     PalanisamyNagar(Zone5)Completed.

6.     Thottathupalayam(zone5.1)Completed.

 

7.     Bommainaickenpalayam(Zone6.2)Completed.

 

8.     ThannerPanthal(Zone7.6)completed.

 

9.     AvinashiNagar(Zone6.1)Completed.

 

10.  PoondiRoad(Zone7.2)Completed.

11.  Sirupuluvapatti(Zone7.6)Completed.

 

12.  Sandaipettai(Zone7.4)Completed.

13.  AngeripalayamSugam Nagar (Zone 7.4) Civilwork completed. Pumpset erection inprogrss.

 

14.  Kavitha Lakshmi nagarExtn (Zone 7.4) To be started.

 

15.  AmbedkarStreet(Zone5.1)Completed.

 

16.  NallappaNagar(Zone7.1)Completed

5 Sewage Pumping stations 4 1. NanjarayanNagarMPS5Allworkscompleted. Sewage Pumping under progress.

 

2. IndiraNagarSPS-6-Allworkscompleted.Sewage Pumping under progress.

3. MadheswaranKovilSPS-7-AllWorkscompleted. Power supply obtained.

SakthinagarMPS7.5-Screen,GritandSuctionwell civil work completed. E&M Work under progress.

6 Pumping Mains CI Pipes 200 mm Dia&750mmDia  

21.258/26.264Km

 

26.56kmsupplied26.264kmlaid.

7 RoadRestorationwork (Km)  

50.857/41.050

Km

 

41.050KmCompleted.

 

Expenditure So far :  281.70Crores

 

 

 

  1. Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer zones 8, 13 and 14 and Expansion of the existing STP at Sarkar- periyapalayam and Rejuvenation of Existing SPS & MPS (Package – 2).

Estimate Amount : Rs.101.55 Crores

Date of Tender : 03.10.2018

Date of Work Order : 04.02.2019

Present Stage of Work :PHYSICALPROGRESS -93%

 

Sl.No. Name of the component Qty Current Status
1 Collection System(Km)
uPVC Pipes 200mm Dia  

85.39/91.00Km

 

91.00Kmsuppliedand89.52KmLaid.

DWC Pipes 350mm Dia to 200mm Dia  

13.405/12.621Km

 

12.621kmsuppliedand10.62kmlaid

CI Pipes LA class 1200mm Dia to 350mm Dia  

4.927/6.17Km

 

6.17kmSuppliedand6.052KmLaid.

 

2

 

Manholes (Nos)

 

4374Nos

 

4374nos erected.

3 House Service connection 17803No’s 15238 No’s up to Boundary Completed.

10241 No’s up to inside Boundary completed.

342 N o’s inter connection completed.

4 Lifting Station 5/9 Revised 1.  VanjipalayamMainRoad(Zone8)Civilwork&Pumpset erection completed. Electrical work under progress.

2.  BhavaniNagar4thStreet(Zone13)Civilwork&Pumpset erection completed. Electrical work under progress.

3.  TVKNagarCollegeRoad(Zone14)Civil work &Pumpset erection completed. Electrical work under progress.

4.  SanjayNagar-Civilwork&Pumpseterection completed. Electrical work under progress.

5.  ChikannaCollege-Civilworkcompleted. E&M under progress.

6.  KattabommanNagar-Civilwork&Pumpset erection completed. Electrical work under progress.

7.   JeevaNagar-Civilworkcompleted.Civil work &Pumpset erection completed. Electrical work under progress.

8.   PerumalKoil Street-Civil workcompleted. E&M under progress.

9.   Kavilipalayam-Civilworkcompleted.E&M under progress.

5 Sewage Pumping stations 2 1.   KattabommanNagar-Civilwork&Pumpset erection completed. Electrical work under progress..

Anaipalayam,Jayalalitha Nagar-Civil work &Pumpset erection completed. Electrical work under progress.

6 PumpingMainsCIPipes

600mmDia&400mmDia

 

6.930Km

 

6.930Kmsupplied,6.811KmLaid.

 

7

RoadRestorationwork(Km)  

47.816

 

48.14KmCompleted.

 

8

Improvementofexisting STP 15MLD  

1

AeratorandClarifiercivilworkcompleted.

PumpErectionworkunderprogress.Transformer and allied works to be started.

 

Expenditure So far :  89.90Crores

 

 

 

 

 

  1. Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 9, 15, 16 and 17 (Package – 3)

Estimate Amount : Rs.115.80 Crores

Date of Tender  : 03.10.2018

Date of Work Order : 04.02.2019

Present Stage of Work :PHYSICALPROGRESS -93%

 Sl.No. Name of the component Qty Current Status
1 Collection System(Km)
uPVCPipes200mmDia  

132.672 Km

132.00Kmsupplied&132.00KmLaid.
DWC Pipes 350mm Dia to 200mmDia  

19.948/20.392

Km

20.392KmSupplied&16.972KmLaid.
CI Pipes LA class 1200mm Dia to350mmDia 9.078/12.498

Km

12.498KmSupplied &11.95KmLaid.
 2  Manholes (Nos) 5758/6418

Nos

6418Nos.erected.
3 HouseServiceconnection 15249Nos.uptoBoundaryCompleted. 11658Nos.inside BoundaryCompleted.

322 Nos inter Connection Completed.

4 LiftingStation 8/16 Revised 1.IdumbanNagar(Zone9.1)Civilwork&Pumpset erection completed. Electrical work under progress.

2.Vinayagapuram (Zone 15.1) Civil work&Pumpseterectioncompleted. Electrical work under progress.

3.Muthunagar       Civilworkcompleted. Pumpset erection inprogress.

4.KulathupudurMainRoad(Zone9.1) Civil work &Pumpset erection completed. Electrical work under progress.

5.Kullegoundanpudurcrossstreet(Zone 9.1) Civil work completed.

6.NorthThottam(Zone15.2)Civilwork &Pumpset erection completed. Electrical work under progress.

7.SugumarNagar(Zone17.1)Civilwork completed. Pumpset erection in progress.

8.Sakthi colony-Palayakadu(one17.2)

Civilworkcompleted.

9.Chinnandipalayam STP Site- Civil work&Pumpseterectioncompleted. Electrical work under progress.

10.Kallampalayam207/15-1-Civilwork completed.

11.MeenachiammanKoil-Civilwork completed.

12.IduvaiRoad-Civilworkinprogress.

13.PattukottaiyarNagar-Civilwork completed.

14.Kumarappapuram      Civil  work completed.

15.Sivasakthi Nagar Civilwork completed.

16.ThennampalayamCivilworkin progress.

5 SewagePumpingstations 3 1.       Karumarampalayam  Civil work &Pumpseterectioncompleted.Electrical work under progress.

2.       SRNagarNorth(Zone9)-Civilwork &Pumpset erection completed. Electrical work under progress.Progress.

3.       Pattukottaiyar Nagar – Civil work &Pumpseterectioncompleted.Electrical work under progress.

6  

PumpingMainsCIPipes500mmDia

,400&300mmDia

 

10.70Km

 

10.70Kmsupplied,10.62KmLaid.

 

Expenditure So far :  103.17Crores

Design and Construction of Sewage Treatment Plant of capacity 36 MLD in Sarkarperiyapalayam and 20 MLD in Chinnandipalayam including 10 years of operation and maintenance on DBOTbasis for UGSS in Tiruppur City Municipal Corporation.Estimate Amount: Rs.61.72 Crores

Date of Tender: 03.10.2018

Date of Work Order: 28.02.2019

Present Stage of Work: At 36 MLD: 

PHYSICALPROGRESS       99%

 Sl.No. Name of the component Qty Current Status
1 PlantandMandatoryspareparts supplied from within the

country

1No 100
2 DesignServices 1No Completed
3 i)36MLDSTP

Sarkarperiyapalayam

1No  

1.               SBR:AllWorkscompleted

 

2.  CCT:Allworkscompleted.

 

3.  TonnerRoom:Allworkscompleted.

 

4.  GravityThickener:Allworkscompleted.

 

5.  AirblowerHouse:AllWorkscompleted.

 

6.  Sludge Sump with pump House: All works completed.

 

7.  Admin Building & MCC Building:All works completed.

 

8.               CentrifugeBuilding:Allworkscompleted.

9. Pre-TreatmentUnit(PTU):Allworkscompleted.

 

10.           Internal Road work, drainage work and Gate Arch: Completed

 

*    PowersupplyobtainedfromTNEB

 

*  CTOobtainedon28.11.2022fromTNPCB

 

Partially running up to collected from 6800 Nos of HSC.

 

Average inflow  – 2MLD /Day

 

ii)20MLDSTP

Chinnandipalayam

 

1.  :Completed

 

2.  GravityThickener:Completed.

 

3.               Centrifuge:Completed.

 

4.               Sludgesumpcumpumphouse:Completed.

5.               ThickenedSludgeSump&CentrateandOverflow Sump:Completed.

 

6.               CCT:Completed.

 

7.               TonnerRoom:Completed.

8.               AdminBuilding&MCCBuilding:Completed.

 

9.               AirBlowerBuilding:Completed.

 

10. Pre-TreatmentUnit(PTU):Completed.

 

11.           Internal Road work with Drainage and Gate Arch: Completed.

PowersupplyobtainedfromTNEB.

CTO applied. Application forward to PCB Board office at Chennai .

Ready to Operate.

Operation&Maintenance 1No

 

Expenditure So far :  67.54Crores