AMRUT Scheme
New Water Supply Scheme
1.Construction of Raw Water Intake well, Pump House with Surge Protection Tank, Supply and installation of Pump set and motors with all electrical works in Bhavani River bank at Mettupalayam and Supplying, Laying and Jointing of Pumping Main from Raw Water Intake to Water Treatment Plant near Annur including Pipe Carrying Bridges wherever necessary(Package– 1).
Project Cost : Rs.132.36.00 Crores
Date of Tender: 05.10.2018
Date of Work Order: 28.02.2019
Contract Value: 109.17 Cr
Contractor: M/S Keyem Infra Projects Limited, Chennai.
Present Stage of Work – 100%
Date of completion: 27.02.2023
Expenditure So far : 130.96 Crores
| Sl.No. | Name of the component | Qty | Current Status | ||
| I | Head Works | ||||
| Raw Water Intake Well | 1 No. | Completed. | |||
| River bank Protection works | 150 m | Completed. | |||
| Connecting Pipe 1800 mm MS Pipe
between Intake well to Sump |
26 M X 2 | Completed | |||
| Raw Water Sump cum pumphouse | 1 No. | Completed. | |||
| 2 | Electro mechanical Items | Completed | |||
| Supply, delivery and erection of raw water Vertical Turbine pump sets | 6 Nos. | Completed | |||
| Electrical installations | 1 No. | completed | |||
| 3 | Surge Protection Tank | 1 No. | completed. | ||
| 4 | Flow Meter | 2 No. | completed. | ||
| 5 | Raw water main | Completed | |||
| 1422 mm dia x 12 mm MS Pipe | 19.27 KM | Revised Qty (Km) | Supply Qty (Km) | Laid Qty (Km) | |
| 19.82 km | 19.97 Km | 19.83Km | |||
| Trail Run Pumping from Headworks to WTP | 2330.71 ML Total Raw water Pumped in 1st Apr to 31st May 2025.
52769.35 ML Total Raw water pumped from 01.01.2023 to 31.05.2025 |
||||
- Construction of Water treatment Plant of Capacity 196 MLD expandable to 270 MLD with complete SCADA system for the entire Project on Design Build, Operate and Transfer basis for new water supply scheme In Tiruppur City Municipal Corporation. Period of Completion 24 Months followed by 6 Months trail run and commissioning.(Package – 2).
Project Cost : Rs.95.02 Crores
Date of Tender :05.10.2018, 18.01.2019.
Date of Work Order : 28.06.2019
Contract Value: Rs.85.44 Cr.
Contractor: M/S Eco Protection Engineers Pvt Ltd.
Present Stage of Work :100 % Completed
Date of completion: 30.09.2022
Expenditure So far :94.25Crores.
| Sl.No. | Name of the component | Qty | Current Status |
| 1 | Basic Engineering package | 1 No. | Approved |
| 2 | Hydraulic design | 1 No. | Approved |
| 3 | Structural design for Clear Water reservoir | 1 No. | Approved. |
| 4 | Clear Water Reservoir | 1 No. | Completed. |
| 5 | Flocculator & Inclined plate settler | 1No. | Completed. |
| 6 | Sludge Conditioner tank | 1No. | Completed. |
| 7 | Sludge Thickener Unit | 1No. | Completed. |
| 8 | Chlorination Building | 1No. | Completed. |
| 9 | MCC Room | 1No. | Completed. |
| 10 | Chemical House | 1 No | Completed. |
| 11 | Filter House | 1 No | Completed. |
| 12 | Back wash water Recirculation sump | 1 No | Completed. |
| 13 | Aerator | 1 No | Completed |
| 14 | Raw Water Channel | 1 No | Completed |
| 15 | Back Wash Water Pump Room | 1 No | Completed |
| 16 | Administration Building | 1 No | Completed |
| 17 | Centrifuge Building | 1 No | Completed |
| 18 | Internal Drainage, Compound wall and Road formation | 1 No | Completed |
| 19 | Clear Water Discharge from WTP (Trail Run) | 2284.26 ML Total Clear water Discharged from WTP in 1st Apr to 31st May 2025.
51847.39 ML Total Clear water Discharged from 01.01.2023 to 31.05.2025 |
3.Supplying, Laying and Jointing Clear Water Gravity Main from Water Treatment Plant to OHTs in Tiruppur Corporation including Pipe Carrying Bridges wherever necessary.(Package – 3).
Project Cost : Rs.405.00 Crores
Date of Tender :05.10.2018
Date of Work Order: 03.06.2019
Contract Value: Rs.383.82 Cr
Contractor: M/s. Koya & Company Construction Limited,
Present Stage of Work: –100 % Completed ,
Date of completion: 15.11.2022
Expenditure So far :405.00 Crores
| Name of the component | Qty (km) | Current Status | ||||
| Clear water Gravity Transmission main | ||||||
| Pipe Size | Estimate Qty | Revised Qty | Supply | Laid | ||
| (Km) | (Km) | (Km) | (Km) | |||
| 1829 mm dia MS pipe | 20.02 | 20.018 | 20.018 | 20.00 | ||
| 1626mm dia MS Pipe | 18.210 | 17.180 | 17.180 | 17.180 | ||
| 1118mm dia MS Pipe | 4.720 | 4.720 | 4.720 | 4.706 | ||
| MS Pipes | 914mm dia MS Pipe | 4.310 | 7.857 | 7.857 | 7.855 | |
| 813mm dia MS Pipe | 13.190 | 9.526 | 9.526 | 9.489 | ||
| 1829 mm Dia to 610 mm | ||||||
| Dia | ||||||
| 711mm dia MS Pipe | 9.410 | 9.367 | 9.367 | 9.366 | ||
| Total-78.840Km | 610mm dia MS pipe | 8.980 | 8.910 | 8.910 | 8.870 | |
| Total | 78.84 | 77.578 | 77.578 | 77.466 | ||
| Pipe Size | Estimate Qty | Revised Qty | Supply | Laid | ||
| (Km) | (Km) | (Km) | (Km) | |||
| 500mm dia DI Pipe | 8.596 | 10.347 | 10.347 | 10.347 | ||
| 450mm dia DI Pipe | 2.970 | 2.970 | 2.970 | 2.970 | ||
| DI – K7 Pipes | 400mm dia DI Pipe | 14.179 | 13.791 | 13.791 | 13.491 | |
| 500 mm Dia to 150 mm | ||||||
| 350mm dia DI Pipe | 9.966 | 9.966 | 9.966 | 9.946 | ||
| Dia | ||||||
| 300mm dia DI Pipe | 15.119 | 15.119 | 15.119 | 15.087 | ||
| Total-71.036Km | ||||||
| 250mm dia DI Pipe | 11.097 | 6.993 | 6.993 | 6.949 | ||
| 200mm dia DI Pipe | 7.184 | 6.064 | 6.064 | 6.064 | ||
| 150mm dia DI Pipe | 1.925 | 1.925 | 1.925 | 1.888 | ||
| Total | 71.036 | 67.175 | 67.175 | 66.742 | ||
| Grand Total | 149.876 | 144.753 | 144.753 | 144.208 | ||
| Construction of Pipe Carrying Bridges | 10/9 | 9 No. completed. | ||||
| Existing OHT Inlet pipe connection | Water filling Existing OHTs- 39 nos. Water filling New OHTs- 25 Nos.
04 Nos New OHTs – Trail run completed upto ground level. |
|||||
- Construction of 12 Nos (W.S Zones- 2, 3, 4, 8, 22, 23, 26,28, 29, 30, 31, 32) Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zones-I & II area. (Package – 4).
Project Cost : Rs.203.06 Crores
Date of Tender : 05.10.2018
Date of Work Order : 01.03.2019
Contract Value: Rs. 194.74 Cr.
Contractor: M/S R P P Infra Projects Ltd JV with M/S Annai Infra Developers limited
Present Stage of Work :-97% Work Completed.
Probable Date of completion: 31.07.2025.
Expenditure So far :177.54 Crores.
| S No. | Location of Tank | Capacity | Present Stage of Work | Current Status |
| 1 | Pandian Nagar | 10.00LL | Completed. | Commissioned and supply effected. |
| 2 | Matheswaran Koil 1 | 20.00LL | Completed. | Trail run work under progress. Water tightness test to be done |
| 3 | Matheswaran Koil 2 | 20.00LL | Completed. | Water tightness work under progress & Trail run under
progress |
| 4 | Thiru vee ka nagar | 10.00LL | Completed. | Trail run work under progress |
| 5 | G.N Garden | 5.00LL | Completed. | Commissioned and supply effected. |
| 6 | Sneha Nagar | 10.00LL | Completed. | Trail run work under progress |
| 7 | NRK Puram | 12.50LL | Completed. | Trail run work under progress |
| 8 | Kumar Nagar | 10.00 LL | Completed. | Finishing work under progress. |
| 9 | Kumar Nagar | 20.00LL | Completed. | Finishing work under progress. |
| 10 | Bharatiyar Complex | 20.00LL | Completed. | DMA Zone (24×7) Water
tightness work to be done. |
| 11 | Palayakadu | 15.00LL | Completed | Trail run work under progress |
| 12 | Gate Thottam | 5.0 LL | Completed. | Trail run under progress. |
| Sl.No. | Name of the component | Qty | D-System Current Status | |||||
| 13 |
HDPE Pipe 225mm dia to 110mm dia |
330.788 / 497.556Km |
Pipe Size | Estimate (Km) | Revised (Km) | Supply (Km) | Laid (Km) | Balance (Km) |
| 110mm HDPE | 317.408 | 485.636 | 487.500 | 483.902 | 1.735 | |||
| 160mm HDPE | 10.008 | 10.029 | 10.200 | 10.029 | – | |||
| 225mm HDPE | 3.372 | 1.617 | 2.004 | 1.617 | – | |||
| Total | 330.788 | 497.282 | 499.704 | 495.548 | 1.735 | |||
| Sl.No. | Name of the component | Qty | D-System Current Status | |||||
| DI – K7 Pipes 700mm dia to 200mm dia | 171.869 /
117.244Km |
Pipe
Size |
Estimate
(Km) |
Revised
(Km) |
Supply
(Km) |
Laid
(Km) |
Balance
(Km) |
|
| 200mm DI | 37.745 | 24.574 | 29.581 | 24.247 | 0.326 | |||
| 250mm
DI |
6.043 | 6.040 | 6.043 | 6.040 | 0 | |||
| 300mm DI | 51.733 | 30.737 | 33.365 | 30.470 | 0.267 | |||
| 350mm
DI |
9.452 | 7.907 | 8.5085 | 7.852 | 0.055 | |||
| 400mm DI | 28.611 | 19.954 | 25.126 | 19.799 | 0.155 | |||
| 450mm
DI |
0.104 | 0.095 | 0.104 | 0.095 | 0 | |||
| 500mm DI | 25.457 | 17.517 | 17.964 | 16.730 | 0.787 | |||
| 600mm DI | 12.558 | 11.633 | 11.6385 | 10.887 | 0.746 | |||
| 700mm DI | 0.166 | – | – | – | 0 | |||
| Total | 171.869 | 118.459 | 132.330 | 116.12 | 2.336 | |||
| 502.657/614.80 | Grand Total | 502.657 | 615.741 | 632.034 | 611.548 | 4.071 | ||
| 14 | Chlorination Plants | 12Nos | 12 Nos of Shed work completed. | |||||
| 15 | House Service Connections | 57553/
42123 Nos |
42123 No’s completed.
HSC Water Meter 40000 No’s Completed. |
|||||
5.Construction of 17 Nos (W.S Zones- 34, 35, 36, 37, 38, 39,40, 43, 44, 48, 50, 52, 54, 56, 57, 60, 70) of Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zone-III& IV area. (Package-5).
Project Cost : Rs.184.37 Crores
Date of Tender : 05.10.2018
Date of Work Order : 04.02.2019
Contract Value: Rs. 207.15 Cr.
Contractor: M/S Annai Infra Developers limited
Present Stage of Work :-95% Work Completed.
Probable Date of completion: 31.07.2025.
Expenditure So far :142.41 Crores.
| S No. | Location of Tank | Capacity | Present Stage of Work | Current Status | |
| 1 | Kovil Vazhi | 5.00LL | Completed. | Water supplied through the existing & new line. | |
| 2 | Kalipalayam | 5.00LL | Completed. | Trail Run under progress. | |
| 3 | Chennimalaipalayam | 5.00LL | Completed. | Water supplied through the new pipe line. | |
| 4 | Mahalakshmi Nagar (Vijayapuram) | 7.50LL | Completed. | Water supplied through the new pipe line. | |
| 5 | Karthik Nagar | 7.50LL | Completed. | Trail Run under progress. | |
| 6 | Krishna Nagar | 7.50LL | Completed. | Trail Run under progress. | |
| 7 | Noyyal Burial Ground | 10.00LL | Completed. | Trail Run under progress. | |
| 8 | Dharapuram Road OHT | 10.00 LL | Completed. | DMA Zone (24×7) | |
| 9 | Pudhu Palayam | 12.50LL | Completed. | Trail Run under progress. | |
| 10 | Thiru Nagar | 15.00LL | Completed. | Trail Run under progress. | |
| 11 | Kaliappa Nagar | 20.00LL | Completed. | Trail Run to be started. | |
| 12 | Santhapettai | 7.50LL | Completed. | Water tightness to be started. | |
| 13 | TSK Maragathammal | 7.50LL | Completed. | Trial run under progress. | |
| 14 | Cattle Shed | 10.00LL | Completed. | Trail Run under progress. | |
| 15 | State Bank colony | 15.00LL | Completed. | Valve chamber work to be started | |
| 16 | Masaniyamman Koil | 15.00LL | Completed. | Valve chamber work under progress. | |
| 17 | Andipalayam (SR Nagar) | 12.50LL | Completed. | Inter connection work under progress. |
| Sl.No. | Name of the component | Qty | Current Status | |||||
| 18 | Distribution System Km | |||||||
|
HDPE Pipe 225mm dia to 110mm dia |
344.184/435.88 Km |
Pipe Size | Estimate (Km) | Revised (Km) | Supply (Km) | Laid (Km) | Balance (Km) | |
| 110mm HDPE | 289.136 | 371.96 | 366.45 | 365.01 | 6.95 | |||
| 160mm HDPE | 51.676 | 61.80 | 58.40 | 56.83 | 4.96 | |||
| 225mm HDPE | 3.372 | 2.12 | 3.37 | 2.12 | – | |||
| Total | 344.184 | 435.88 | 428.22 | 423.97 | 11.91 | |||
|
DI – K7 Pipes 700mm dia to 200mm dia |
215.588/140.70 km |
Pipe Size | Estimate (Km) | Revised (Km) | Supply (Km) | Laid (Km) | Balance (Km) | |
| 200mm DI | 74.501 | 52.21 | 51.27 | 48.44 | 3.77 | |||
| 250mm DI | 15.795 | 14.46 | 13.81 | 13.80 | 0.65 | |||
| 300mm DI | 45.790 | 23.47 | 24.45 | 23.40 | 0.07 | |||
| 350mm DI | 9.594 | 7.59 | 8.00 | 7.59 | – | |||
| 400mm DI | 38.627 | 23.22 | 23.89 | 22.22 | 1.00 | |||
| 450mm DI | 2.895 | 2.82 | 2.75 | 2.69 | 0.12 | |||
| 500mm DI | 27.410 | 16.92 | 17.70 | 15.71 | 1.21 | |||
| 600mm DI | 0.810 | – | – | – | – | |||
| 700mm DI | 0.166 | – | – | – | – | |||
| Total | 215.588 | 140.70 | 141.87 | 133.86 | 6.83 | |||
| Grand Total | 559.772/
576.59 Km |
559.772 | 576.59 | 570.10 | 557.84 | 18.75 | ||
| 19 | Chlorination Plants | 17 Nos | 17 Nos Shed work completed. | |||||
| 20 | House Service Connections | 59883/25020 | 24566 No’s Completed.
HSC Water Meter 13228 No’s Completed. |
|||||
- 6. Transforming the existing intermittent water supply to continuous 24×7 water supply distribution system for the water zone 30 & 50 in Tiruppur City Municipal Corporation – Period of Completion 12 months followed by 3 months Trial Run and Commissioning. (Package-6)
Project Cost : Rs. 53.57 Cr
Date of Tender : 18.01.2023
Date of Work Order : 07.07.2023
Contract Value: Rs.37.29 Cr.
Contractor: M/S Eco Protection Engineers Pvt Ltd.
Date of agreement: 07.07.2023
Probable Date of completion: 30.09.2025.
Present Stage of Work : 80 % Work Completed.
Expenditure So far :34.69 Crores
| Sl.N
o. |
Name of the component | Qty | Current Status | ||||||
|
1 |
HDPE Pipe 225mm Dia to 110mm Dia |
56.991 Km |
Pipe Size | Estimate (Km) | Revised (Km) | Supply (Km) | Laid (Km) | Balance ( km) | Hydra ulic Tested in
(Km) |
| 110mm HDPE | 49.265 | 54.766 | 50.86 | 50.86 | 3.906 | 4.862 | |||
| 160mm HDPE | 5.056 | 5.32 | 5.32 | 5.32 | – | 0.314 | |||
| 225mm HDPE | 2.67 | 2.67 | 2.67 | 2.67 | – | – | |||
| Total | 56.991 | 62.75 | 58.85 | 58.85 | 3.906 | 5.176 | |||
|
2 |
DI pipe 300 mm Dia to 500 mm Dia |
3.997 Km |
200 mm DI | 0.397 | 0.397 | 0.396 | 0.391 | 0.06 | – |
| 250 mm DI | 0.538 | 0.640 | 0.640 | 0.620 | 0.02 | – | |||
| 300 mm DI | 0.633 | 0.649 | 0.649 | 0.649 | – | – | |||
| 350 mm DI | 1.670 | 1.683 | 1.683 | 1.651 | 0.082 | 0.684 | |||
| 450 mm DI | 0.596 | 0.605 | 0.605 | 0.605 | – | – | |||
| 500 mm DI | 0.163 | 0.240 | 0.240 | 0.240 | – | – | |||
| Total | 3.997 | 4.21 | 4.21 | 4.156 | 0.054 | 0.684 | |||
| Grand Total | 60.988
Km |
60.988 | 66.96 | 63.06 | 63.006 | 3.96 | 5.86 | ||
| 3 | House service connection | 8400 Nos | 9887 | 8630 Nos completed | |||||
| 4 | AMR water meter | 8400 Nos | 9887 | 8390 Nos completed. | |||||
| S.NO | NAME OF THE COMPONENT | QTY | CURRENT STATUS | |
| NO OF DMA ZONES – 10 | ||||
| 1 | DMA Entry point – Inside DMA: | |||
| a) | Electromagnetic flow meter. | 10 Nos | 9 Nos completed. | |
| b) | Sluice valve / for isolation & scouring. | 75 Nos | 61 Nos completed | |
| c) | Pressure Transmitter & solar PLC control panel with data logger. | 20 Nos | 18 Nos completed. | |
| d) | Water Quality sensor for monitoring chlorine level, PH, conductivity with control panel. | 20 Nos | 14 Nos completed. | |
| e) | Pressure reducing valve (PRV) | 4 Nos | – | |
| f) | PLC control panel with ups with DMA entry & inside DMA. | 38 Nos | 38 completed. | |
| G | Flow Control Valve | 12 Nos | P.O placed. | |
| 2 | ESR OUTLET – 2: | |||
| a) | Electromagnetic flow meter. | 2 Nos | Completed | |
| b) | Sluice valve / for isolation control. | 4 Nos | Completed | |
| c) | Pressure Transmitter. | 2 Nos | Completed | |
| d) | Water Quality sensor for monitoring chlorine level, PH, conductivity with control panel. |
2 Nos |
Completed | |
| e) | PLC control panel with ups. | 2 Nos | Completed | |
| 3 | Monitoring centre infrastructure | |||
| a) | Split Air conditioner | 1 Nos | Completed | |
| b) | PC hardware | 2 Nos | Completed | |
| c) | Software-pc operating system. | 2 Nos | Completed | |
| d) | PC rack panel | 1 Nos | Completed | |
| e) | Laser projector with high brightness screen. | 1 Nos | Commissioning completed | |
| f) | LED – TV – 40-inch display unit | 1 Nos | Commissioning completed | |
| 4 | Information retrieval system | |||
| a) | PC – client | 2 Nos |
– |
|
| b) | PC- application software | 2 Nos | ||
| 5 | Mobile hand-held display unit | |||
| a) | Android application software | 3 Nos | ||
| S.no | Description | Zone | Pipeline status | SEMI status | Hsc status | Amr water meter status | Remarks |
| 1 | DMA -1 | Z-50 &
w- 42,43,45 |
completed | completed | completed | completed | Trial run under progress |
| 2 | DMA -2 | completed | completed | completed | completed | ||
| 3 | DMA – 3 | completed | completed | completed | completed | ||
| 4 | DMA -4 |
Z-30 & w- 24,25,26, 9, 47 |
completed | completed | completed | completed | Trial run under progress |
| 5 | DMA -5 | completed | completed | completed | completed | ||
| 6 | DMA -6 | completed | completed | completed | completed | ||
| 7 | DMA -7 | completed | completed | completed | completed |
valve erection under progress completed as on 30-05-25 |
|
| 8 | DMA -8 | completed | completed | completed | completed | ||
| 9 | DMA – 9 | completed | completed | completed | completed | ||
| 10 | DMA -10 | completed | completed | completed | completed | ||
| 11 | OHT compound | ||||||
| wall | |||||||
| Head works | Under supplemental | ||||||
| compound wall, | item, work started, | ||||||
| 12 | Road works,
street lights and |
Materials Procument
in progress. |
|||||
| land scapping | |||||||
| works |
AMRUT-2017-20
Under Ground Sewerage Scheme
1.Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 5, 6 and 7 (Package – 1).
Project Cost : Rs.381.22 Crores
Date of Tender : 05.10.2018
Date of Work Order : 10.07.2020
Contract Value: Rs.320.22 cr.
Contractor: M/S Eco Protection Engineers Pvt Ltd.
Date of agreement: 10.07.2020
Probable Date of Completion: 31.0.2025
Present Stage of Work : 98% Work Completed.
Expenditure So far : 346.95Crores
| Sl.
No. |
Name of the component | Agreement/Revised Qty | Current Status | ||||
| 1 | Collection System (Km) | Estimated Qty | Revised Qty | Supply Qty | Laid Qty | Balance Qty | |
| uPVC Pipes 200mm Dia | 216.381/214.404 Km | 216.381
Km |
214.404
Km |
214.404
Km |
214.404
Km |
– | |
| DWC Pipes 350mm Dia to 200mm Dia | 33.886/30.627 Km | 33.886
Km |
30.627
Km |
30.627
Km |
30.627
Km |
– | |
| CI Pipes LA class 1200mm Dia to 350mm Dia | 20.135/25.393 Km | 20.135
Km |
25.393
Km |
25.393
Km |
25.393
Km |
– | |
| Total | 270.402/270.424 Km | 270.402
Km |
270.424
Km |
270.424
Km |
270.424
Km |
– | |
| 2 | Manholes (Nos) | 11380/11024 Nos | 11380 Nos | 11024 | 11024 | 11024 | – |
| 3 | House Service connection | No’s up to Outside Boundary completed | 42008 Nos | 28000Nos | – | 27907Nos | 93 Nos |
| No’s up to inside Boundary completed | 42008 Nos | 28000Nos | – | 26590Nos | 1410 Nos | ||
| No’s inter connection completed | 42008 Nos | 28000Nos | – | 25758Nos | 2242 Nos | ||
| 4 | Lifting Station | 14/16 Revised | 1. Nettikattipalayam (Zone 5.2) Completed.
2. Srinagar (Zone 5.1) Completed. 3. M.G.R colony (Zone 6.2) Completed. 4. C.B.N.Palayam(Zone 6)Completed. 5. Palanisamy Nagar (Zone 5) Completed. 6. Thottathupalayam(zone5.1) Completed. 7. Bommainaickenpalayam (Zone 6.2) Completed. 8. Thanner Panthal (Zone 7.6) completed. 9. Avinashi Nagar (Zone 6.1) Completed. 10. Poondi Road (Zone 7.2) Completed. 11. Sirupuluvapatti (Zone 7.6) Completed. 12. Sandaipettai (Zone 7.4) Completed. 13. Angeripalayam Sugam Nagar (Zone 7.4) Civil work completed. Pumpset erection inprogress. 14. Kavitha Lakshmi nagar Extn (Zone 7.4) To be started. 15. Ambedkar Street (Zone 5.1) Completed. 16. Nallappa Nagar (Zone 7.1) Completed |
||||
| 5 | Sewage Pumping stations | 4 | 1.Nanjarayan Nagar MPS 5 –Sewage Pumping under progress.
2.Indira Nagar SPS-6– Sewage Pumping under progress. 3.Madheswaran Kovil SPS-7– Sewage Pumping under progress. 4.Sakthinagar MPS 7.5– Sewage Pumping under progress. |
||||
| 6 | Pumping Mains CI Pipes 200 mm Dia to 750 mm Dia | 21.258/26.56 Km | 26.56 km supplied 26.56 km laid. | ||||
| 7 | Road Restoration work (Km) | 50.857/41.050
Km |
41.050 Km Completed. | ||||
2.Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer zones 8, 13 and 14 and Expansion of the existing STP at Sarkar- periyapalayam and Rejuvenation of Existing SPS & MPS (Package – 2).
Project Cost : Rs.132.95 Crores
Date of Tender : 03.10.2018
Date of Work Order : 04.02.2019
Contract Value: Rs.103.01 Cr.
Contractor: M/S Keyem Infra Project Private Limited
Date of agreement: 04.02.2019
Probable Date of Completion: 31.07.2025
Present Stage of Work : 95 % Work Completed.
Expenditure So far :116.30 Crores
| Sl.No. | Name of the component | Agreement/Revised Qty | Current Status | ||||
| 1 | Collection System (Km) | Estimated Qty | Revised Qty | Supply Qty | Laid Qty | Balance Qty | |
| uPVC Pipes 200mm Dia | 85.39/91.25 Km | 85.39 Km | 91.25Km | 91.25Km | 91.25
Km |
– | |
| DWC Pipes 350mm Dia to
200mm Dia |
13.405/10.64 Km | 13.405 km | 10.64 km | 10.64 km | 10.64
km |
– | |
| CI Pipes LA class 1200mm Dia to 350mm
Dia |
4.927/6.17 Km | 4.927 Km | 6.17km | 6.17km | 6.17
Km |
– | |
| Total | 102.93/108.06 Km | 102.93Km | 108.06Km | 108.06Km | 108.06Km | – | |
| 2 | Manholes (Nos) | 4374/4381 Nos | 4374 Nos | 4381 Nos | 4381
Nos |
– | |
| 3 | House Service connection | No’s up to Outside Boundary completed | 17803 Nos | 17803
Nos |
– | 17803
Nos |
– |
| No’s up to inside Boundary completed | 17803 Nos | 17803
Nos |
– | 17803
Nos |
– | ||
| No’s inter connection completed | 17803 Nos | 17803
Nos |
– | 10595
Nos. |
7208
Nos |
||
| 4 | Lifting Station | 5/9 Revised | 1. Vanjipalayam Main Road (Zone8) Completed all works. EB power supply obtained. Commissioning started. | ||||
| 2. Bhavani Nagar 4th Street (Zone 13) Completed all works. EB power supply obtained. Commissioning started. | |||||||
| 3. TVK Nagar College Road (Zone 14) Completed all works. EB power supply obtained. Commissioning started. | |||||||
| 4. Sanjay Nagar- Completed all works. EB power supply obtained. Commissioning started. | |||||||
| 5. Chikanna College- Completed all works. EB power supply obtained. Commissioning started.
6. Kattabomman Nagar- Completed all works. EB power supply obtained. Commissioning started. 7. Jeeva Nagar- Completed all works. EB power supply obtained. Commissioning started. 8. Perumal Koil Street- Completed all works. Awaiting for EB supply. 9. Kavilipalayam- Completed all works. EB power supply obtained. Commissioning started. |
|||||||
| 5 | Sewage Pumping stations | 2 | 1. Kattabomman Nagar– Civil work & Pumpset erection completed. EB power supply obtained. Commissioning started.
2. Anaipalayam, Jayalalitha Nagar– Civil work & Pumpset erection completed. Awaiting for EB supply. Commisioning started with DG Power Supply |
||||
| 6 | Pumping Mains CI Pipes
600mm Dia & 400mm Dia |
6.930Km | 6 6.930 Km supplied; 6.930 Km Laid. Completed | ||||
| 7 | Road Restoration work (Km) | 47.816/48.14 Km | 48.14Km Completed. | ||||
| 8 | Improvement of existing STP 15MLD | 1 | Aerator and Clarifier civil work completed.
Pump Erection work completed. CEIG Clearance Obtained. |
||||
3.Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 9, 15, 16 and 17 (Package – 3)
Project Cost : Rs.167.12 Crores
Date of Tender : 03.10.2018
Date of Work Order : 04.02.2019
Contract Value: Rs.118.35 Cr.
Contractor: M/S Keyem Infra Project Private Limited
Date of agreement: 04.02.2019
Probable Date of Completion: 31.07.2025
Present Stage of Work : 95 % Work Completed.
Expenditure So far :117.14 Crores
| Sl.No. | Name of the component | Agreement/Revised Qty | Current Status | ||||
| 1 | Collection System (Km) | Estimated Qty | Revised Qty | Supply Qty | Laid Qty | Balance Qty | |
| uPVC Pipes
200mm Dia |
132.672/133.75 Km | 132.672
Km |
133.75
Km |
133.75
Km |
133.680
Km |
0.07 Km | |
| DWC Pipes 350mm Dia
to 200mm Dia |
19.948/19.392 Km | 19.948
Km |
19.392
Km |
19.392
Km |
19.392 Km | – | |
| CI Pipes LA class 1200mm
Dia to 350mm Dia |
9.078/12.655 Km | 9.078 Km | 12.655Km | 12.655Km | 12.655Km | – | |
| Total | 161.69 /165.797 Km | 161.69
Km |
165.797
Km |
165.797
Km |
165.727
Km |
0.07 Km | |
| 2 | Manholes (Nos) | 5758/6417 Nos | 5758 Nos | 6417 Nos | – | 6417 Nos | – |
| 3 | House Service connection | No’s up to Outside Boundary completed | 17032
Nos |
– | 17032 Nos | – | |
| No’s up to inside Boundary completed | 17032
Nos |
– | 17032 Nos | – | |||
| No’s inter connection completed | 17032
Nos |
– | 10817 No’s | 6215Nos | |||
| 4 | Lifting Station | 8/16 revised | 1. Idumban Nagar (Zone 9.1) Civil work & Pumpset erection completed. Awaiting for EB supply.
2. Vinayagapuram (Zone 15.1) Civil work & Pumpset erection completed. Electrical work completed. obtained EB supply. 3. Muthu nagar – All work completed. EB supply obtained. 4. Kulathu pudur Main Road (Zone 9.1) Civil work & Pumpset erection completed. Electrical completed. Awaiting for EB supply. 5. Kullegoundan pudur cross street (Zone 9.1) Civil work completed, Pumpset erection completed. Electrical work completed. Awaiting EB supply. 6. North Thottam (Zone 15.2) Civil work & Pumpset erection completed. obtained EB supply. 7. Sugumar Nagar (Zone 17.1) Civil work completed. Pumpset completed. Awaiting EB supply. 8. Sakthi colony-Palayakadu (one 17.2) Civil work completed. Pumpset erection completed. 9. Chinnandipalayam STP Site- Civil work & Pumpset erection completed. Electrical work completed. Trail run under progress. 10. Kallampalayam 207/15-1- Civil work completed. Pumpset erection under progress. 11. Meenachiamman Koil- Civil work completed. Pumpset erection competed. 12. Iduvai Road-Sidewall- civil work completed. 13. Pattukottaiyar Nagar- Civil work completed. Pumpset erection under progress. 14. Kumarappapuram – Civil work completed. Pumpset erection under progress. 15. Sivasakthi Nagar – Pumpset erection completed. Electrical work completed. Awaiting for EB supply. Thennampalayam – Civil work completed. Pumpset erection to be started. |
||||
| 5 | Sewage Pumping stations | 3 | 1. Karumarampalayam Completed all works. Awaiting for EB supply.
2. SR Nagar North (Zone 9)- Completed all works. Obtained EB supply. Commissioning started. 3. Pattukottaiyar Nagar – Completed all works. Awaiting for EB supply. |
||||
| 6 | Pumping Mains CI Pipes 500mm Dia ,400 &
300mm Dia |
10.70Km | 10.70 Km supplied; 10.70 Km Laid. | ||||
- Design and Construction of Sewage Treatment Plant of capacity 36 MLD in Sarkarperiyapalayam and 20 MLD in Chinnandipalayam including 10 years of operation and maintenance on DBOT basis for UGSS in Tiruppur City Municipal Corporation.
Project Cost: Rs.72.57 Crores
Date of Tender: 03.10.2018
Date of Work Order: 28.02.2019
Contract Value: Rs.71.57 Cr.
Contractor: M/S Eco Protection Engineers Pvt Ltd.
Date of agreement: 28.02.2019
Date of completion: 30.11.2022
Present Stage of Work : 100 % Work Completed.
Expenditure So far :70.72 Crores
| Sl.No.
|
Name of the component | Qty | Current Status |
| 1 | Plant and Mandatory spare parts
supplied from within the employer’s country |
1No | 100 % of equipment’s has been supplied |
| 2 | Design Services | 1No | Completed |
| 3 | i) 36MLD STP
Sarkarperiyapalayam |
1No | 1. SBR: All Works completed
2. CCT: All works completed.
3. Tonner Room: All works completed.
4. Gravity Thickener: All works completed.
5. Air blower House: All Works completed.
6. Sludge Sump with pump House: All works completed.
7. Admin Building & MCC Building: All works completed.
8. Centrifuge Building: All works completed. 9. Pre- Treatment Unit (PTU): All works completed.
10. Internal Road work, drainage work and Gate Arch: Completed * CTO obtained on 28.11.2022 from TNPCB
Fully running up to collected from 25758 of HSC. Sewage Inlet flow 392.676 ML received and treated 387.285 ML treated out flow in May month. Average of 12.667 MLD Inlet, 12.493 MLD Treated outlet. |
| ii) 20MLD STP
Chinnandipalayam |
1. SBR: Completed
2. Gravity Thickener: Completed. 3. Centrifuge: Completed. 4. Sludge sump cum pumphouse: Completed. 5. Thickened Sludge Sump& Centrate and Overflow Sump: Completed. 6. CCT: Completed. 7. Tonner Room: Completed. 8. Admin Building & MCC Building: Completed. 9. Air Blower Building: Completed.
10. Pre- Treatment Unit (PTU): Completed.
11. Internal Road work with Drainage and Gate Arch: Completed.
* CTO obtained on 12.12.2023 from TNPCB.
Fully running up to collected from 9457 HSC. Sewage Inlet flow 36.16 ML received and treated 35.51 ML treated out flow in May month. Average of 1.166 MLD Inlet, 1.145 MLD Treated outlet. |
||
| 4 | Operation & Maintenance | 1No | – |
AMRUT-2.O (2023-24)
Under Ground Sewerage Scheme
Providing Comprehensive Underground Sewerage Scheme to Added areas (zone -11, 11.1 & 11.3) in Tiruppur City Municipal Corporation including 60 months of Operation and Maintenance
Project Cost : Rs.192.95 Crores
Date of Tender : 18.03.2024
Date of Work Order : 17.10.2024
Contract Value: Rs.190.19 cr.
Contractor: M/S Eco Protection Engineers Pvt Ltd.
Date of agreement: 11.11.2024
Probable Date of Completion: 16.10.2027
Present Stage of Work : 28% Work Completed.
Expenditure So far : 23.01 Crores
| Components As per Agreement | Progress | |
| Main & Sub pumping station (Nos) | 3 | 1 Station- RCC Wall 4th lift Shuttering Work under progress. 1 Station CETP Pipe line Shifting work under progress.1 Station Public Objection. |
| Lift Manholes (Nos) | 7 | 3 Station Civil work Completed. 2 Station work under progress. 1 Stations to be started. 1 Station Private Land issue. |
| Sewer Line in KM | 109.87 | 106.20Km pipe supplied and 30.54Km Laid. Balance 79.33 Km. |
| Machine holes (Nos) | 4177 | 1360 Nos Erected. Balance 2817 Nos. |
| No.of HSCs (Nos) | 16708 | HSC’s – 1080Nos laid. Balance 15628Nos. |
| Pumping Main in KM | 9.72 | 150mm to 900mm CI Pipes – 5.311 Km Pipe Supplied and 2.21 Km laid. Balance 7.50Km. |