AMRUT – UGSS INCENTIVE – CORPORATION STAFF AND ELECTED REPRESENTATIVE’S DETAILS
AMRUT Scheme
Water Supply-Source Improvement & Distribution System
- Construction of Raw Water Intake well, Pump House with Surge Protection Tank, Supply and installation of Pump set and motors with all electrical works in Bhavani River bank at Mettupalayam and Supplying, Laying and Jointing of Pumping Main from Raw Water Intake to Water Treatment Plant near Annur including Pipe Carrying Bridges wherever necessary(Package– 1).
Estimate Amount: Rs.101.00 Crores
Date of Tender: 05.10.2018
Date of Work Order: 28.02.2019
Present Stage of Work – 100%
Date of completion: 27.02.2023
Sl.No | Name of the component | Qty | Current Status | ||
I | Head Works | ||||
Raw Water Intake Well | 1 No. | Completed. | |||
River bank Protection works | 150 m | Completed. | |||
Connecting Pipe 1800 mm MS Pipe between Intake well to Sump | 26 M X 2 | Completed. | |||
Raw Water Sump cum pump house | 1 No. | Completed. | |||
2 | Electro mechanical Items | Trail Run under progress. | |||
Supply, delivery and erection of raw water Vertical Turbine pump sets | 6 Nos. | Trail Run under progress. | |||
Electrical installations | 1 No. | Completed. | |||
3 | Surge Protection Tank | 1 No. | Completed. | ||
4 | Raw water main | Completed. | |||
1422 mm dia x 12 mm MS Pipe | 19.27 KM | Supply | Laid | Hydraulic Test | |
19.82 Km | 19.97Km | 19.83 Km | |||
Trail Run Pumping from Headworks to WTP | 16345.00 ML Total Raw water pumped from 01.01.2023 to 29.11.2023 |
Expenditure So far :126.31Crores
Construction of Water treatment Plant of Capacity 196 MLD expandable to 270 MLD with complete SCADA system for the entire Project on Design Build, Operate and Transfer basis for new water supply scheme In Tiruppur City Municipal Corporation. Period of Completion 24 Months followed by 6 Months trail run and commissioning.(Package – 2).
Estimate Amount : Rs.82.94 Crores
Date of Tender :05.10.2018, 18.01.2019.
Date of Work Order : 28.06.2019
Present Stage of Work :100 %
Date of completion: 30.09.2022
Sl.No | Name of the component | Qty | Current Status |
1 | Basic Engineering package | 1 No. | Approved |
Hydraulic design | 1 No. | Approved | |
Structural design for Clear Water reservoir | 1 No. | Approved | |
Clear Water Reservoir | 1 No. | Completed. | |
2 |
Flocculator& Inclined plate settler | 1 No. | Completed. |
3 | Sludge Conditioner tank | 1 No. | Completed. |
4 | Sludge Thickener Unit | 1 No. | Completed. |
5 | Chlorination Building | 1 No. | Completed. |
MCC Room | 1 No. | Completed. | |
|
Chemical House | 1 No. | Completed. |
Filter House | 1 No | Completed. | |
Back wash water Recirculation sump | 1 No | Completed. | |
Aerator | 1 No | Completed. | |
Raw Water Channel | 1 No | Completed. | |
Back Wash Water Pump Room | 1 No | Completed. | |
Administration Building | 1 No | Completed. | |
Centrifuge Building | 1 No | Completed. | |
Internal Drainage, Compound wall and Road formation | 1 No | Completed. | |
Clear Water Discharge from WTP (Trail Run) | 16253 ML Total Clear water Discharged WTP from 01.01.2023 to 29.11.2023 |
Expenditure So far :91.41Crores.
- Supplying, Laying and Jointing Clear Water Gravity Main from Water Treatment Plant to OHTs in Tiruppur Corporation including Pipe Carrying Bridges wherever necessary.(Package – 3).
Estimate Amount : Rs.356.00 Crores
Date of Tender :05.10.2018
Date of Work Order: 03.06.2019
Present Stage of Work: PHYSICAL PROGRESS–100 %, Date of completion: 15.11.2022
Name of the component | Qty (km) | Current Status | |||
Clear water Gravity Transmission main | |||||
MS Pipes
1829 mm Dia to 610 mm Dia Total-78.820Km |
Pipe Size | Estimate
(Km) |
Supply | Laid | Hydraulic Test |
1829 mm dia MS pipe | 20.02 | 20.018 | 20.018 | 20.00 | |
1626mm dia MS Pipe | 18.210 | 17.180 | 17.180 | 17.180 | |
1118mm dia MS Pipe | 4.720 | 4.720 | 4.720 | 4.706 | |
914mm dia MS Pipe | 4.310 | 7.857 | 7.857 | 7.855 | |
813mm dia MS Pipe | 13.190 | 9.526 | 9.526 | 9.489 | |
711mm dia MS Pipe | 9.410 | 9.367 | 9.367 | 9.366 | |
610mm dia MS pipe | 8.980 | 8.910 | 8.910 | 8.870 | |
Total | 78.84 | 77.578 | 77.578 | 77.466 | |
DI – K7 Pipes
500 mm Dia to 150 mm Dia Total-69.486Km |
Pipe Size | Estimate
(Km) |
Supply | Laid | Hydraulic Test |
500mm dia DI Pipe | 8.596 | 10.347 | 10.347 | 10.347 | |
450mm dia DI Pipe | 2.970 | 2.970 | 2.970 | 2.970 | |
400mm dia DI Pipe | 14.179 | 13.791 | 13.791 | 13.491 | |
350mm dia DI Pipe | 9.966 | 9.966 | 9.966 | 9.946 | |
300mm dia DI Pipe | 15.119 | 15.119 | 15.119 | 15.087 | |
250mm dia DI Pipe | 11.097 | 6.993 | 6.993 | 6.949 | |
200mm dia DI Pipe | 7.184 | 6.064 | 6.064 | 6.064 | |
150mm dia DI Pipe | 1.925 | 1.925 | 1.925 | 1.888 | |
Total | 71.036 | 67.175 | 67.175 | 66.742 | |
Construction of Pipe Carrying Bridges | 10/9 | 9 No. completed. | |||
Existing OHT Inlet pipe connection | 74.153 | Water filling Existing OHTs- 39 nos. Water filling New OHTs- 12 Nos. 15 Nos New OHTs – Trail run completed up to ground level. |
Expenditure So far :402.11Crores
Construction of 12 Nos (W.S Zones- 2, 3, 4, 8, 22, 23, 26,28, 29, 30, 31, 32) Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zones-I & II area. (Package – 4).
Estimate Amount: Rs.185.00 Crores
Date of Tender : 05.10.2018
Date of Work Order : 01.03.2019
Present Stage of Work :PHYSICALPROGRESS-92%
S No. | Location of Tank | Capacity | Present Stage of Work |
1 | Pandian Nagar | Roof slab completed. | Colour Washing & Trail run work under progress |
2 | MatheswaranKoil 1 | Roof slab completed. | Finishing work & Trail run under progress |
3 | MatheswaranKoil 2 | Roof slab completed. | Finishing work under progress |
4 | Thiru vi kanagar | Roof slab completed. | Colour Washing work under progress |
5 | G.N Garden | Roof slab completed. | Colour Washing work & Trail run under progress |
6 | Sneha Nagar | Roof slab Completed. | Colour Washing work under progress |
7 | NRK Puram | Roof slab completed. | Colour Washing work under progress |
8 | Kumar Nagar | 2nd brace work completed. | Above 2nd brace Steel work Under progress |
9 | Kumar Nagar | 3rd brace completed. | Above 3rd Brace Column box fixing work under progress. |
10 | Bharatiyar Complex | 1st lift of sidewall Completed | 2nd lift of sidewall work under progress. |
11 | Palayakadu | Roof slab completed. | Colour Washing work under progress |
12 | Gate Thottam | Floor slab work under progress. | Floor slab Steel work under progress. |
Sl.No. | Name of the
component |
Qty | D-System Current Status | ||||||||||||||
13 | HDPE Pipe
225mm dia to 110mm dia |
330.788Km | Pipe Size | Estimate
(Km) |
Revised (Km) | Supply
(Km) |
Laid
(Km) |
Remarks | |||||||||
110mm
HDPE |
317.408 | 476.907 | 456.504 | 448.852 | 70.969Km
Tested |
||||||||||||
160mm
HDPE |
10.008 | 10.00 | 10.008 | 10.00 | 2.906Km
Tested |
||||||||||||
225mm
HDPE |
3.372 | 1.592 | 2.004 | 1.592 | |||||||||||||
Total | 330.788 | 488.499 | 468.516 | 460.444 | 73.875Km
Tested |
||||||||||||
Sl.No. | Name of the
component |
Qty | D-System Current Status | ||||||||||||||
DI – K7 Pipes 700mm dia to 200mm dia | 171.869Km | Pipe
Size |
Estimate
(Km) |
Revised
(Km) |
Supply
(Km) |
Laid
(Km) |
Remarks | ||||||||||
200mm
DI |
37.745 | 24.028 | 29.581 | 22.512 | 4.258Km
Tested |
||||||||||||
250mm
DI |
6.043 | 6.040 | 6.043 | 6.040 | 0.462Km
Tested |
||||||||||||
300mm
DI |
51.733 | 29.722 | 33.365 | 28.731 | 3.397Km
Tested |
||||||||||||
350mm
DI |
9.452 | 7.819 | 8.508 | 7.601 | 2.043Km
Tested |
||||||||||||
400mm
DI |
28.611 | 18.959 | 25.126 | 16.842 | 4.288Km
Tested |
||||||||||||
450mm
DI |
0.104 | 0.095 | 0.104 | 0.095 | – | ||||||||||||
500mm
DI |
25.457 | 15.963 | 17.964 | 14.454 | 2.906Km
Tested |
||||||||||||
600mm
DI |
12.558 | 12.589 | 11.638 | 9.571 | 2.423Km
Tested |
||||||||||||
700mm
DI |
0.166 | – | – | – | |||||||||||||
Total | 171.869 | 115.215 | 132.329 | 105.848 | 19.78km
Tested |
||||||||||||
14 | Chlorination
Plants |
12Nos | – | ||||||||||||||
15 | House Service Connections | 57553/41000 | 40133 No’s completed.
HSC Water Meter 19716 No’s Completed. |
||||||||||||||
Expenditure So far :152.54Crores.
Construction of 17 Nos (W.S Zones- 34, 35, 36, 37, 38, 39,40, 43, 44, 48, 50, 52, 54, 56, 57, 60, 70) of Elevated Service Reservoirs with Chlorination facility and providing Distribution system including HSC in Corporation Zone-III& IV area. (Package-5).
Estimate Amount : Rs.195.00 Crores
Date of Tender : 05.10.2018
Date of Work Order : 04.02.2019
Present Stage of Work :Physical Progress: 91 %
S No. | Location of Tank | Capacity | Present Stage of Work | |||||||||
1 | KovilVazhi | 5.00LL | Completed. | |||||||||
2 | Kalipalayam | 5.00LL | Pipe Connection work under progress | |||||||||
3 | Chennimalaipalayam | 5.00LL | Trail Run under progress. | |||||||||
4 | Mahalakshmi Nagar (Vijayapuram) | 7.50LL | Trail Run under progress. | |||||||||
5 | Karthik Nagar | 7.50LL | Pipe Connection work under progress | |||||||||
6 | Krishna Nagar | 7.50LL | Completed. | |||||||||
7 | Noyyal Burial Ground | 10.00LL | Colour Washing work to be started. | |||||||||
8 | Dharapuram Road OHT | 10.00 LL | Finishing work & Pipe
Connection work under Progress |
|||||||||
9 | PudhuPalayam | 12.50LL | Pipe Connection work under Progress | |||||||||
10 | Thiru Nagar | 15.00LL | Colour Wash to be started | |||||||||
11 | Kaliappa Nagar | 20.00LL | Finishing work & Pipe
Connection work under Progress |
|||||||||
12 | Santhapettai | 7.50LL | Above 3rd brace Columnwork under progress. | |||||||||
13 | TSK Maragathammal | 7.50LL | Finishing work & Pipe
Connection work under Progress |
|||||||||
14 | Cattle Shed | 10.00LL | Finishing work under progress | |||||||||
15 | State Bank colony | 15.00LL | Finishing work & Pipe
Connection work under Progress |
|||||||||
16 | MasaniyammanKoil | 15.00LL | Floor slab work under progress | |||||||||
17 | Andipalayam (SR Nagar) | 12.50LL | Floor slab work under progress | |||||||||
Sl.No. | Name of the
component |
Qty | Current Status | |||||||||
18 | Distribution System Km | |||||||||||
HDPE Pipe 225mm dia to 110mm dia | 344.184Km | Pipe
Size |
Estimate (Km) | Revised
(Km) |
Supply
(Km) |
Laid
(Km) |
||||||
110mm
HDPE |
289.136 | 347.485 | 337.590 | 320.555 | ||||||||
160mm
HDPE |
51.676 | 58.454 | 58.43 | 52.105 | ||||||||
225mm
HDPE |
3.372 | 3.372 | 3.372 | 2.120 | ||||||||
Total | 344.184 | 409.311 | 399.392 | 374.78 | ||||||||
DI – K7 Pipes
700mm dia to 200mm dia |
215.588km | Pipe
Size |
Estimate (Km) | Revised
(Km) |
Supply
(Km) |
Laid
(Km) |
||||||
200mm
DI |
74.501 | 50.32 | 51.266 | 50.25 | ||||||||
250mm
DI |
15.795 | 13.868 | 10.252 | 10.429 | ||||||||
300mm
DI |
45.790 | 21.440 | 24.454 | 20.006 | ||||||||
350mm
DI |
9.594 | 8.002 | 6.965 | 6.44 | ||||||||
400mm
DI |
38.627 | 23.890 | 17.061 | 17.061 | ||||||||
450mm
DI |
2.895 | 2.895 | 2.750 | 2.750 | ||||||||
500mm
DI |
27.410 | 17.699 | 14.191 | 12.143 | ||||||||
600mm
DI |
0.810 | – | – | – | ||||||||
700mm
DI |
0.166 | – | – | – | ||||||||
Total | 215.588 | 138.114 | 126.939 | 119.079 | ||||||||
19 | Chlorination Plants | 17 Nos | – | |||||||||
20 | House Service
Connections |
59883/27000 | 24509 No’s Completed.
HSC Water Meter 1420 No’s Completed. |
|||||||||
Expenditure So far :127.84Crores
TRANSFORMING THE EXISTING INTERMITTENT WATER SUPPLY TO CONTINUOUS 24X7 WATER SUPPLY DISTRIBUTION SYSTEM FOR THE WATER ZONE 30 & 50 IN TIRUPPUR CITY MUNICIPAL (Package – 6)
CORPORATION – Period of Completion 12 months followed by 3 months Trial Run and commissioning.
Estimate cost: Rs. 41.00 Cr Contract Value: Rs.37.29 Cr.
Contractor: M/S Eco Protection Engineers Pvt Ltd.
Date of agreement: 07.07.2023 Date of completion: 06.07.2024
PHYSICAL PROGRESS – 30 %
Sl. No. |
Name of the components | Total Qty
as per Agreement |
Progress
As on 30.11.2023 |
Scheduled date of completion |
1 | Establishment of DMAs for Water distribution network for 24×7 water supply for the wards inside Pilot zones 30 &50 | Zone -30-7 DMAs
Zone -50- 3 DMAS Total : 10 DMAs |
Work under progress | 06.07.2024 |
2 | Rehabilitation of water mains for Distribution system including Sluice valves for Isolating the sub-district including all civil works.
DI K-7 & HDPE PN -6 Pipes |
41 Km for Zone 30
19 Km for Zone 50 Total : 60 Km |
Ø Distribution Main :- 110mm HDPE Pipe -49.266 Km Pipe Supplied and 26.29 Km Laid.
Ø 160mm HDPE Pipe -5.058Km Pipe Supplied and 2.19 Km Laid.
Ø 225mm HDPE Pipe -2.67Km Pipe Supplied and 0.15 Km Laid. |
|
3 | Renewal of House service connections with AMR water meters– including Water meter Protection Box | 20 Points of Pressure & Quality
sensors – Total : 8400 |
HSC – 876 No’s Outside Boundary Completed out of 8400Nos | |
4 | Design, Supply and Installation of SCADA system required for effective management of the water supply system based on the continuous data, its analysis and management. | 1Job | Work to be Started. | |
5 | Providing leak detection equipment for carrying out active leakage control | 1Set | Work to be Started. |
Expenditure So far :11.62Crores
Under Ground Sewerage Scheme -2017-2020
- Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 5, 6 and 7 (Package – 1).
Estimate Amount : Rs.246.30 Crores
Date of Tender : 03.10.2018
Present Stage of Work :PHYSICALPROGRESS-95%
Sl.
No. |
Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVCPipes200mmDia | 216.381/214.404Km | 214.404kmsuppliedand214.404Km Laid. | |
DWCPipes350mmDiato200mmDia | 33.886/30.627Km | 30.627kmSuppliedand30.627km laid | |
CI Pipes LA class 1200mm Dia to350mmDia | 20.135/25.393Km | 25.393kmsuppliedand25.393Kmlaid | |
2 |
Manholes (Nos) |
11380/11024Nos | 11024NosCastedand11024Noserected |
3 | House Service connection | 23000
42008Nos |
21599 No’s up to Boundary Completed.
12607 No’s up to inside Boundary completed. 5773N o’s inter connection completed. |
4 | Lifting Station | 14/16 Revised | 1. Nettikattipalayam(Zone5.2)Completed.
2. Srinagar(Zone5.1)Completed 3. M.G.Rcolony(Zone6.2)Completed. 4. C.B.N.Palyam(Zone6)Completed. 5. PalanisamyNagar(Zone5)Completed. 6. Thottathupalayam(zone5.1)Completed.
7. Bommainaickenpalayam(Zone6.2)Completed.
8. ThannerPanthal(Zone7.6)completed.
9. AvinashiNagar(Zone6.1)Completed.
10. PoondiRoad(Zone7.2)Completed. 11. Sirupuluvapatti(Zone7.6)Completed.
12. Sandaipettai(Zone7.4)Completed. 13. AngeripalayamSugam Nagar (Zone 7.4) Civilwork completed. Pumpset erection inprogrss.
14. Kavitha Lakshmi nagarExtn (Zone 7.4) To be started.
15. AmbedkarStreet(Zone5.1)Completed.
16. NallappaNagar(Zone7.1)Completed |
5 | Sewage Pumping stations | 4 | 1. NanjarayanNagarMPS5Allworkscompleted. Sewage Pumping under progress.
2. IndiraNagarSPS-6-Allworkscompleted.Sewage Pumping under progress. 3. MadheswaranKovilSPS-7-AllWorkscompleted. Power supply obtained. SakthinagarMPS7.5-Screen,GritandSuctionwell civil work completed. E&M Work under progress. |
6 | Pumping Mains CI Pipes 200 mm Dia&750mmDia |
21.258/26.264Km |
26.56kmsupplied26.264kmlaid. |
7 | RoadRestorationwork (Km) |
50.857/41.050 Km |
41.050KmCompleted. |
Expenditure So far : 281.70Crores
- Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer zones 8, 13 and 14 and Expansion of the existing STP at Sarkar- periyapalayam and Rejuvenation of Existing SPS & MPS (Package – 2).
Estimate Amount : Rs.101.55 Crores
Date of Tender : 03.10.2018
Date of Work Order : 04.02.2019
Present Stage of Work :PHYSICALPROGRESS -93%
Sl.No. | Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVC Pipes 200mm Dia |
85.39/91.00Km |
91.00Kmsuppliedand89.52KmLaid. |
|
DWC Pipes 350mm Dia to 200mm Dia |
13.405/12.621Km |
12.621kmsuppliedand10.62kmlaid |
|
CI Pipes LA class 1200mm Dia to 350mm Dia |
4.927/6.17Km |
6.17kmSuppliedand6.052KmLaid. |
|
2 |
Manholes (Nos) |
4374Nos |
4374nos erected. |
3 | House Service connection | 17803No’s | 15238 No’s up to Boundary Completed.
10241 No’s up to inside Boundary completed. 342 N o’s inter connection completed. |
4 | Lifting Station | 5/9 Revised | 1. VanjipalayamMainRoad(Zone8)Civilwork&Pumpset erection completed. Electrical work under progress.
2. BhavaniNagar4thStreet(Zone13)Civilwork&Pumpset erection completed. Electrical work under progress. 3. TVKNagarCollegeRoad(Zone14)Civil work &Pumpset erection completed. Electrical work under progress. 4. SanjayNagar-Civilwork&Pumpseterection completed. Electrical work under progress. 5. ChikannaCollege-Civilworkcompleted. E&M under progress. 6. KattabommanNagar-Civilwork&Pumpset erection completed. Electrical work under progress. 7. JeevaNagar-Civilworkcompleted.Civil work &Pumpset erection completed. Electrical work under progress. 8. PerumalKoil Street-Civil workcompleted. E&M under progress. 9. Kavilipalayam-Civilworkcompleted.E&M under progress. |
5 | Sewage Pumping stations | 2 | 1. KattabommanNagar-Civilwork&Pumpset erection completed. Electrical work under progress..
Anaipalayam,Jayalalitha Nagar-Civil work &Pumpset erection completed. Electrical work under progress. |
6 | PumpingMainsCIPipes
600mmDia&400mmDia |
6.930Km |
6.930Kmsupplied,6.811KmLaid. |
7 |
RoadRestorationwork(Km) |
47.816 |
48.14KmCompleted. |
8 |
Improvementofexisting STP 15MLD |
1 |
AeratorandClarifiercivilworkcompleted.
PumpErectionworkunderprogress.Transformer and allied works to be started. |
Expenditure So far : 89.90Crores
- Providing Sewerage Collection System, Construction of Sub-Pumping Stations, Master Pumping Stations, Supply, laying and jointing Pumping Mains in sewer Zones 9, 15, 16 and 17 (Package – 3)
Estimate Amount : Rs.115.80 Crores
Date of Tender : 03.10.2018
Date of Work Order : 04.02.2019
Present Stage of Work :PHYSICALPROGRESS -93%
Sl.No. | Name of the component | Qty | Current Status |
1 | Collection System(Km) | ||
uPVCPipes200mmDia |
132.672 Km |
132.00Kmsupplied&132.00KmLaid. | |
DWC Pipes 350mm Dia to 200mmDia |
19.948/20.392 Km |
20.392KmSupplied&16.972KmLaid. | |
CI Pipes LA class 1200mm Dia to350mmDia | 9.078/12.498
Km |
12.498KmSupplied &11.95KmLaid. | |
2 | Manholes (Nos) | 5758/6418
Nos |
6418Nos.erected. |
3 | HouseServiceconnection | 15249Nos.uptoBoundaryCompleted. 11658Nos.inside BoundaryCompleted.
322 Nos inter Connection Completed. |
|
4 | LiftingStation | 8/16 Revised | 1.IdumbanNagar(Zone9.1)Civilwork&Pumpset erection completed. Electrical work under progress.
2.Vinayagapuram (Zone 15.1) Civil work&Pumpseterectioncompleted. Electrical work under progress. 3.Muthunagar Civilworkcompleted. Pumpset erection inprogress. 4.KulathupudurMainRoad(Zone9.1) Civil work &Pumpset erection completed. Electrical work under progress. 5.Kullegoundanpudurcrossstreet(Zone 9.1) Civil work completed. 6.NorthThottam(Zone15.2)Civilwork &Pumpset erection completed. Electrical work under progress. 7.SugumarNagar(Zone17.1)Civilwork completed. Pumpset erection in progress. 8.Sakthi colony-Palayakadu(one17.2) Civilworkcompleted. 9.Chinnandipalayam STP Site- Civil work&Pumpseterectioncompleted. Electrical work under progress. 10.Kallampalayam207/15-1-Civilwork completed. 11.MeenachiammanKoil-Civilwork completed. 12.IduvaiRoad-Civilworkinprogress. 13.PattukottaiyarNagar-Civilwork completed. 14.Kumarappapuram Civil work completed. 15.Sivasakthi Nagar Civilwork completed. 16.ThennampalayamCivilworkin progress. |
5 | SewagePumpingstations | 3 | 1. Karumarampalayam Civil work &Pumpseterectioncompleted.Electrical work under progress.
2. SRNagarNorth(Zone9)-Civilwork &Pumpset erection completed. Electrical work under progress.Progress. 3. Pattukottaiyar Nagar – Civil work &Pumpseterectioncompleted.Electrical work under progress. |
6 |
PumpingMainsCIPipes500mmDia ,400&300mmDia |
10.70Km |
10.70Kmsupplied,10.62KmLaid. |
Expenditure So far : 103.17Crores
Design and Construction of Sewage Treatment Plant of capacity 36 MLD in Sarkarperiyapalayam and 20 MLD in Chinnandipalayam including 10 years of operation and maintenance on DBOTbasis for UGSS in Tiruppur City Municipal Corporation.Estimate Amount: Rs.61.72 Crores
Date of Tender: 03.10.2018
Date of Work Order: 28.02.2019
Present Stage of Work: At 36 MLD:
PHYSICALPROGRESS 99%
Sl.No. | Name of the component | Qty | Current Status |
1 | PlantandMandatoryspareparts supplied from within the
country |
1No | 100 |
2 | DesignServices | 1No | Completed |
3 | i)36MLDSTP
Sarkarperiyapalayam |
1No |
1. SBR:AllWorkscompleted
2. CCT:Allworkscompleted.
3. TonnerRoom:Allworkscompleted.
4. GravityThickener:Allworkscompleted.
5. AirblowerHouse:AllWorkscompleted.
6. Sludge Sump with pump House: All works completed.
7. Admin Building & MCC Building:All works completed.
8. CentrifugeBuilding:Allworkscompleted. 9. Pre-TreatmentUnit(PTU):Allworkscompleted.
10. Internal Road work, drainage work and Gate Arch: Completed
* PowersupplyobtainedfromTNEB
* CTOobtainedon28.11.2022fromTNPCB
Partially running up to collected from 6800 Nos of HSC.
Average inflow – 2MLD /Day |
ii)20MLDSTP Chinnandipalayam |
1. :Completed
2. GravityThickener:Completed.
3. Centrifuge:Completed.
4. Sludgesumpcumpumphouse:Completed. 5. ThickenedSludgeSump&CentrateandOverflow Sump:Completed.
6. CCT:Completed.
7. TonnerRoom:Completed. 8. AdminBuilding&MCCBuilding:Completed.
9. AirBlowerBuilding:Completed.
10. Pre-TreatmentUnit(PTU):Completed.
11. Internal Road work with Drainage and Gate Arch: Completed. PowersupplyobtainedfromTNEB. CTO applied. Application forward to PCB Board office at Chennai . Ready to Operate. |
||
Operation&Maintenance | 1No | – |
Expenditure So far : 67.54Crores