TIRUPATTUR MUNICIPALITY
ALL SCHEMES ABSTRACT
National Urban Livelihood Mission 2017 – 18
Name of Work :- Construction of Special Shelter at Thrupathur Government Hospital Camous
(South Side) in Thirupathur Municipality
A.S.No :- CMA, Chennai Roc.No.38038 / 2013 / UPA2 dated 15.02.2018
Estimate Amount :- Rs.65.00 Lakhs
Date of Tender :- 07.02.2019
Date of Work Order :- 15.02.2019
Present Stage of Work :- Completed and put into use
Expenditure so far :- Rs.64.48 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Construction of decentralized MCC 3 TPD at Krishnagiri SH Road
– Periyar Nagar in W.No.28
A.S.No :- SBM – 7th SHPC dated 23.08.2018
Estimate Amount :- Rs.52.00 Lakhs
Date of Tender :- 22.10.2018
Date of Work Order :- 09.11.2018
Present Stage of Work :- Completed and put into use
Expenditure so far :- Rs.50.51 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Construction of decentralized MCC 3 TPD at Anna Nagar – Salem Road
in W.No.28 with compound wall and approach road.
A.S.No :- SBM – 7th SHPC dated 23.08.2018
Estimate Amount :- Rs.68.00 Lakhs
Date of Tender :- 22.10.2018
Date of Work Order :- 09.11.2018
Present Stage of Work :- Completed and put into use. Machineries erection to be done
Expenditure so far :- Rs.12.89 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Construction of decentralized MCC 3 TPD at Rettaimalai Srinivasan Street
in W.No.1 with compound wall and approach road
A.S.No :- SBM – 7th SHPC dated 23.08.2018
Estimate Amount :- Rs.60.05 Lakhs
Date of Tender :- 22.10.2018
Date of Work Order :- 09.11.2018
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.20.27 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Construction of decentralized MCC 3 TPD at Kovilur Road Egiya Layout
(Georgepettai) in W.No.3 with compound wall and approach road
A.S.No :- SBM – 7th SHPC dated 23.08.2018
Estimate Amount :- Rs.61.00 Lakhs
Date of Tender :- 22.10.2018
Date of Work Order :- 09.11.2018
Present Stage of Work :- Brick work upto roof level completed. Truss fabrication work under
progress.
Expenditure so far :- —
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Supply and delivery of 20 Nos.Battery Operated Vehicle
A.S.No :- SBM – 7th SHPC dated 23.08.2018
Estimate Amount :- Rs.36.00 Lakhs
Date of Tender :- 10.09.2018
Date of Work Order :- 09.11.2018
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.36.00 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Supply and delivery of 4 Nos.LCV
A.S.No :- SBM – 7th SHPC dated 23.08.2018
Estimate Amount :- Rs.22.40 Lakhs
Date of Tender :- 28.11.2018
Date of Work Order :- 14.12.2018
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.22.40 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Supply and delivery of 6000 Ltrs.capacity truck mounted high pressure Jet
Rodding cum Sewage Suction Machine
A.S.No :- SBM – 7th SHPC K.Dis.No.26788 / P3 / 2018 dated 29.10.2018
Estimate Amount :- Rs.49.00 Lakhs
Date of Tender :- 07.02.2019
Date of Work Order :- 04.03.2019
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.49.00 Lakhs
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Revamping of Dump Site through Bio Mining to recover the land at Compost Yard.
A.S.No :- SBM – 7th SHPC dated 13.08.2018
Estimate Amount :- Rs.953.00 Lakhs
Date of Tender :- 28.06.2019
Date of Work Order :- 30.08.2019
Present Stage of Work :- Basic work to erect machineries under progress
Expenditure so far :- —
Swachh Bharath Mission – Solid Waste Management (7th SHPC)
Name of Work :- Supply and delivery of 16 Nos.Battery Operated Vehicle
A.S.No :- SBM – 8th SHPC Roc.No.1191 / P3 / 2019 dated 21.01.2019
Estimate Amount :- Rs.28.80 Lakhs
Date of Tender :- 07.02.2019
Date of Work Order :- 04.03.2019
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.28.64 Lakhs
Swachh Bharath Mission – Solid Waste Management (8th SHPC)
Name of Work :- Supply and delivery of 2 Nos.LCV
A.S.No :- SBM – 8th SHPC Roc.No.1191 / P3 / 2019 dated 21.01.2019
Estimate Amount :- Rs.11.20 Lakhs
Date of Tender :- 07.02.2019
Date of Work Order :- 04.03.2019
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.10.77 Lakhs
Swachh Bharath Mission – Solid Waste Management (8th SHPC)
Name of Work :- Purchase of 1 No. Excavator Backhoe loader
A.S.No :- SBM – 8th SHPC Roc.No.1191 / P3 / 2019 dated 21.01.2019
Estimate Amount :- Rs.28.50 Lakhs
Date of Tender :- 07.02.2019
Date of Work Order :- 04.03.2019
Present Stage of Work :- Completed and put into use.
Expenditure so far :- Rs.26.61 Lakhs
Swachh Bharath Mission – Solid Waste Management (10th SHPC)
Name of Work :- Construction of Material Resource Recovery Centre in Pa. Vu.Sa Nagar Compost
Yard
A.S.No :- CMA, Chennai Proc.Roc.No.28819-4 / P3 / 2019 dated 02.12.2019
Estimate Amount :- Rs.18.00 Lakhs
Date of Tender :- 30.01.2020
Date of Work Order :- 10.02.2020
Present Stage of Work :- To be commenced
Expenditure so far :- —
14th Central Finance Commission Grant (Package 1)
Name of Work :- Providing BT Surface at Ponniamman Koil Street in W.No.5
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.25.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 2)
Name of Work :- Providing BT Surface at VCM Street in W.No.8
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.25.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 3)
Name of Work :- Providing BT Surface at Sakthi Nagar 1 to 5 in W.No.2
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.25.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- WMM laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 4)
Name of Work :- Providing BT Surface at Dharmaraja Koil 1st Street in W.No.14
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.15.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- WMM laid. BT to be laid.
Expenditure so far :- —
14th Central Finance Commission Grant (Package 5)
Name of Work :- Providing BT Surface at Kumarasamy Koil Street in W.No.20
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.20.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 6)
Name of Work :- Providing BT Surface at Arumuganar Street in W.No.20
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.25.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 7)
Name of Work :- Providing BT Surface at Pa.Vu.Sa Nagar in W.No.32
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.25.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- WMM laid. BT to be laid.
Expenditure so far :- —
14th Central Finance Commission Grant (Package 8)
Name of Work :- Providing BT Surface at North Muthappar Street, Sami Street & Aminuthin Street
in W.No.25
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.25.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 9)
Name of Work :- Providing BT Surface at Periyar Nagar in W.No.28
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.20.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- WMM laid. BT to be laid.
Expenditure so far :- —
14th Central Finance Commission Grant (Package 10)
Name of Work :- Providing BT Surface at Gandhi Nagar in W.No.26
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.12.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
14th Central Finance Commission Grant (Package 11)
Name of Work :- Providing BT Surface at Sundaram Nagar in W.No.34
A.S.No :- MCR.No.1 dated 06.01.2020
Estimate Amount :- Rs.18.00 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 05.03.2020
Present Stage of Work :- Sectioning and levelling completed. WMM to be laid
Expenditure so far :- —
CGF and O & M Fund 2018 – 19
Name of Work :- Construction of Storm Water Drain with Culvert to Sama Goundar Vattam in
W.No.33
A.S.No :- MA & WS Dept Minutes of the meeting dated 18.04.12018
Estimate Amount :- Rs.30.00 Lakhs
Date of Tender :- 31.07.2018
Date of Work Order :- 21.08.2018
Present Stage of Work :- Completed
Expenditure so far :- Rs.30.00 Lakhs
SuWaSem – 2019
Name of Work :- Restoration and rejuvenation of water bodies to TMC Colony Kulam & Recharge of
3 existing wells in Thirupathur Municipality
A.S.No :- MD, TWAD Board, Chennai Proc.Roc.No.280416 / HG Wing / DLC / SuWaSem /
2018 dated 19.06.2019 & District Collector, Vellore Proc.Roc.No.F.SuWaSem /
TWAD / RWS / Vellore dated 02.07.2019
Estimate Amount :- Rs.12.00 Lakhs
Date of Tender :- 04.10.2019
Date of Work Order :- 18.10.2019
Present Stage of Work :- Work nearing completion.
Expenditure so far :- —
MP Fund 2019 – 2020
Name of Work :- Providing BT Surface to Venkateshwara Nagar in W.No.32 (From Venkateshwara
Nagar to Thillai Vattam)
A.S.No :- District Collector, Thirupathur Proc.Roc.No.A2 / 190 / 2020 dated 18.03.2020
Estimate Amount :- Rs.22.00 Lakhs
Date of Tender :- 10.06.2020
Date of Work Order :- —
Present Stage of Work :- Subject placed before council for disposal
Expenditure so far :- —
MP Fund 2019 – 2020
Name of Work :- Providing 12 mtr height High Mast Light with 8 set of LED fittings at Thirupathur
Bus Stand
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 190 / 2019 dated 27.02.2020
Estimate Amount :- Rs.6.50 Lakhs
Date of Tender :- 10.06.2020
Date of Work Order :- —
Present Stage of Work :- Subject placed before council for disposal
Expenditure so far :- —
MP Fund 2019 – 2020
Name of Work :- Providing 9 mtr height High Mast Light with 5 set of LED fittings near Ponniamman
Koil
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 190 / 2019 dated 27.02.2020
Estimate Amount :- Rs.4.50 Lakhs
Date of Tender :- 10.06.2020
Date of Work Order :- —
Present Stage of Work :- Subject placed before council for disposal
Expenditure so far :- —
MLA Fund 2018- 2019
Name of Work :- Construction of PDS outlet for Dharmaraja Koil Street in W.No.14
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 1646 / 2018 dated 10.03.2018
Estimate Amount :- Rs.9.90 Lakhs
Date of Tender :- 20.12.2018
Date of Work Order :-
Present Stage of Work :- Delayed due to public objection. Alternate site clearance work is nearing
completion.
Expenditure so far :- —
MLA Fund 2019 – 2020
Name of Work :- Providing 90 mm PVC water supply distribution pipeline for Sivasakthi Nagar in
W.No.35
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 190 / 2019 dated 10.06.2019
Estimate Amount :- Rs.2.50 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 20.02.2020
Present Stage of Work :- Physically completed
Expenditure so far :- Rs.2.50 Lakhs
MLA Fund 2019 – 2020
Name of Work :- Providing 110 mm PVC water supply distribution pipeline for Venkateshwara Nagar
in W.No.32
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 190 / 2019 dated 10.06.2019
Estimate Amount :- Rs.1.50 Lakhs
Date of Tender :- 28.01.2020
Date of Work Order :- 20.02.2020
Present Stage of Work :- Completed
Expenditure so far :- Rs.1.50 Lakhs
MLA Fund 2019 – 2020
Name of Work :- Providing BT Surface Road to TNHB Phase I in W.No.34
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 1646 / 2019 dated 11.02.2020
Estimate Amount :- Rs.16.00 Lakhs
Date of Tender :- 05.03.2020
Date of Work Order :- 29.05.2020
Present Stage of Work :- —
Expenditure so far :- —
MLA Fund 2019 – 2020
Name of Work :- Providing 110 mm PVC water supply distribution pipeline to Aariff Nagar in
W.No.32
A.S.No :- District Collector, Vellore Proc.Roc.No.A2 / 1646 / 2019 dated 11.02.2020
Estimate Amount :- Rs.9.70 Lakhs
Date of Tender :- 05.03.2020
Date of Work Order :- 29.05.2020
Present Stage of Work :- —
Expenditure so far :- —
MLA Fund 2020 – 2021
Name of Work :- Providing Black Top Surface Road to Avvai Nagar in Ward No.35 at
Thirupathur
A.S.No :- District Collector, Thirupathur Proc.Roc.No.A1 / 041 / 2020 dated 14.08.2020
Estimate Amount :- Rs.11.00 Lakhs
Date of Tender :- 10.09.2020
Date of Work Order :- —
Present Stage of Work :- Subject placed before council for tender disposal
Expenditure so far :- —
MLA Fund 2020 – 2021
Name of Work :- Providing Black Top Surface Road to Chandiran Nagar (Kutiannan Vattam) &
Rajiv Gandhi Nagar in Ward No.35 at Thirupathur
A.S.No :- District Collector, Thirupathur Proc.Roc.No.A1 / 041 / 2020 dated 14.08.2020
Estimate Amount :- Rs.24.75 Lakhs
Date of Tender :- 10.09.2020
Date of Work Order :- —
Present Stage of Work :- Subject placed before council for tender disposal
Expenditure so far :- —
MLA Fund 2020 – 2021
Name of Work:- Construction of Additional Class Room at Gowthampettai Municipal School in
Ward No.30 at Thirupathur
A.S.No :- District Collector, Thirupathur Proc.Roc.No.A4 / 041 / 2020 dated 01.09.2020
Estimate Amount :- Rs.6.00 Lakhs
Date of Tender :- 25.09.2020
Date of Work Order :- —
Present Stage of Work :- Tender called on 25.09.2020
Expenditure so far :- —
MLA Fund 2020 – 2021
Name of Work :- Construction of Storm Water Drain with Culvert to Puthupettai Road 7th Street,
Gandhi Nagar in Ward No.26 at Thirupathur
A.S.No :- District Collector, Thirupathur Proc.Roc.No.A4 / 041 / 2020 dated 01.09.2020
Estimate Amount :- Rs.5.00 Lakhs
Date of Tender :- 25.09.2020
Date of Work Order :- —
Present Stage of Work :- Tender called on 25.09.2020
Expenditure so far :- —
TURIP 2017 – 18
Name of Work :- Providing BT Surface and Construction of Storm Water Drain with
culvert to Government Garden Road in Ward.No.15
A.S.No :- CMA, Chennai Proc.Roc.No.21422 / 2017 / E3 dated 03.10.2017
Estimate Amount :- Rs.50.00 Lakhs
Date of Tender :- 06.12.2017
Date of Work Order :- 18.12.2017
Present Stage of Work :- Completed
Expenditure so far :- Rs.50.00 Lakhs
TURIP 2018 – 19 (Package 1)
Name of Work :- Providing CC Road at GH Road and BT Surface at Ramakrishna
School Road, London Mission Road
A.S.No :- CMA, Chennai Proc.Roc.No.12981 / 2018 / E3 dated 17.07.2018
Estimate Amount :- Rs.213.00 Lakhs
Date of Tender :- 25.10.2018
Date of Work Order :- 31.01.2019
Present Stage of Work :- BT Road completed and Drain work completed in GH Road
& CC to be laid
Expenditure so far :- Rs.168.10 Lakhs
TURIP 2018 – 19 (Package 2)
Name of Work :- Providing BT Surface at Railway Station Road, Jinnah Road, Perumal Koil
Street, Peeranam Abdul Kuthus Street, Kottai Street, Ajimiyan Street &
T.M.Sulaiman Street
A.S.No :- CMA, Chennai Proc.Roc.No.12981 / 2018 / E3 dated 17.07.2018
Estimate Amount :- Rs.200.00 Lakhs
Date of Tender :- 25.10.2018
Date of Work Order :- 31.01.2019
Present Stage of Work :- Storm Water Drain and Culvert work completed. WMM & BT to be
laid.
Expenditure so far :- Rs.106.33 Lakhs
TURIP 2018 – 19 (Package 3)
Name of Work :- Providing BT Surface at Government Garden Road, Ari Street, Gandhi
Nagar Main Road and Gandhi Nagar Cross Street
A.S.No :- CMA, Chennai Proc.Roc.No.12981 / 2018 / E3 dated 17.07.2018
Estimate Amount :- Rs.210.00 Lakhs
Date of Tender :- 25.10.2018
Date of Work Order :- 31.01.2019
Present Stage of Work :- Completed
Expenditure so far :- Rs.187.27 Lakhs
TURIP 2018 – 19 (Package 4)
Name of Work :- Providing BT Surface at Gandhi Pettai Pillaiyar Koil Street, Sivaraj Pettai
Street, Chinna Mathar Street, Sulthan Miyan Street, Abbai Street, Birbal
Nannumiyan Street, Chinna Kulam Mariyamman Koil Street & Arasamara
Street
A.S.No :- CMA, Chennai Proc.Roc.No.12981 / 2018 / E3 dated 17.07.2018
Estimate Amount :- Rs.224.00 Lakhs
Date of Tender :- 25.10.2018
Date of Work Order :- 31.01.2019
Present Stage of Work :- Chinna Kulam Mariyamman Koil Street and Arasamara Street BT
road completed. WMM completed and BT to be laid for other
works
Expenditure so far :- Rs.34.69 Lakhs
TURIP 2018 – 19 (Package 5)
Name of Work :- Providing BT Surface at Ramakkapettai, TNHB Phase I Main Road, TNHB
Phase I Cross Street, TNHB Phase II Main Road, TNHB Phase II Cross
Street
A.S.No :- CMA, Chennai Proc.Roc.No.12981 / 2018 / E3 dated 17.07.2018
Estimate Amount :- Rs.165.00 Lakhs
Date of Tender :- 25.10.2018
Date of Work Order :- 31.01.2019
Present Stage of Work :- Completed
Expenditure so far :- Rs.152.49 Lakhs
TURIP 2019 – 20 (Package 1)
Name of Work :- Providing BT Surface Road at Mayapillaiyar Koil Street in W.No.5, Sakthi
Nagar in W.No.2, Sama Nagar in W.No.7 (Railway Station Road to YMCA
School end), Mariyamman Koil Street in W.No.4, Sowkath Ali Pettai in
W.No.6, Peeran Line in W.No.7, Venugopalsamy Street in W.No.22,
Dhandapani Koil Street, Jinnah Road 3rd Street Junction to Bus Out Way
area in W.No.13, Dharmaraja Koil Street in W.No.14, Kovilur Road in
W.No.3, Lakshmi Ammal Street, Raja Bathar Street in W.No.16,
Thiru.Vee.Ka Street in W.No.15 & Sundaram Nagar Main Road in W.No.34
A.S.No :- CMA, Chennai Proc.Roc.No.17349 / 2019 / E3 dated 16.10.2019
Estimate Amount :- Rs.250.00 Lakhs
Date of Tender :- 27.11.2019
Date of Work Order :- 05.03.2020
Present Stage of Work :- WMM completed for 6 works and BT to be laid and Drain work completed
in GH Road & CC to be laid
Expenditure so far :- —
TURIP 2019 – 20 (Package 2)
Name of Work :- Providing BT Surface Road at Ellaiamman Koil Street in W.No.9, Chairman
Lakshmanar Street in W.No.17, CHetty Street in W.No.20, Katcheri Street in
W.No.20, Nethaji Road and Sami Street in W>No.20 & 21, Chandhamiyan Street,
Khan Sahib Street, Immam Sahib Junction Street in W.No.21, Advocate
Ramanathan Street in W.No.28, Kamarajar Nagar, Muthumariamman Koil Street in
W.No.28, Velan Nagar in W.No.33, Sivasakthi Nagar in W.No.35, Bharathidasan
Nagar & Valluvar Nagar in W.No.36.
A.S.No :- CMA, Chennai Proc.Roc.No.17349 / 2019 / E3 dated 16.10.2019
Estimate Amount :- Rs.250.00 Lakhs
Date of Tender :- 27.11.2019 (1st Call). Second Call on 30.06.2020
Date of Work Order :- —
Present Stage of Work :- Tender received. LOA issued to remit balance 1% of ASD
Expenditure so far :- —
REVOLVING FUND OF UIDSSMT – TUFIDCO Loan Fund 2018 – 19
Name of Work :- Providing Internal Plumbing arrangements for 7913 Water Supply House Service
Connection
A.S.No :- G.O.(Ms) No.126 dated 28.11.2018 & CMA, Chennai Roc.No.13277 / 2018 / WS1
dated 03.07.2018
Estimate Amount :- Rs.275.00 Lakhs
Date of Tender :- 20.06.2019
Date of Work Order :- 16.08.2019
Present Stage of Work :- Work in progress
Expenditure so far :- —
TUFIDCO Loan Fund 2018 – 19 (Package 1)
Name of Work :- Providing Inter Link connection between inner premises of residence and chamber
for 8000 Nos.Sewage Connection
A.S.No :- G.O.(Ms) No.44 dated 24.02.2016 & CMA, Chennai Roc.No.13146 / 2018 / UGSS
2 – 1 & 2 dated 23.05.2018
Estimate Amount :- Rs.545.00 Lakhs
Date of Tender :- 31.07.2018
Date of Work Order :- 31.08.2018
Present Stage of Work :- Work in progress
Expenditure so far :- —
TUFIDCO Loan Fund 2018 – 19 (Package 2)
Name of Work :- Providing Inter Link connection between inner premises of residence and chamber
for 7000 Nos.Sewage Connection
A.S.No :- G.O.(Ms) No.44 dated 24.02.2016 & CMA, Chennai Roc.No.13146 / 2018 / UGSS
2 – 1 & 2 dated 23.05.2018
Estimate Amount :- Rs.475.00 Lakhs
Date of Tender :- 31.07.2018
Date of Work Order :- 31.08.2018
Present Stage of Work :- Work in progress
Expenditure so far :- —