All Schemes

FINANCIAL PROGRESS OF VARIOUS SCHEME UPTO 15.7.2020

TURIP 2017-18

PROVIDING BT ROAD, STROM WATER DRAIN & CULVERT AT TIRUCHENGODE MUNICIPAL AREA ( 2 PACAKGES)  —
CMA OFFICE PROCEEDING ROC NO. 21422/2017/E3 DATE.03.10.2017    RS.500.00 LAKHS  

26.12.201   WORK COMPLETED    RS.478.60 LAKHS

TURIP 2018-19

PROVIDING BT ROAD, STROM WATER DRAIN & CULVERT AT TIRUCHENGODE MUNICIPAL AREA ( 2 PACAKGES)
CMA OFFICE PROCEEDING ROC NO.12981/2018/E3  DATE. 17.07.2018  RS.500.00 LAKHS
26.10.2018  WORK COMPLETED   RS.377.26 LAKHS

TURIP 2019-20
PROVIDING BT ROAD, STROM WATER DRAIN & CULVERT AT TIRUCHENGODE MUNICIPAL AREA ( 5 PACAKGES)
CMA OFFICE PROCEEDING ROC NO.25039/2019/E3  DATE. 16.10.2019    RS.1000.00 LAKHS
08.11.2019 & 26.11.2019  WORK IS IN PROGRESS   RS.0.00 LAKHS

SWM 2016-17

SUPPLY&DELIVERY OF PUSHCART&COMPACTER BIN&COMPACTOR LORRY&CONSTRUCTION OF 1/3RD ROOF & PRESORTING SHED
CMA OFFICE PROCEEDING ROC NO.11088-15/2017/P3  DATE. 24.05.2017 RS.163.00 LAKHS
15.06.2017 WORK COMPLETED RS.143.57 LAKHS

SWM 2018-19

CONSTRUCTION OF MCC CENTER 5 LOCATION
CMA OFFICE PROCEEDING ROC NO.22866/2018/P3  DATE. 23.08.2018   RS.248.00 LAKHS
23.10.2018    WORKS COMPLTED & 1 WORK IS IN PROGRESS   RS.149.63 LAKHS

SWM 2018-19

SUPPLY & DELVERY OF 38 NOS BATTERY OPERATED VEHILE
CMA OFFICE PROCEEDING ROC NO.22866/2018/P3  DATE. 23.08.2018
RS.68.40 LAKHS   26.10.2018   WORK COMPLETED   RS.67.31 LAKHS

SWM 2018-19

SUPPLY & DELVERY OF 06 NOS LIGHT COMMERCIAL VEHILE
CMA OFFICE PROCEEDING ROC NO.22866/2018/P3  DATE. 23.08.2018 RS.33.60 LAKHS
17.10.2018  WORK COMPLETED  RS.33.26 LAKHS

SWM 2018-19

REMOVAL OF LEGACY WASTE 26574 CUM DUMPED IN THE ANIMOOR COMPOST YARD THROUGH BIO-MINING PROCESSEMOVAL LEGACY WASTE
CMA OFFICE PROCEEDING ROC NO.22866/2018/P3  DATE. 23.08.2018
RS.175.00 LAKHS   23.10.2018   6200 CU.M LEGACY WASTE WAS PROCESSED. RS.0.00 LAKHS

IUDM 2018-19

CONSTRUCTION OF 40 KLD CAPACITY FAECAL SLUDGE TREATMENT PLANT AT ANIMOOR COMPOST YARD OF TIRUCHENGODE MUNICIPALITY, NAMAKKAL (DISTRICT)(PERIOD FOR COMPLETION OF CONSTRUCTION – 9 MONTHS AND PERIOD OF OPERATION AND MAINTENANCE – 6 MONTHS)
CMA OFFICE PROCEEDING ROC NO.26888/UGSS-2/2018 DATED: 12.11.2018   RS.441.00 LAKHS 

04.03.2019   WORK IS IN PROGRESS    RS.106.25 LAKHS

IUDM 2018-19

AUGMENTATION OF WATER SUPPLY  SCHEME TO TIRUCHENGODE MUNICIPALITY  IN NAMAKKAL DISTRICT.(EXECUTED BY TWAD BOARD)
GO (MS) NO 12/MA&WS (MA2) DEPT DT 29.01.2019  RS.8385.00 LAKHS   08.03.2019
WORK COMPLETE WORK IS IN PROGRESS D RS.3200.00 LAKHS

UIDSSMT 2018-19 (TUFIDCO LOAN)

PROVIDING INTERNAL PLUMBING WORKS FOR HOUSE SERVICE CONNECTION 12761 NOS
CMA OFFICE PROCEEDING ROC NO. 13277/2018/WS1 DATE. 19.06.2018
RS.438.00 LAKHS  30.01.2019
WORK COMPLETE WORK IS IN PROGRESS D RS.0.00 LAKHS

15th CFC – 2020-2021

Kalaignar Nagarpura Mempatu Thittam

National Urban Health Mission