S.No | Name of Work | Est Amount in Lakhs | Billed works ason in Lakhs | AS | TS | Tender Date | W.O Date | Present stage | Remarks |
1 | Turip 2017-18 | 150.00 | 108.90 | 03.10.2017 | 17.11.2017 | 13.12.2017 | 01.02.2018 | Work is in progress | All works completed Except Bagar Hussain St-4 CC road with SWD |
2 | Turip 2018-19 | 100.00 | – | 21.08.2018 | 17.09.2019 | 17.10.2019 | 05.12.2018 | Work is in progress | Work is in progress |
3 | Internal plumbing | 94.00 | – | 03.07.2018 | 22.01.2019 | 14.02.2019 | 28.02.2019 | Work is in progress | HSC – 620 nos completed |
4 | Water ATM | 378.00 | – | – | – | 15.10.2018 | 02.11.2018 | No progress | MOU issued |
5 | IUDM 2018-19 | 491.45 | – | 28.01.2019 | 01.02.2019 | 20.02.2019 | 28.02.2019 | Work is in progress | Work is in progress |
6 | Water supply improvement works | 203.50 | 58.50 | 02.01.2019 | 01.02.2019 | 28.02.2019 | 06.03.2019 | Work is in progress | Mathinapalli Headwork- Erection 10 HP motor in 10 nos in existing Infilteration Well |
7 | MCC MGR Nagar | 50.90 | – | 23.08.2018 | 14.09.2018 | 16.10.2018 Retender 09.11.2018 | 05.12.2018 | Work is in progress | Roof work, Brick work & Toilet block works in progress |
8 | MCC Fathima Nagar | 50.90 | – | 23.08.2018 | 14.09.2018 | 16.10.2018 Retender 09.11.2018 | 05.12.2018 | No progress | Due to public agitation, after compromising the public the work will be started. |
9 | MCC Arunthathiyar colony | 50.90 | – | 23.08.2018 | 14.09.2018 | 16.10.2018 Retender 09.11.2018 | 05.12.2018 | Work is in progress | Truss work completed. Tub work is in progress. |
10 | SDRF -2019 | 77.00 | – | 28.05.2019 | 14.06.2019 | 25.06.2019 | 26.06.2019 | WORK COMPLETED | WORK COMPLETED |