Sno | Scheme Name | Name of Work | AS No. /AS Date | AS Year | AS Amount | Estimate Amount(In Cr) | Current Stage as on23.07.2024 | Payment Madeso far (in Cr) | Target DateAs PerAgreement | |
Stage ofwork | Percent % | |||||||||
1 | 3 | 6 | 9 | 10 | 11 | 12 | 21 | 22 | 23 | 26 |
1 | SBM 2.0 | SBM 2.0 Construction of Community Toilet and Urinal block in Aranarai at Ward No.17 | 5990/2022/SBMDated:11/04/22 | 2021-22 | 2496000 | 0.25 | Basement Level | 0 | 0 | 25/11/24 |
2 | SBM 2.0 | SBM 2.0 Construction of 3 TPD Micro Compost Centre at Neduvasal road Compost yard in Perambalur Municipality | 6450/2024/SBM-1(2) – 1Dated:14/03/24 | 2023-24 | 3450000 | 0.35 | Basement Level | 10 | 0 | 25/11/24 |
3 | SBM 2.0 | SBM 2.0 Construction of Urinals at New Bus stand in ward No.6 | 6450/2024/SBM-1 – 2Dated:14/03/24 | 2023-24 | 96000 | 0.01 | Foundation Brick Work In Progress. | 10 | 0 | 28/07/24 |
4 | SFC -SCHOOL IMPROVEMENT GRANT – INFRASTRUCTURE WORKS | SFC -SCHOOL IMPROVEMENT GRANT – INFRASTRUCTURE WORKS Construction of Three Class Room School Building at Aranarai Middle school. | 6002/2023/SS2Dated:25/10/23 | 2022-23 | 5300000 | 0.53 | Below Basement | 10 | 0 | 29/03/24 |
5 | WS Internal Plumbing | WS Internal Plumbing Providing internal Plumping works for Water supply HSC”s In Perambalur Municipality ( 6800 Nos) | 13277/2018/WS1Dated:19/06/18 | 2018-19 | 23400000 | 2.34 | Pipe Laid | 30 | 0.27 | 29/07/19 |
6 | SFC ARREAR FUND | SFC ARREAR FUND Relaying of Road-Cement Concrete Road089016S0102-PALLIVASAL STREET 1ST CROSS STREET , 089016S0103-PALLIVASAL STREET 2ND CROSS STREET , 089002S0031-Vivekanandar street 1 , 089002S0032-Vivekanandar street 2 , 089002S0033-POST OFFICE STREET (THURAIYUR MAIN ROAD) , | 22038/2023/SS-6 ADated:28/06/23Road DetailsRoad Length :526 Mts | 2023-24 | 1800000 | 0.18 | Plain Cement Concrete M 20 | 40 | 0 | 11-02-2023 |
7 | Kalaignar Nagarpura Mempatu Thittam | Kalaignar Nagarpura Mempatu Thittam Construction of Additional Bus Stand in the existing Bus Stand premises at Survey No:333/18, 333/38 | G.O (4D) No. 31, Annex-IIDated:07/08/23 | 2023-24 | 37200000 | 3.72 | Column Rising | 40 | 0.44 | 22/09/24 |
8 | SFC ARREAR FUND | SFC ARREAR FUND Relaying of Road-Bituminous Road089005R0229-Mettu Street EAST 16th street , 089005R0230-Mettu Street EAST17th street , 089005R0231-Mettu Street EAST 18th street , 089016R0830-POOSARI STREET , | 22038/2023/SS-26Dated:28/06/23Road DetailsRoad Length :474 Mts | 2023-24 | 2000000 | 0.2 | Road Marking / Road Furniture | 60 | 0 | 11-02-2023 |
9 | UGD-Internal Plumbing | UGD-Internal Plumbing Providing Under Ground Drainage house service interlink connection between inner prenises of resident and chamber for house service connection 4700 Nos ”in Perambalur Municipality | 30544/UGSS-1/2017Dated:25/01/16 | 2017-18 | 17800000 | 1.78 | Brick Work | 90 | 0.19 | 08-02-2018 |
10 | 15th CFC Tied Grant | 15th CFC Tied Grant Construction of 1.00 Lakh Litre capacity Ground Level Reservoir at KK nagar ward No.11 in Perambalur Municipality | 19119/2022/EA-2Dated:01/11/23 | 2022-23 | 1696000 | 0.17 | Finishing Work | 100 | 0 | 08-08-2024 |