1. SUH –
DAY NULM
| S.No | Project ID | Name of Work | AS Details | TS Details | Work Order Date | Agreement Date | Agreement Period | Agreement Value | Physical Progress in % | Stage of the Work | Payment Made so far |
Financial Progress in % | Target Date As Per Agreement | ||||
| AS Number | AS Date | AS Amount | TS Number | TS Date | TS Amount | ||||||||||||
| Region Status | |||||||||||||||||
| Name of the Region : CHENGALPATTU | |||||||||||||||||
| Name of the Scheme : 15th CFC | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 1 | 15TH CFC/2020-21/095/BUILDING/00007 | Conversion of LPG Gasifier System in Existing Crematorium at near Gedilam River bed | 847/E1/2021 | 30/Nov/2021 | 106.2 | 39/2021-2022 – 10 | 02/Dec/2021 | 9.9 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.9 | 100 | 9.9 | 0.00 | 06/May/2022 | |
| 2 | 15TH CFC/2020-21/095/BUILDING/00008 | Maintenance and Repair works for Community Toilet block at W.no.12, Asokh Nagar (Near Chettipattarai colony) in Panruti Municipality | 847/E1/2021 | 30/Nov/2021 | 106.2 | 38/2021-2022 – 9 | 02/Dec/2021 | 9.9 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.9 | 100 | 8.1 | 0.00 | 06/May/2022 | |
| 3 | 15TH CFC/2020-21/095/BUILDING/00009 | Maintenance and Repair works for Community Toilet block at W.no.19, Thandupalayam, W.no.11, Railway colony, ward no.16, Thiruvathigai (Near OHT) ward and wrad no.33, Rasapalayam in Panruti Municipality. | 847/E1/2021 | 30/Nov/2021 | 106.2 | 37/2021-2022 – 8 | 02/Dec/2021 | 6 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 6 | 100 | 5.7 | 0.00 | 06/May/2022 | |
| 4 | 15TH CFC/2020-21/095/BUILDING/00010 | Maintenance and Repair works for Community Toilet block at W.no.28, Kalathumedu Iyyanar Kovil Pattai (Near Municipal Office) and Iyyanar Kovil Street (Near Temple) in Panruti Municipality. | 847/E1/2021 | 30/Nov/2021 | 106.2 | 36/2021-2022 – 7 | 02/Dec/2021 | 6.5 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 6.5 | 100 | 2.36 | 0.00 | 06/May/2022 | |
| 5 | 15TH CFC/2020-21/095/BUILDING/00011 | Maintenance and Repair works for Community Toilet block at W.no.26, V.Andikuupam Nanthanar Colony, W.no.3, Vizhalanmangalam VOC Nagar and W.no.27, Thattanchavadi Gandhi Nagar in Panruti Municipality | 847/E1/2021 | 30/Nov/2021 | 106.2 | 35/2021-2022 – 6 | 02/Dec/2021 | 6 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 6 | 100 | 3.41 | 0.00 | 06/May/2022 | |
| 6 | 15TH CFC/2020-21/095/BUILDING/00012 | Construction of compound wall with watch man room to Chettipatarai colony OHT and Construction compound wall to Aa.Pa .Sivaraman nagar OHT | 847/E1/2021 | 30/Nov/2021 | 106.2 | 34/2021-2022 – 5 | 02/Dec/2021 | 9.9 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.9 | 100 | 9.9 | 0.00 | 06/Sep/2022 | |
| 7 | 15TH CFC/2020-21/095/BUILDING/00013 | Construction of compound wall with watch man room at V.Andikuppam OHT permises and Construction Pump room to Municipal office OHT at Ayyanar kovil Pattai in Panruti Municipality. | 847/E1/2021 | 30/Nov/2021 | 106.2 | 33/2021-2022 – 4 | 02/Dec/2021 | 9.8 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.8 | 100 | 7.32 | 0.00 | 04/Mar/2022 | |
| 8 | 15TH CFC/2020-21/095/BUILDING/00014 | Construction of new Store room for water supply and Street light materials at back side of Municipal office | 847/E1/2021 | 30/Nov/2021 | 106.2 | 32/2021-2022 – 3 | 02/Dec/2021 | 9.9 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.9 | 100 | 8.69 | 0.00 | 02/Jul/2022 | |
| 9 | 15TH CFC/2020-21/095/PARK/00004 | Supply and Delivery of Park play Materials and restoration compound wall at Gandhi Park. | 847/E1/2021 | 30/Nov/2021 | 106.2 | 40/2021-2022 – 11 | 02/Dec/2021 | 9.9 | 03/Jan/2022 | 04/Jan/2022 | 270 days | 9.9 | 100 | 7.9 | 0.00 | 02/Mar/2022 | |
| 10 | 15TH CFC/2020-21/095/SWD/00003 | Relaying of CC Road and construction of Strom Water Drain With Culvert at Thattanchavadi Gandhi nagar colony. | 847/E1/2021 | 30/Nov/2021 | 106.2 | 41/2021-2022 – 12 | 02/Dec/2021 | 9.5 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.5 | 100 | 9.45 | 0.00 | 02/Mar/2022 | |
| 11 | 15TH CFC/2020-21/095/WS/00005 | Providing Deep Borewell With 10HP Motor at V.O.C Nagar Near Mariyamman Koil and Pumping Main from Mariyamman Koil to VOC nagar OHT | 847/E1/2021 | 30/Nov/2021 | 106.2 | 30/2021-2022 – 1 | 02/Dec/2021 | 9.9 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9.9 | 100 | 7.7 | 0.00 | 02/Feb/2022 | |
| 12 | 15TH CFC/2020-21/095/WS/00006 | Supply and Delivery of Moveable Type 63 KVA Genset | 847/E1/2021 | 30/Nov/2021 | 106.2 | 31/2021-2022 – 2 | 02/Dec/2021 | 9 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 9 | 100 | 9 | 0.00 | 02/Feb/2022 | |
| 13 | 15TH CFC/2021-22/095/BUILDING/00044 | Providing Paver Block Surface at existing vehicle shed at back side of Municipal office | 864/E1/2021 | 31/Dec/2021 | 69 | 75/2021-2022 – 8 | 03/Jan/2022 | 9 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 9 | 100 | 9 | 0.00 | 06/May/2022 | |
| 14 | 15TH CFC/2021-22/095/BUILDING/00107 | Replacing of Existing Damaged Cement Roof Sheet into GI sheet and Providing Vehicle Battery Charge Electrical points at vehicle parking shed back side of Municipal office in Panruti Municipality. | 946/E1/2022 | 25/Jan/2022 | 45.5 | 77 – 1 | 25/Jan/2022 | 9.9 | 12/Apr/2022 | 13/Apr/2022 | 270 days | 9.9 | 100 | 9.9 | 0.00 | 12/Jun/2022 | |
| 15 | 15TH CFC/2021-22/095/BUILDING/00109 | Supply, delivery and fixing of 2HP & 5HP Motors, Servicing of Straters, Control panels, Human Charging Trolley with Bearing, Cremation Chamber flue ducts and Painting work in the Existing Gasifier Crematorium near Kedilam river bed in Panruti Municipality. | 946/E1/2022 | 25/Jan/2022 | 45.5 | 81 – 5 | 25/Jan/2022 | 4.5 | 12/Apr/2022 | 13/Apr/2022 | 270 days | 4.5 | 100 | 4.41 | 98.04 | 13/May/2022 | |
| 16 | 15TH CFC/2021-22/095/BUILDING/00131 | Renovation of Gasifier Crematiorium and Construction of 2 nos bathroom (1.50×1.50m each) with water supply arrangements and toilet 2 seats and | 31112/2021/CFC-1 | 24/Aug/2022 | 37.53 | TS-8 | 24/Aug/2022 | 7.93 | 21/Sep/2022 | 22/Nov/2022 | 270 days | 7.93 | 100 | 7.93 | 100.00 | 22/Nov/2022 | |
| 17 | 15TH CFC/2021-22/095/CULVERT/00135 | Recontruction of RCC Slab Culvert (6mx1.50m) at 0 m Chainage in KAMARAJ LANE (Unicode No.095022S045) in Ward 22 | 31112/CFC-1 | 23/Sep/2022 | 1.08 | 17 | 23/Sep/2022 | 1.08 | 01/Dec/2022 | 03/Dec/2022 | 270 days | 1.08 | 100 | 1.08 | 0.00 | 02/Jan/2023 | |
| 18 | 15TH CFC/2021-22/095/PURCHASE/00110 | Supply and Delivery of 54.50 liter Capacity Wheeled Skid Steer Loader in Panruti Municipality. | 946/E1/2022 | 25/Jan/2022 | 45.5 | 80 – 4 | 25/Jan/2022 | 25 | 04/Jul/2022 | 05/Jul/2022 | 270 days | 25 | 100 | 24.94 | 0.00 | 03/Sep/2022 | |
| 19 | 15TH CFC/2021-22/095/SL/00001 | Conversion of Existing street light lamps into Energy saving lamps, providing street Lights in the omitted /added area and maintain the street light system for a period of 10 years in Panruti Municipality | 31112/2021/CFC | 14/Oct/2022 | 28.89 | 117 | 03/Nov/2022 | 28.89 | 06/Mar/2023 | 06/Mar/2023 | 270 days | 16.78 | 100 | work completed | 20.54 | 0.00 | 04/Jul/2023 |
| 20 | 15TH CFC/2021-22/095/SWD/00132 | Construction of Storm water Drain at ward 9. A.Mani Nagar Main street (095009R129) Length 0.60m,vent 0.45m A.Mani nagar 3rd cross (095009R129)45m | 31112/2021/CFC-1 | 24/Aug/2022 | 37.53 | TS-9 | 24/Aug/2022 | 9.9 | 21/Sep/2022 | 22/Sep/2022 | 270 days | 9.9 | 100 | 9.88 | 0.00 | 22/Nov/2022 | |
| 21 | 15TH CFC/2021-22/095/SWD/00133 | Construction of Storm water Drain at ward.22 Vinayan lane (095022R371) length 160.00m height 0.60m vent 0.30m and Relaying of CC Road at low lying area at ward Kamaraj Street (095022R372) length 60.m width 4.40m | 31112/2021/CFC-1 | 24/Aug/2022 | 37.53 | TS-10 | 24/Aug/2022 | 9.8 | 21/Sep/2022 | 22/Sep/2022 | 270 days | 9.8 | 100 | 9.79 | 0.00 | 22/Nov/2022 | |
| 22 | 15TH CFC/2021-22/095/SWD/00134 | Construction of Storm water Drain length 124m,vent 0.45m ht 0.40m and Relaying of CC Road at 69m at low lying area at Main nagar(095024R384) | 31112/2021/CFC-1 | 24/Aug/2022 | 37.53 | TS-11 | 24/Aug/2022 | 9.9 | 21/Sep/2022 | 22/Sep/2022 | 270 days | 9.9 | 100 | 9.9 | 0.00 | 22/Nov/2022 | |
| 23 | 15TH CFC/2021-22/095/SWM/00043 | Supply and fixing of Sherdder Machine with shed at Kamaraj nagar | 864/E1/2021 | 31/Dec/2021 | 69 | 76/2021-2022 – 9 | 03/Jan/2022 | 5 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 5 | 100 | 5 | 0.00 | 06/May/2022 | |
| 24 | 15TH CFC/2021-22/095/SWM/00048 | Construction of Decentralized Waste Water Treatment Plant Near Kedilam River Bank at ward 30 Devaraj nagar in Panruti Municipality | 864/E1/2021 | 31/Dec/2021 | 69 | 71/2021-2022 – 4 | 03/Jan/2022 | 9.9 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 9.9 | 100 | 9.9 | 0.00 | 24/Apr/2022 | |
| 25 | 15TH CFC/2021-22/095/SWM/00049 | Construction of Decentralized Waste Water Treatment Plant Near Kedilam River Bank at ward 30 VOC street in Panruti Municipality | 864/E1/2021 | 31/Dec/2021 | 69 | 70/2021-2022 – 3 | 03/Jan/2022 | 9.9 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 9.9 | 100 | 8.25 | 0.00 | 06/May/2022 | |
| 26 | 15TH CFC/2021-22/095/SWM/00113 | Supply, Delivery and fixing of Incinerator and Electrical weigh machine with printing facilities to Panruti Municipality | 946/E1/2022 | 25/Jan/2022 | 45.5 | 78 – 2 | 25/Jan/2022 | 3.1 | 12/Apr/2022 | 13/Apr/2022 | 270 days | 3.1 | 100 | 3.1 | 0.00 | 13/May/2022 | |
| 27 | 15TH CFC/2021-22/095/SWM/00116 | Supply and delivery of 120 Liter capacity PVC Dustbins to Panruti Municipality | 946/E1/2022 | 25/Jan/2022 | 45.5 | 79 – 3 | 25/Jan/2022 | 3 | 12/Apr/2022 | 13/Apr/2022 | 270 days | 3 | 100 | 3 | 99.94 | 13/May/2022 | |
| 28 | 15TH CFC/2021-22/095/WS/00045 | Providing Rain Water Harvesting Reacharge pits at Various location | 864/E1/2021 | 31/Dec/2021 | 69 | 74/2021-2022 – 7 | 03/Jan/2022 | 3.9 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 3.9 | 100 | 3.9 | 0.00 | 06/May/2022 | |
| 29 | 15TH CFC/2021-22/095/WSIS/00046 | Supply and Delivery of Sulice Valves at Various Places in Municipal limit (65mm Dia-15 Nos, 80mm Dia-2 Nos, 4″ Dia- 4 Nos, 6″ Dia- 4 Nos and 8″ Dia- 4 Nos) | 864/E1/2021 | 31/Dec/2021 | 69 | 73/2021-2022 – 6 | 03/Jan/2022 | 3.5 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 3.5 | 100 | 2.69 | 0.00 | 06/May/2022 | |
| 30 | 15TH CFC/2021-22/095/WSIS/00047 | Supply and Delivery of Starter with Panel Boards (2HP -5 Nos, 10HP-3 Nos, 15HP-4Nos and 35HP-2 Nos) and Copper Cable (1.5 Sq mm -500 m, 2.5 Sq mm -600 m, 4 Sq mm -500 m and 10 Sq mm -300 m) at Various Places in Municipal limit | 864/E1/2021 | 31/Dec/2021 | 69 | 72/2021-2022 – 5 | 03/Jan/2022 | 8 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 8 | 100 | 8 | 0.00 | 06/May/2022 | |
| 31 | 15TH CFC/2021-22/095/WSIS/00050 | Providing Distribution of Pipeline to Manjini Nagar 1 and 2 Streets, Ambedkar Nagar , Dhanalakshmi Nagar Lane, Temple View Garden Street, Thayumanavar Street, Varadharaja Puram, Housing Board to Pakkiripalayam Colony up to Mariyamman Koil and Ayyanar Koil Pattai | 864/E1/2021 | 31/Dec/2021 | 69 | 69/2021-2022 – 2 | 03/Jan/2022 | 9.9 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 9.46 | 100 | 9.9 | 0.00 | 25/Mar/2022 | |
| 32 | 15TH CFC/2021-22/095/WSIS/00051 | Supply and Delivery of Submerscible Pumpset at Various Places in Municipal limit (2HP -5 Nos, 10HP-3 Nos, 15HP- 4 Nos and 35HP-2 Nos) | 864/E1/2021 | 31/Dec/2021 | 69 | 68/2021-2022 – 1 | 03/Jan/2022 | 9.9 | 24/Jan/2022 | 24/Jan/2022 | 270 days | 9.9 | 100 | 9.9 | 0.00 | 06/May/2022 | |
| 33 | 15THCFC/2022-23/095/PURCHASE/00009 | Supply and Delivery of 9 Nos Battery Operated Vehicle to Panruti Municipality | 16117 /2022/CFC-1 | 21/Mar/2023 | 18 | 96 | 24/Apr/2023 | 18 | 01/May/2023 | 01/May/2023 | 270 days | 18 | 100 | 17.13 | 0.00 | 16/May/2023 | |
| 34 | 15THCFC/2022-23/095/PURCHASE/00010 | Supply and Delivery of 8 nos Light Commercial Vehicle in Panruti Municipality | 16117/2022/CFC-1 | 21/Mar/2023 | 58.4 | 95 | 24/Mar/2023 | 58.4 | 01/May/2023 | 01/May/2023 | 270 days | 58.4 | 100 | 58.4 | 0.00 | 16/May/2023 | |
| 35 | 15THCFC/2022-23/095/SANITATION/00016 | Repair and renovation of Community toilet at ward no.5 chekkumedu alongwith supply of 2 nos. Electronic weighing machine ,2 nos. Napkin incinerator –big and 3 nos. fly catcher for MCC | 165/2021/B1 _13 | 06/Jun/2023 | 6.06 | 74 | 19/May/2023 | 6.06 | 28/Jun/2023 | 28/Jun/2023 | 270 days | 6.06 | 100 | 4.15 | 0.00 | 27/Aug/2023 | |
| 36 | 15THCFC/2022-23/095/SWM/00014 | Supply ,delivery and installation of automatic siever machine with 3 HP motor suitable for a capacity of 1 ton per hour including all taxes and transportation charges ,etc complete- Two (2) Nos., ., of 32 No’s 150 litre capacity HDPE garbage bins , 36 No’s 80 lit capacity HDPE garbage bins for BOV Garbage Collection Vehicle | 165/2021/B1_14 | 06/Jun/2023 | 2.35 | 71 | 19/May/2023 | 2.35 | 28/Jun/2023 | 28/Jun/2023 | 270 days | 2.35 | 100 | 2.29 | 0.00 | 27/Aug/2023 | |
| 37 | 15THCFC/2022-23/095/SWM/00015 | Supply and erection of rag bailing machine for bailing of recyclable wasre such as plastic paper and rags with suitable power pack and control valves with hand operated lever .The overall machine size is 1800mm X 780mmX length 690mm with separate stand for mounting hand operated hydraulic cylinder and started .The machine will be operated hydraulically with 7.50 HP motor. Bale weight approx 50 to 60 kgs . The duration of bale is 15-20 minutes per bale .Bundle height 700X500 X650mm.The doors will | 165/2021/B1_11 | 06/Jun/2023 | 3.6 | 72 | 19/May/2023 | 3.6 | 28/Jun/2023 | 28/Jun/2023 | 270 days | 3.6 | 100 | 3.59 | 0.00 | 27/Aug/2023 | |
| 38 | 15THCFC/2022-23/095/SWM/00017 | Supply, fixing and Commissioning of Shredder machine with following specification: Double stage cleaner ,cutter thickness 15mm,cutter dia 200mm built with heavy duty tappered roller bearing with 5 HP 3 phase 1440 rpm with chain coupling device and gear box for 10 to 30 rpm suitable for organic and non organic upto 1 ton/hour including all taxes and transportation charges Supply, fixing and Commissioning of Belt conveyor belt with the following specification Length of 6 mtrs and br |
165/2021/B1_12 | 06/Jun/2023 | 6.35 | 73 | 19/May/2023 | 6.35 | 28/Jun/2023 | 28/Jun/2023 | 270 days | 6.35 | 100 | 6.33 | 0.00 | 27/Aug/2023 | |
| 39 | 15THCFC/2023-24/095/CULVERT/00002 | Construction of Culvert at Ward No.1 Sivanpadai Street, Ward No.2 Pillaiyar Kovil Street, and Pnnappan Street, and Nalver Street, Ward No.3 Dharga Vandimedu 1st and 2nd Street, and V.O.C Street, Ward No.4 Nadar colony and dhanapal street, and Appalu street, junction Ward No.5 marriamman kovil street, and jawahar street, Ward No.6 Ambedkar cross street, Ward No.7 Thiruvalluvar nagar 3rd street, and 3rd cross street, and 4th street and 5th street, Ward No.8 Adhamkhan dharga street, Ward No.13 | 165/2021/A1 | 06/Dec/2023 | 47 | 160 | 07/Dec/2023 | 47 | 09/Feb/2024 | 09/Feb/2024 | 270 days | 47 | 100 | Work completed | 46.75 | 99.46 | 09/May/2024 |
| 40 | 15THCFC/2023-24/095/ROAD/00027 | Relaying of Road-095016R275-BAJANAMADA STREET , 095027R494-KADHARMASSKHAN MAIN NAGAR , | 1042/2023/b1/8 | 06/Jul/2023 | 9.9 | 10 | 23/Jun/2023 | 9.9 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 9.9 | 100 | 9.53 | 0.00 | 16/Sep/2023 | |
| 41 | 15THCFC/2023-24/095/ROAD/00028 | Relaying of Road-095022R367-S P D RAMASAMY STREET , 095026R429-THIDIRKUPPAM MAIN STREET , | 1042/2023/b1/10 | 06/Jul/2023 | 18.1 | 12 | 23/Jun/2023 | 18.1 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 18.1 | 100 | 8.2 | 0.00 | 16/Sep/2023 | |
| 42 | 15THCFC/2023-24/095/ROAD/00029 | Relaying of Road-095019R332-POLICE LINE 2ND CROSS STREET , 095019R340-POLICE LINE 2ND CROSS STREET , 095020R346-RAMASAMY STREET , 095021R353-THAGOOR STREET-2 , | 1042/2023/b1/9 | 06/Jul/2023 | 12 | 11 | 23/Jun/2023 | 12 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 12 | 100 | 11.99 | 0.00 | 16/Sep/2023 | |
| Name of the Scheme : 15th CFC Tied Grant | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 43 | 15THCFC/2023-24/095/WS/00022 | Providing bore well with power pump at ashok nagar water supply pipe laying work at edapalayam road in ward no 26,10and 11 | 281/2024/E1 | 02/Feb/2024 | 20.92 | 363/2023-24 | 02/Feb/2024 | 20.92 | 27/Feb/2024 | 27/Feb/2024 | 270 days | 20.92 | 100 | 20.87 | 0.00 | 27/May/2024 | |
| 44 | 15THCFC/2025-26/095/PURCHASE/00001 | Supply and delivery of 6000 liters capacity stainless steel water tanker | 25264/2025/EA-2 | 23/Oct/2025 | 33 | 55 | 30/Oct/2025 | 33 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 33 | 100 | work Completed | 31 | 0.00 | 18/Feb/2026 |
| 45 | 15THCFC/2025-26/095/PURCHASE/00004 | Supply and Delivery of three phase Submersible Pumpset and values for existing borewells at various places. | 25264/2025/E A-2 | 23/Oct/2025 | 19.7 | 58 | 30/Oct/2025 | 19.7 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 19.7 | 100 | completed | 19.66 | 99.82 | 18/Feb/2026 |
| 46 | 15THCFC/2025-26/095/WS/00002 | Bore well flushing at Various places | 25264/ 2025/EA-2 | 23/Oct/2025 | 2.7 | 56 | 30/Oct/2025 | 2.7 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 2.7 | 100 | completed | 2.7 | 100.00 | 18/Feb/2026 |
| 47 | 15THCFC/2025-26/095/WS/00003 | Providing Deep Bore well at Ward.No.23 Panrutiyar Nagar, Ward No. 28 Sathiya Moorthy Street and Ward No. 13 Valkara Street | 25264/2025 /EA-2 | 23/Oct/2025 | 22 | 57 | 30/Oct/2025 | 22 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 22 | 100 | Work Completed | 22 | 100.00 | 18/Feb/2026 |
| 48 | 15THCFC/2025-26/095/WS/00005 | Repair and maintenance work at ward No.7, Thiruvalluvar Nagar OHT(1.00LL) | 25264/2025 /EA -2 | 23/Oct/2025 | 8 | 59 | 30/Oct/2025 | 8 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 8 | 100 | Completed | 8 | 100.00 | 18/Feb/2026 |
| 49 | 15THCFC/2025-26/095/WS/00006 | Repair and maintenance of OHT (2.00LL Capacity) and providing laying paver block at Ward No. 1, V. Andikuppam (Azhagappar Street) OHT premises | 25264/2025/EA 2 | 23/Oct/2025 | 7.1 | 60 | 30/Oct/2025 | 7.1 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 7.1 | 100 | Completed | 7.1 | 100.00 | 18/Feb/2026 |
| 50 | 15THCFC/2025-26/095/WS/00007 | Repair and maintenance work and providing laying paver block at ward No.14 Thiruvathigai OHT | 25264/2025/EA2 | 23/Oct/2025 | 9 | 61 | 30/Oct/2025 | 9 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 9 | 100 | Work Completed | 9 | 100.00 | 18/Feb/2026 |
| 51 | 15THCFC/2025-26/095/WS/00008 | Repair and maintenance work and providing laying paver block at ward No.19 Kamaraj nagar OHT (Bus stand back side 4.00LL capacity) | 25264/2025/E A2 | 23/Oct/2025 | 12.05 | 62 | 30/Oct/2025 | 12.05 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 12.05 | 100 | work completed | 12.05 | 100.00 | 18/Feb/2026 |
| 52 | 15THCFC/2025-26/095/WS/00009 | Repair and maintenance of OHT (0.60LL) and Laying paver block at Ward No. 25, Adipillai street OHT | 25264/2025/EA-2 | 23/Oct/2025 | 10 | 63 | 30/Oct/2025 | 10 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 10 | 100 | Work Completed | 10 | 100.00 | 18/Feb/2026 |
| 53 | 15THCFC/2025-26/095/WS/00010 | Repair and maintenance work and laying paver block at ward no.27 municipal office back side OHT (9.00LL) | 25264/2025/EA_2 | 23/Oct/2025 | 36.5 | 64 | 30/Oct/2025 | 36.5 | 20/Nov/2025 | 20/Nov/2025 | 90 Days | 36.5 | 100 | Completed | 36.5 | 0.00 | 18/Feb/2026 |
| Name of the Scheme : 15th CFC UnTied Grant | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 54 | 15THCFCUNT/2023-24/095/BUILDING/00023 | Providing Paver road at gasifier crematorium | 281/2024/E1_2 | 02/Feb/2024 | 13.14 | 364/2023-24 | 02/Feb/2024 | 13.14 | 27/Feb/2024 | 27/Feb/2024 | 270 days | 13.14 | 100 | 13.14 | 0.00 | 27/May/2024 | |
| 55 | 15THCFCUNT/2023-24/095/ROAD/00006 | Relaying of Road-Cement Concrete Road095013R193-VALKARAR STREET MAIN ROAD , 095014R215-MGR NAGAR , | 271/2023-24/E1 | 02/Feb/2024 | 25 | 342/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 23.56 | 0.00 | 03/Jun/2024 | |
| 56 | 15THCFCUNT/2023-24/095/ROAD/00007 | Relaying of Road-Cement Concrete Road095014R227-KARAVAKARA STREET , 095032R545-A ANDIKUPPAM MAIN ROAD , | 271/2024/E1 | 02/Feb/2024 | 25 | 335/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.5 | 0.00 | 03/Jun/2024 | |
| 57 | 15THCFCUNT/2023-24/095/ROAD/00008 | Relaying of Road-Cement Concrete Road095005R073-MARIAMMAN KOIL STREET , 095006R080-AMBETHKAR NAGAR METTU STREET , | 271/2024/E1-3 | 02/Feb/2024 | 25 | 336/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.5 | 0.00 | 03/Jun/2024 | |
| 58 | 15THCFCUNT/2023-24/095/ROAD/00009 | Relaying of Road-Cement Concrete Road095001R003-JAHEER HUSSAIN ST , 095016S032-2ND CROSS STREET , 095004R069-DHANAPAL STREET , | 271/2024/E1-4 | 02/Feb/2024 | 25 | 337/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.15 | 0.00 | 03/Jun/2024 | |
| 59 | 15THCFCUNT/2023-24/095/ROAD/00010 | Relaying of Road-Cement Concrete Road095021R366-VALLALAR STREET , | 271/2024/E1-9 | 02/Feb/2024 | 10 | 343/2023-24 | 02/Feb/2024 | 10 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 10 | 100 | 9.99 | 0.00 | 03/Jun/2024 | |
| 60 | 15THCFCUNT/2023-24/095/ROAD/00011 | Relaying of Road-Cement Concrete Road095028R499-SATHYAMOORTHY STREET , | 271/2024/E1-7 | 02/Feb/2024 | 25 | 340/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.34 | 0.00 | 03/Jun/2024 | |
| 61 | 15THCFCUNT/2023-24/095/ROAD/00012 | Relaying of Road-Cement Concrete Road095007R098-THIRUVALLUVAR NAGAR 8TH CROSS STREET , 095022S044-MURUNGAPAKKAM STREET-1 , 095009R124-RAILWAY COLONY TEMPLE RIGHT SIDE , | 271/2024/E1-6 | 02/Feb/2024 | 25 | 339/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.5 | 0.00 | 03/Jun/2024 | |
| 62 | 15THCFCUNT/2023-24/095/ROAD/00017 | Relaying of Road-Cement Concrete Road095001R010-AZHAGAPPAR STREET , 095010R136-KASIMKHAN STREET(PAKKIRIPALAYAM) , 095007S017-THIRUVALLUVAR NAGAR 9TH CROSS STREET , | 271/2024/E1-5 | 02/Feb/2024 | 25 | 338/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.5 | 0.00 | 03/Jun/2024 | |
| 63 | 15THCFCUNT/2023-24/095/ROAD/00021 | Relaying of Road-Cement Concrete Road095016S030-ELUPPAI THOPPU MAIN ROAD , 095017R305-KUPPU GOWNDER MAIN STREET , 095004R070-NADAR COLONY STREET , 95001R001-JAHEER HUSSAIN ST , | 271/2024/E1-8 | 02/Feb/2024 | 25 | 341/2023-24 | 02/Feb/2024 | 25 | 05/Mar/2024 | 05/Mar/2024 | 270 days | 25 | 100 | 24.37 | 0.00 | 03/Jun/2024 | |
| 64 | 15THCFCUNT/2024-25/095/BUILDING/00021 | Construction of compound wall and Flooring paver block arrangement in ward 29 devaraj nagar MCC | 598-1/2025/E2 | 20/Feb/2025 | 21.18 | 31/2024-25 | 20/Feb/2025 | 21.18 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 21.18 | 100 | completed | 21.18 | 100.00 | 12/Jan/2026 |
| 65 | 15THCFCUNT/2024-25/095/PURCHASE/00020 | Purchasing CI Sluice valve for Water Supply Distribution line | 598/2025/E2 | 20/Feb/2025 | 0.34 | 32/2024-25 | 20/Feb/2025 | 0.34 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 0.34 | 100 | Completed | 0.34 | 98.76 | 12/Jan/2026 |
| Name of the Scheme : 15thCFC-Health | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 66 | 15TH CFC/2021-22/095/BUILDING/00098 | UPHC Panruti – Building- 1 No. | 32454/2021/AMRUT-2/Panruti | 17/Dec/2021 | 25 | 81/2021-2022/-1 | 28/Dec/2021 | 25 | 13/Jan/2022 | 13/Jan/2022 | 270 days | 25 | 100 | 25 | 0.00 | 12/Jul/2022 | |
| 67 | 15THCFCUPC/2023-24/095/BUILDING/00001 | Construction of Additional Buildings for GH Panruti | 19731/2023/EA-2 | 19/Jan/2024 | 500 | 172 | 22/Jan/2024 | 500 | 22/Feb/2024 | 22/Feb/2024 | 540 Days | 500 | 100 | Work Completed | 458.66 | 0.00 | 15/Aug/2025 |
| 68 | 15THCFCUPC/2023-24/095/BUILDING/00047 | Construction of Urban Health Sub Centre Avayampalayam at Panruti Municipality. | 25875/2023/EA2 | 16/Aug/2023 | 30 | 85 | 06/Sep/2023 | 30 | 18/Jan/2024 | 18/Jan/2024 | 270 days | 30 | 100 | completed | 29.96 | 99.87 | 08/Jul/2024 |
| Name of the Scheme : CMBFS-COMMON KITCHEN | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 69 | CMBFS/2022-23/095/BUILDING/00011 | Contruction of Common Kitchen Building at L.R Palayam Municipal Elementary School in WD_01 Panruti Municipality | 306/E1/2022 | 22/Mar/2023 | 28 | 181/22-23 | 24/Mar/2023 | 28 | 14/Apr/2023 | 14/Apr/2023 | 270 days | 28 | 100 | 16.99 | 0.00 | 11/Oct/2023 | |
| Name of the Scheme : Kalaignar Nagarpura Mempatu Thittam | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 70 | KALAIGNAR /2021-22/095/PARK/00058 | Providing Green space development at Ward No 21 Veerattalingam Layout – Ward – B, Block -17 TS No.69 in Panruti Municipality | G.O.(Ms) No.90 MAWS (NS) Dept. | 27/Oct/2021 | 48 | 22/2021-2022 | 12/Nov/2021 | 48 | 30/Nov/2021 | 30/Nov/2021 | 270 days | 48 | 100 | completed | 32.99 | 0.00 | 29/May/2022 |
| 71 | KALAIGNAR /2021-22/095/ROAD/00059 | Relaying of Road-095/2021/011/R/0000327-CHETTIPATTARAI COLONY RIGHT SIDE 1ST CROSS , 095/2021/016/R/0000367-BURIAL GROUND ROAD FROM VEERANAM ROAD , 095/2021/016/R/0000259-RAJIV GHANDHI NAGAR MAIN STREET , 095/2021/016/R/0000247-RAJIV GHANDHI NAGAR 1 ST CROSS STREET , 095/2021/016/R/0000244-RAJIV GHANDHI NAGAR 2ND CROSS STREET , 095/2021/016/R/0000241-RAJIV GHANDHI NAGAR 3RD CROSS STREET , 095/2021/016/R/0000238-RAJIV GHANDHI NAGAR 4TH CROSS STREET , 095/2021/016/R/0000224-RAJIV GHANDHI NAGAR 5TH | G.O.(Ms) No.92 MAWS (NS) Dept. | 30/Oct/2021 | 109.25 | 110/2021-22 | 19/Nov/2021 | 109.25 | 10/Dec/2021 | 10/Dec/2021 | 270 days | 109.25 | 100 | 104.2 | 0.00 | 08/Jun/2022 | |
| 72 | KALAIGNAR /2022-23/095/PARK/00102 | Park at Moopanar Nagar ward no. A, Block 22, TS No. 14/4A 1A | G.O.(Ms) No.88 MAWS (NS) Dept. | 17/Jun/2022 | 41.95 | 48/2022-23 | 27/Jun/2022 | 41.95 | 26/Jul/2022 | 26/Jul/2022 | 270 days | 41.95 | 100 | completion | 37.37 | 0.00 | 22/Jan/2023 |
| 73 | KALAIGNAR /2022-23/095/WB/00125 | Water Bodies at ward no. 2, vizhamangalam nagar, ward no. A Block21, TS No. 33 in Panruti Municipality | G.O.(4D)No.18 MAWS(SSFC) Dept., – I – Panruti | 21/Oct/2022 | 42 | 384 | 04/Nov/2022 | 42 | 08/Dec/2022 | 08/Dec/2022 | 270 days | 42 | 100 | 30.56 | 0.00 | 09/Mar/2023 | |
| 74 | KNMT/2023-24/095/BUILDING/00030 | Construction of Knowledge Centre at Lakshmipathy Nagar Survey No. 49, T.S. No. 149 | G.O. (4D) No. 22 | 21/Jun/2023 | 219 | 651/2023-2024 | 14/Jun/2023 | 219 | 13/Jul/2023 | 13/Jul/2023 | 540 Days | 219 | 100 | 207.45 | 0.00 | 03/Jan/2025 | |
| 75 | KNMT/2023-24/095/ROAD/00018 | Relaying of Road-095002R028-VIZHAMANGALAM BURIAL GROUND ROAD , 095008R118-VMS NAGAR (CUDDALORE ROAD) , 095008R119-VMS NAGAR (CUDDALORE ROAD) , 095008R120-VMS NAGAR (CUDDALORE ROAD) , 095009R135-RAILWAY COLONY-1ST CROSS STREET , 095010R137-MOHAMMED NAGAR (PAKKIRIPALAYAM) , 095012R181-PATTASAMY STREET 1ST CROSS , 095016R282-V.S PANDURANAGAN NAGAR 3RD STREET , 095023R379-NORTH CROSS STREET-2 , 095025R421-SEELAKARA CROSS STREET-2 , | G.O. (4D) No. 22 | 21/Jun/2023 | 148 | 257 | 14/Jun/2023 | 71 | 10/Jul/2023 | 11/Jul/2023 | 270 days | 71 | 100 | 71 | 0.00 | 09/Oct/2023 | |
| 76 | KNMT/2023-24/095/ROAD/00019 | Relaying of Road-095026R428-CROSS STREET-2 , 095026R427-CROSS STREET-3 , 095026R594-ANNAMALAIYAR NAGAR MAIN STREET , 095026R595-ANNAMALAIYAR NAGAR 1ST CROSS STREET , 095026R596-ANNAMALAIYAR NAGAR 2ND CROSS STREET , 095026R597-ANBU NAGAR MAIN STREET , 095029R508-WEST 1ST CROSS STREET , 095029R511-EAST 1ST CROSS STREET , 095020R349-SIVA SAKTHI NAGAR , 095031R534-ANJANEYA NAGAR , | G.O. (4D) No. 22 | 21/Jun/2023 | 148 | 256 | 14/Jun/2023 | 77 | 10/Jul/2023 | 14/Jul/2023 | 270 days | 77 | 100 | 76.95 | 0.00 | 12/Oct/2023 | |
| 77 | KNMT/2024-25/095/BUILDING/00029 | Construction of daily market (Chennai to Kumbakonam Highways) at Ward No. A, T.S. No. 108, Block No. 49 In Panruti Municipality | 2015/2024/ P1 | 12/Jul/2024 | 582 | 55 | 24/Jul/2024 | 582 | 08/Oct/2024 | 08/Oct/2024 | 540 Days | 582 | 0 | Market work Dropped on G.O (4D) No.12 Date 17.02.2026 | 0 | 0.00 | 01/Apr/2026 |
| 78 | KNMT/2024-25/095/PARK/00031 | Developments of park and play field at Saraswathi Nagar in ward No. 26 (ward No. A, Survey No. 220/4, 221/4, 226/11,12, Block No. 34) in Panruti Municipality | 2105 /2024/P1 | 12/Jul/2024 | 25 | 1 | 12/Jul/2024 | 25 | 17/Oct/2024 | 17/Oct/2024 | 270 Days | 25 | 100 | Work Completed | 21.68 | 0.00 | 14/Jul/2025 |
| 79 | KNMT/2024-25/095/ROAD/00013 | Formation of New Road-Earthern to BT Road095016R262-OSURAN AMMAN KOIL WEST CROSS STREET , 095016R267-1ST CROSS STREET(VARATHARAJAPURAM) , 095024R404-CROSS STREET 1 , 095025R411-SEELAKARA CROSS STREET-2 , 095025R413-ANJANEYA NAGAR 2 , 095025R414-ANJANEYA NAGAR 1 , 095031R524-LAKSHMIPATHY NAGAR WEST 1ST CROSS STREET , 095031R533-VSP NAGAR EXTENSION UP TO ELUPAI THOPPU , 095031R537-VSP NAGAR MAIN STREET 5TH CROSS , 095032R554-ERULANKUPPAM NORTH STREET , 095033R570-EAST SIDE EARTHERN ROAD 1 , 095028 | 2105/2024/P1 | 31/Jan/2024 | 73 | 334/2024-25 | 02/Feb/2024 | 73 | 29/Feb/2024 | 29/Feb/2024 | 270 days | 73 | 100 | 72.98 | 99.97 | 29/May/2024 | |
| 80 | KNMT/2024-25/095/TW013/00030 | Modernization of old Bus Stand and Shops at Ward No.06, Survey No.68,103,104 In Panruti Municipality. | 2105/2024/P1, | 12/Jul/2024 | 470 | 47 | 24/Jul/2024 | 470 | 08/Oct/2024 | 08/Oct/2024 | 540 Days | 470 | 88 | Floor Tile Work, Plumbing And Electrical Work Completed. Painting Work Is In Progress . Out Of 6343M2 Cc Road Work , 2500M2 Work Completed. Balance Work in Progress | 276.53 | 0.00 | 01/Apr/2026 |
| 81 | KNMT/2025-26/095/CULVERT/00040 | Construction of Culvert with Cover Slab at T.Rasapalayam Cross Street 5(095033R578),T.Rasapalayam Cross Street 4(095033R579),T.Rasapalayam Cross Street 3(095033R581),T.Rasapalayam Main road(095033R565),T.Rasapalayam Colony Main street – 2(095033R574),T.Rasapalayam Cross Street 7(095033R575),Koil Cross Street(095033R576),T.Rasapalayam Cross Street 6(095033R577),T.Rasapalayam main street(095033R564),T.Rasapalayam Cross Street 3(095033R582),T.Rasapalayam colony main street – 2(095033R573) in Panrut | G .D (4D) No. 24 | 19/May/2025 | 3 | 36/2025-26 | 19/May/2025 | 3 | 20/Jun/2025 | 20/Jun/2025 | 90 Days | 3 | 100 | Completed | 6 | 100.00 | 18/Sep/2025 |
| 82 | KNMT/2025-26/095/CULVERT/00041 | Construction of Culvert with Cover Slab at TCross street 1 (devagi nagar)(095027R459),Cross street 3(095027R463),Cross street 2(095027R485),Vadivelan nagar main street(095027R469),Cross street 1 (devagi nagar)(095027R468),Cross street 1(095027R483),Devaki nagar main street(095027R460),Thayarammal nagar main street(095027R456),East cross street 5(095027R461),West cross street 2(095027R458),Cross street 4(095027R462),Cross street 1 (devagi nagar)(095027R465),Dhanalakshmi nagar main street(095027R4 | G.D ( 4D) No. 24 | 19/May/2025 | 3 | 37/2025-26 | 19/May/2025 | 3 | 20/Jun/2025 | 20/Jun/2025 | 90 Days | 3 | 100 | Completed | 3 | 100.00 | 18/Sep/2025 |
| 83 | KNMT/2025-26/095/CULVERT/00042 | Construction of Culvert with Cover Slab at West cross street-1(095026R443),West cross street-5(095026R446),Cross street-2(095026R445),Vengatta nagar(095026R434),Muthiah nagar main street(095026R450),West cross street 4(095026R447),Cross street-3(095026R444),North cross street 1(095026R451) in Panruti Municipality | G.D (4D ) No. 24 | 19/May/2025 | 3 | 38/2025-26 | 19/May/2025 | 3 | 20/Jun/2025 | 20/Jun/2025 | 90 Days | 3 | 100 | Completed | 3 | 100.00 | 18/Sep/2025 |
| 84 | KNMT/2025-26/095/PARK/00035 | Development of park and Play Field at Rasi Nagar, in ward No.7, (Ward no.B,Survey No.1/1, Block No 3-4,) Panruti Municiaplity | G.O (4D) No.20 | 08/May/2025 | 34 | 35/2025-26 | 09/May/2025 | 34 | 20/Jun/2025 | 20/Jun/2025 | 180 Days | 34 | 100 | Completed | 33.94 | 99.84 | 17/Dec/2025 |
| 85 | KNMT/2025-26/095/ROAD/00031 | Formation of New Road-Earthern to BT Road095001R005-BANUPRIYA NAGAR CROSS STREET-5 , 095001R006-BANUPRIYA NAGAR CROSS STREET-4 , 095001R007-BANUPRIYA NAGAR CROSS STREET-3 , 095007R109-A PA SIVARAMAN NAGAR EAST 2ND CROSS STREET , 095013R194-VALKARAR STREET CROSS ST 1 , 095016R268-VSP NAGAR SOUTH 1ST CROSS STREET , 095016R274-WEST 1ST CROSS STREET , 095016R283-CONNECTING ILUPPAIA THOPPU , 095016R285-RAGAVENDIRA NAGAR MAIN STREET , 095016R284-RAGAVENDIRA NAGAR SOUTH SIDE 2ND STREET , 095016R295-RAJ | Miniutes of the 8th Meeting of the CPS and Monitoring Committee to Consider the KNMT on 02.04.25 | 02/Apr/2025 | 179 | 18484/2023/DO1 | 07/Apr/2025 | 179 | 16/May/2025 | 16/May/2025 | 90 Days | 179 | 100 | completed | 179 | 100.00 | 14/Aug/2025 |
| 86 | KNMT/2025-26/095/SWD/00036 | Construction of Storm Water Drain with Cover Slab at T.Rasapalayam Cross Street 5(095033R578),T.Rasapalayam Cross Street 4(095033R579),T.Rasapalayam Cross Street 3(095033R581),T.Rasapalayam Main road(095033R565),T.Rasapalayam Colony Main street – 2(095033R574),T.Rasapalayam Cross Street 7(095033R575),Koil Cross Street(095033R576),T.Rasapalayam Cross Street 6(095033R577),T.Rasapalayam main street(095033R564),T.Rasapalayam Cross Street 3(095033R582),T.Rasapalayam colony main street – 2(095033R573) | G.O (4D) No.24 | 19/May/2025 | 72 | 75/2025-26 | 19/May/2025 | 72 | 07/Jul/2025 | 07/Jul/2025 | 180 Days | 72 | 100 | Work Completed | 69.44 | 0.00 | 03/Jan/2026 |
| 87 | KNMT/2025-26/095/SWD/00037 | Construction of Storm Water Drain with Cover Slab at TCross street 1 (devagi nagar)(095027R459),Cross street 3(095027R463),Cross street 2(095027R485),Vadivelan nagar main street(095027R469),Cross street 1 (devagi nagar)(095027R468),Cross street 1(095027R483),Devaki nagar main street(095027R460),Thayarammal nagar main street(095027R456),East cross street 5(095027R461),West cross street 2(095027R458),Cross street 4(095027R462),Cross street 1 (devagi nagar)(095027R465),Dhanalakshmi nagar main stree | G.O. (4D) NO 24 | 19/May/2025 | 95 | 77/2025-26 | 19/May/2025 | 95 | 07/Jul/2025 | 07/Jul/2025 | 180 Days | 95 | 100 | Work Completed | 92.08 | 96.93 | 03/Jan/2026 |
| 88 | KNMT/2025-26/095/SWD/00038 | Construction of Storm Water Drain with Cover Slab at West cross street-1(095026R443),West cross street-5(095026R446),Cross street-2(095026R445),Vengatta nagar(095026R434),Muthiah nagar main street(095026R450),West cross street 4(095026R447),Cross street-3(095026R444),North cross street 1(095026R451) in Panruti Municipality | G.D (4D) N o. 24 | 19/May/2025 | 80 | 76/2025-26 | 19/May/2025 | 80 | 07/Jul/2025 | 07/Jul/2025 | 180 Days | 80 | 100 | Work Completed | 0 | 0.00 | 03/Jan/2026 |
| 89 | KNMT/2025-26/095/SWD/00039 | Construction of Storm Water Drain with Cover Slab at kamaraj nagar(nandha gopal)(095019R328),police line 1st street(095019R330),police line 1st street(095019R335),police line 2nd cross street(095019R336),kamaraj nagar1st cross street mla(095019R338),police line 1st street(095019R341),kamaraj nagar(095019R322),police line 3rd street(095019R337),Melapalayam pattai upto vsp nagar(095016R260) in Panruti Municipality | G.D (4D) No. 24 | 19/May/2025 | 79 | 78/2025-26 | 19/May/2025 | 79 | 07/Jul/2025 | 07/Jul/2025 | 180 Days | 79 | 100 | Work completed | 74.98 | 0.00 | 03/Jan/2026 |
| 90 | KNMT/2025-26/095/WB/00034 | Improvement and Rejuvenation of water bodies at vellai kolam ward no . 32 D, Block no.13, survey no.11/1.in Panruti Municipality | G.O (4 D)No.20 | 08/May/2025 | 50 | 74/2025-26 | 12/May/2025 | 50 | 20/Jun/2025 | 20/Jun/2025 | 180 Days | 50 | 65 | Fencing work and Footpath Work in Progress | 19.04 | 0.00 | 17/Dec/2025 |
| 91 | KNMT/2025-26/095/WS/00033 | Improvements of Water Supply System to Panruti Municipality, | G.O (4D) No.14 | 21/Apr/2025 | 2279 | 18484/2023/DO1 | 06/May/2025 | 2279 | 07/Jul/2025 | 07/Jul/2025 | 365 Days | 2279 | 55 | Out Of 10 Oht’s-8 Oht’s Roof Laid, 1 Oht Side wall raising work in progress, 1 Oht Floor slab shuttering and steel Fabrication completed and Spiral staircase raising work in progress, Distribution Pipe Laying Work Out Of 84.90 Km, 61.00 Km Completed Balance Work In Progress | 450.18 | 0.00 | 07/Jul/2026 |
| Name of the Scheme : MLA Fund | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 92 | MLA/2022-23/095/BUILDING/00038 | Construction of Funeral Hall at in Ward no.1 V.Andikuppam in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 33 | 10/Feb/2023 | 8 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 8 | 100 | 7.17 | 0.00 | 22/Jun/2023 | |
| 93 | MLA/2022-23/095/BUILDING/00039 | Construction of Funeral Hall at in Ward no.15 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 36 | 10/Feb/2023 | 8 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 8 | 100 | 7.23 | 0.00 | 22/Jun/2023 | |
| 94 | MLA/2022-23/095/BUILDING/00040 | Construction of RCC Burning Shed at Ward no.16 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 37 | 10/Feb/2023 | 7 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 7 | 100 | 5.81 | 0.00 | 22/Jun/2023 | |
| 95 | MLA/2022-23/095/BUILDING/00041 | Construction of Funeral Hall at in Ward no.25 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 40 | 10/Feb/2023 | 8 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 8 | 100 | 2.86 | 0.00 | 22/Jun/2023 | |
| 96 | MLA/2022-23/095/BUILDING/00042 | Construction of Funeral Hall at in Ward no.27 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 41 | 10/Feb/2023 | 8 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 8 | 100 | 3.06 | 0.00 | 22/Jun/2023 | |
| 97 | MLA/2022-23/095/BUILDING/00043 | Construction of Anganwadi Building at in Ward no.20 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 39 | 10/Feb/2023 | 13 | 11/May/2023 | 11/May/2023 | 270 days | 13 | 100 | 9.79 | 0.00 | 07/Nov/2023 | |
| 98 | MLA/2022-23/095/BUILDING/00044 | Construction of Anganwadi Building at in Ward no.32 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 42 | 10/Feb/2023 | 13 | 11/May/2023 | 11/May/2023 | 270 days | 13 | 100 | 9.79 | 0.00 | 07/Nov/2023 | |
| 99 | MLA/2022-23/095/CULVERT/00035 | Construction of Drain,Culvert and Cement concrete road W.no.7 Thiruvallour 1st street and cross street in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 34 | 10/Feb/2023 | 10 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 10 | 100 | 8.26 | 0.00 | 22/Jun/2023 | |
| 100 | MLA/2022-23/095/CULVERT/00036 | Construction of Bath Room, Drain and Culvert at Ward no. 19 in Panruti Municipality | A2/5810/2021 | 10/Feb/2023 | 95 | 38 | 10/Feb/2023 | 10 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 10 | 100 | 9.23 | 0.00 | 22/Jun/2023 | |
| 101 | MLA/2022-23/095/ROAD/00037 | Relaying of Road-Cement Concrete Road095011S027-CHETTIPATTARAI COLONY LEFT SIDE 6TH CROSS , 095011S026-CHETTIPATTARAI COLONY RIGHT SIDE 2ND CROSS , 095011R169-CHETTIPATTARAI COLONY RIGHT SIDE 2ND CROSS , | A2/5810/2021 | 10/Feb/2023 | 95 | 35 | 10/Feb/2023 | 10 | 24/Mar/2023 | 24/Mar/2023 | 270 days | 10 | 100 | 9.38 | 0.00 | 22/Jun/2023 | |
| Name of the Scheme : Nagarpura Salai Mempattu Thittam | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 102 | NSMT/2022-23/095/ROAD/00012 | Relaying of Road-095/2021/001/R/0000446-SIVAN PADAI ST , 095/2022/002/R/0000245-VIZHAMANGALAM WEST CROSS STREET-2 , 095/2022/002/R/0000243-VIZHAMANGALAM WEST CROSS STREET-1 , 095/2022/003/R/00006-AVULIYA NAGAR-2 , 095/2022/007/R/0000158-THIRUVALLUVAR NAGAR 3RD CROSS STREET , 095/2022/008/R/0000109-ADAMKHAN DARGA (2ND CROSS) , 095/2021/008/S/0000199-ADAMKHAN DARGA (3RD CROSS) , 095/2021/010/R/0000378-PAKKIRIPALAYAM COLONY MAIN STREET-2 , 095/2022/018/R/000049-POLICE LINE 4TH STREET , 095/2022/01 | G.O. (D) No. 192 | 31/Mar/2023 | 68 | 221/2022-23 | 11/Apr/2023 | 68 | 11/May/2023 | 11/May/2023 | 270 days | 68 | 100 | 36.91 | 54.28 | 09/Aug/2023 | |
| 103 | NSMT/2022-23/095/ROAD/00013 | Relaying of Road-095/2022/027/R/000083-LINK ROAD (FROM DIVERSION ROAD TO , | G.O. (D) No.192 | 31/Mar/2023 | 10 | 39 | 01/Apr/2023 | 10 | 11/May/2023 | 11/May/2023 | 270 days | 10 | 100 | 10 | 0.00 | 09/Aug/2023 | |
| 104 | NSMT/2023-24/095/ROAD/00031 | Relaying of Road-Cement Concrete Road095002R040-V. PILLIYAR KOIL STREET , 095002R024-PONNAPPAN LANE , 095002R023-GOPAL STREET , 095003R057-VOC NAGAR MAIN ROAD , 095004R072-KASTHURIBAI STREET , 095005R075-JAWAHAR MAIN STREET , 095005R074-PONNUSAMY STREET , 095002R022-NALVAR STREET , | Minutes of the meeting PSMC1 | 06/Jun/2023 | 56 | 264/2023-2024 | 21/Jun/2023 | 56 | 21/Jul/2023 | 21/Jul/2023 | 270 days | 56 | 100 | completed | 56 | 0.00 | 19/Oct/2023 |
| 105 | NSMT/2023-24/095/ROAD/00032 | Relaying of Road-Cement Concrete Road095007R113-A PA SIVARAMAN NAGAR 1ST CROSS STREET , 095007R108-A PA SIVARAMAN NAGAR EAST 2ND CROSS STREET , 095008R114-ADAMKHAN DARGA , 095009R123-RAILWAY COLONY TEMPLE LEFT SIDE , 095013R198-KANNAGI STREET , 095013R189-ANAIPILLAI STREET , 095013R200-SUNAMMABUKARA STREET , 095013R201-BHARATHI STREET , 095014R230-PUTHU PALLIVASAL STREET , 095014R231-EDAPALAYAM 1ST STREET , | Minutes of the meeting PSMC2 | 09/Jun/2023 | 66 | 265/2023-2024 | 21/Jun/2023 | 66 | 21/Jul/2023 | 21/Jul/2023 | 270 Days | 66 | 100 | completed | 66 | 100.00 | 16/Apr/2024 |
| 106 | NSMT/2023-24/095/ROAD/00033 | Relaying of Road-Cement Concrete Road095017R299-POLICE LINE 7TH STREET(R29) , 095020R344-AVAYAMPALAYAM STREET , 095020R345-AVAIPUTHU STREET , 095022R368-KUCHIPALAYAM STREET , 095023R381-VANUVAR STREET , 095025R418-AADHIPILLAI STREET , | Minutes of the meeting PSMC3 | 06/Jun/2023 | 71 | 266/2023-2024 | 21/Jun/2023 | 71 | 21/Jul/2023 | 21/Jul/2023 | 270 days | 71 | 100 | completed | 70.78 | 0.00 | 19/Oct/2023 |
| Name of the Scheme : Namakku Naame Thittam | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 107 | NAMAKKU NA/2021-22/095/BUILDING/00095 | Construction of Additional Toillet Block and Rejunevation of Existing Toilet Block at ward no. 3, Dharga Vandimedu Municipal School in Panruti Municipality | ROC.NO 27519-36/2021/P2–I-Panruti-1 | 30/Apr/2022 | 9.9 | 3/2021-2022 | 30/Apr/2022 | 9.9 | 25/May/2022 | 27/May/2022 | 270 days | 9.9 | 100 | 9.87 | 0.00 | 24/Sep/2022 | |
| 108 | NAMAKKU NA/2021-22/095/BUILDING/00097 | Construction of RCC Burning Shed at ward no.24, A. Mani Nagar Burial Ground near Compost Yard | ROC.NO 27519-36/2021/P2–I-Panruti-2 | 30/Apr/2022 | 6.5 | 4/2021-2022 | 30/Apr/2022 | 6.5 | 25/May/2022 | 27/May/2022 | 270 days | 6.5 | 100 | 6.5 | 0.00 | 24/Sep/2022 | |
| 109 | NAMAKKU NA/2021-22/095/BUILDING/00124 | Repair & Renovation of Toilet & Urinal Block @ Ward No.2 in Vilamangalam Municipal school. | 27519-51/2021/P2 | 13/Sep/2022 | 24.7 | TS-16 | 13/Sep/2022 | 4.5 | 14/Oct/2022 | 17/Oct/2022 | 270 days | 4.5 | 100 | 4.35 | 96.72 | 12/Feb/2023 | |
| 110 | NAMAKKU NA/2021-22/095/PURCHASE/00099 | Supply and Delivery of Table cum Desk 12 nos and computer 2 nos with other accessories to T.N. Pavadai Pillai Municipal High School | ROC.NO 27519-38/2021/P2 | 30/Apr/2022 | 3 | 2/2021-2022 | 30/Apr/2022 | 3 | 25/May/2022 | 27/May/2022 | 270 days | 3 | 100 | 2.98 | 0.00 | 15/Aug/2022 | |
| 111 | NAMAKKU NA/2021-22/095/PURCHASE/00100 | Supply and Delivery of Table cum Desk 7 nos and computer 1 nos with other accessories to Melapalayam Municipal Middle School | ROC.NO 27519-38/2021/P2-1 | 30/Apr/2022 | 1.7 | 5/2021-22 | 30/Apr/2022 | 1.7 | 25/May/2022 | 27/May/2022 | 270 days | 1.7 | 100 | 1.66 | 0.00 | 15/Aug/2022 | |
| 112 | NAMAKKU NA/2021-22/095/ROAD/00121 | Providing CC Road at WD 21 Thiru Nagar Cross street 3 Relaying of Road-095/2021/021/R/0000153-EAST CROSS STREET-1 , | 27519-51/2021/P2 | 13/Sep/2022 | 24.7 | TS-15 | 13/Sep/2022 | 3.7 | 14/Oct/2022 | 17/Oct/2022 | 270 days | 3.7 | 100 | 3.49 | 0.00 | 14/Dec/2022 | |
| 113 | NAMAKKU NA/2021-22/095/SWD/00096 | Construction of Strom Water Drain for 85m length and Relaying of CC Road for 37 m length, 4.00m width at ward no. 22 Kamaraj street (Unicode No. 095022R372) | ROC.NO 27519-36/2021/P2–I-Panruti | 30/Mar/2022 | 5 | 88/2021-2022 | 14/Mar/2022 | 5 | 25/May/2022 | 27/May/2022 | 270 days | 5 | 100 | 5 | 0.00 | 26/Jul/2022 | |
| 114 | NNT/2022-23/095/ROAD/00005 | Relaying of Road-095/2022/027/R/000012-PANCHAVARNAM NAGAR STREET , | 837/2022/B1_22 | 16/Mar/2023 | 7.85 | 94 | 16/Mar/2023 | 7.85 | 17/Apr/2023 | 17/Apr/2023 | 270 days | 7.85 | 100 | 7.84 | 0.00 | 16/Jul/2023 | |
| 115 | NNT/2022-23/095/ROAD/00006 | Relaying of Road-095/2022/022/R/000043-KAMARAJ STREET , | 837/2022/B1_21 | 16/Mar/2023 | 12 | 93 | 16/Mar/2023 | 12 | 17/Apr/2023 | 17/Apr/2023 | 270 Days | 12 | 100 | 12 | 100.00 | 12/Jan/2024 | |
| 116 | NNT/2022-23/095/ROAD/00007 | Repair /Maintenance-095/2022/023/R/000033-VADAMALAI RAMASAMY STREET , | 837/2022/B1_23 | 16/Mar/2023 | 7.7 | 91 | 16/Mar/2023 | 7.7 | 17/Apr/2023 | 17/Apr/2023 | 270 days | 7.7 | 100 | 7.68 | 0.00 | 16/Jul/2023 | |
| 117 | NNT/2022-23/095/SWD/00008 | Construction of drain and culvert at Ward No.19, Kamarajar Nagar, (Dr.Nandha Gopal) Unicode No.095019R328 & 329 | 837/2022/B1_24 | 16/Mar/2023 | 9.38 | 92 | 16/Mar/2023 | 9.38 | 17/Apr/2023 | 17/Apr/2023 | 270 days | 9.38 | 100 | 9.38 | 0.00 | 16/Jul/2023 | |
| 118 | NNT/2022-23/095/SWD/00028 | Construction of Drain and Culvert at Wno 8 VMS Nager Main street Unicode No 095008R118,1st Cross street Unicode No 095008R119 and 2nd Cross street Unicode No 095008R120 in Panruti Municipality. | 1042/2022/A1 | 06/Jul/2023 | 11.45 | 28 | 07/Jul/2023 | 11.45 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 11.45 | 100 | 11.45 | 0.00 | 16/Oct/2023 | |
| 119 | NNT/2024-25/095/ROAD/00046 | PROVIDING PAVER BLOCK ROAD AT SAIBABA COLONY IN WARD NO : 21 | 435/2024/E1 | 02/Sep/2024 | 9.25 | 4 | 06/Sep/2024 | 9.25 | 30/Sep/2024 | 30/Sep/2024 | 270 days | 9.25 | 0 | Awaiting for funds | 0 | 0.00 | 29/Dec/2024 |
| 120 | NNT/2025-26/095/BUILDING/00053 | Construction of RCC Bus Shelter at Ward No. 26 Kokkupalayam Road in Panruti Municipality. | 15236/2025 /T2-1 | 01/Feb/2026 | 12 | 87/2025-26 | 04/Feb/2026 | 12 | 20/Feb/2026 | 20/Feb/2026 | 90 Days | 12 | 65 | Plastering work in Progress | 0 | 0.00 | 21/May/2026 |
| 121 | NNT/2025-26/095/PARK/00051 | Construction of Compound Fencing and play material at Ward No. 27 Panchavarnam Nagar Park in Panruti Municipality | 15236/2025/T2-1 | 01/Feb/2026 | 12 | 85/2025-26 | 04/Feb/2026 | 12 | 20/Feb/2026 | 20/Feb/2026 | 90 Days | 12 | 60 | Foot Path and Paver Block Work Completed. Balance work In Progress | 0 | 0.00 | 21/May/2026 |
| 122 | NNT/2025-26/095/SWD/00052 | Construction of Drain and Culvert at Ward No.31 Lakshmi Pahti nagar Main street in Panruti Municipality. | 15236 /2025/T2-1 | 01/Feb/2026 | 12 | 86/2025-26 | 04/Feb/2026 | 12 | 20/Feb/2026 | 20/Feb/2026 | 90 Days | 12 | 100 | Work Completed | 0 | 0.00 | 21/May/2026 |
| Name of the Scheme : O&M AND INFRA GAP FILLING FUND | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 123 | O&M AND IN/2021-22/095/BUILDING/00015 | Repairs and Maintenance to Bus Stand Public free toilet in Panruti Municipality | 19089/2021/E2 | 19/Dec/2020 | 13.85 | 42/2021-2022 – 1 | 22/Nov/2021 | 2.45 | 03/Jan/2022 | 03/Mar/2022 | 270 days | 1.88 | 100 | 2.45 | 0.00 | ||
| 124 | O&M AND IN/2021-22/095/BUILDING/00030 | Repairs and maintenance to A.Andikuppam community toilet at ward no.32 in panruti municipality | 19089/2021/E2 | 19/Dec/2020 | 13.85 | 45/2021-2022 – 4 | 22/Nov/2021 | 3.7 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 3.03 | 100 | 3.7 | 0.00 | 25/Jul/2022 | |
| 125 | O&M AND IN/2021-22/095/BUILDING/00032 | Repairs and maintenance to Erulankuppam community toilet at ward no.32 in Panruti municipality | 19089/2021/E2 | 19/Dec/2020 | 13.85 | 44/2021-2022 – 3 | 22/Nov/2021 | 2.75 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 2.75 | 100 | 2.22 | 80.61 | 25/Jul/2022 | |
| 126 | O&M AND IN/2021-22/095/BUILDING/00094 | Repairs and maintenance to PTS Mani Nagar Community Toilet at Ward.06 in Panruti Municpality | 19089/2021/E2 | 19/Dec/2020 | 13.85 | 43/2021-2022 – 2 | 22/Nov/2021 | 4.95 | 03/Jan/2022 | 03/Jan/2022 | 270 days | 4.29 | 100 | 2.33 | 0.00 | 04/Mar/2022 | |
| Name of the Scheme : SBM | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 127 | SWACH BHAR/2018-19/095/SWM/00066 | Construction of MCC with a capacity of 3 TPD at ward.11 Chairman Mani Nagar in panruti municipality | 1191/B3/2019-Rs.11600000 | 21/Jan/2019 | 116 | 898/2018-19 – 1 | 01/Feb/2019 | 58 | 01/Mar/2019 | 01/Mar/2019 | 270 days | 58 | 0 | Work Cancellation letter submitted to the CMA office,Chennai ROC. 3432/2022/E1 Dt 23.02.2023 | 0 | 0.00 | |
| 128 | SWACH BHAR/2018-19/095/SWM/00080 | Construction of MCC with a capacity of 3 TPD at ward.29 Devaraj Nagar | 1191/B3/2019-Rs.11600000 | 21/Jan/2019 | 116 | 900/2018-19 – 2 | 01/Feb/2019 | 58 | 01/Mar/2019 | 01/Mar/2019 | 270 days | 58 | 100 | 39.12 | 0.00 | 30/May/2019 | |
| Name of the Scheme : SBM 2.0 | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 129 | SBM 2.0/2023-24/095/PURCHASE/00034 | Supply and delivery of cesspool truck suction machine with blow back (12 ton GVW (BS VI )) chessis 6000 litre capacity and vacum pump 500 cum/hr -1 No | 9192/2022/SBM1 | 21/Jul/2023 | 86.5 | 19 | 21/Aug/2023 | 86.5 | 17/Nov/2023 | 17/Nov/2023 | 270 days | 86.5 | 100 | 86.46 | 99.95 | 15/Feb/2024 | |
| 130 | SBM 2.0/2024-25/095/BUILDING/00001 | Renovation of community toilet in ward no 24 Nandhanar colony | 26740/2024/SBM-1(1) | 26/Sep/2024 | 3.8 | 14 | 27/Sep/2024 | 3.8 | 02/Dec/2024 | 03/Dec/2024 | 270 Days | 3.8 | 0 | Awaiting for funds | 3.8 | 0.00 | 30/Aug/2025 |
| 131 | SBM 2.0/2024-25/095/BUILDING/00002 | Renovation of community toilet in ward no 27 Panchavarnam Nagar (iyyanar Kovil Pattai) | 26740/2024/SBM-1( 1) | 26/Sep/2024 | 9 | 15/2024-25 | 27/Sep/2024 | 9 | 02/Dec/2024 | 03/Dec/2024 | 270 days | 9 | 0 | Awaiting for funds | 0 | 0.00 | 03/Mar/2025 |
| 132 | SBM 2.0/2024-25/095/BUILDING/00003 | Renovation of Community Toilet in Ward No.09 Railway Colony | 26740/2024/SBM-1 (1) | 26/Sep/2024 | 6 | 16 | 27/Sep/2024 | 6 | 02/Dec/2024 | 03/Dec/2024 | 270 days | 6 | 0 | Awaiting for funds | 0 | 0.00 | 03/Mar/2025 |
| 133 | SBM 2.0/2024-25/095/BUILDING/00004 | Renovation of community Toilet in ward No 15 Near Sivan Kovil Thiruvathigai | 26740/ 2024/SBM-1(1) | 26/Sep/2024 | 6 | 17 | 27/Sep/2024 | 6 | 02/Dec/2024 | 03/Dec/2024 | 270 days | 6 | 0 | Awaiting for funds | 0 | 0.00 | 03/Mar/2025 |
| 134 | SBM 2.0/2024-25/095/BUILDING/00019 | Construction of Public Toilet Block at ward no.20, GH Building Campus in Panruti Municipality. | 192/2025/SBM-1 | 18/Mar/2025 | 29 | 41/2024-25 | 18/Mar/2025 | 29 | 15/Apr/2025 | 15/Apr/2025 | 270 Days | 29 | 100 | Work Completed | 4.93 | 0.00 | 10/Jan/2026 |
| 135 | SBM 2.0/2024-25/095/BUILDING/00025 | Construction of new public toilet at ward no.24 in Panruti municipality | 6450/2024/SBM-1(1) | 14/Mar/2024 | 15 | 66 | 14/Mar/2024 | 15 | 18/Jun/2024 | 18/Jun/2024 | 270 days | 15 | 100 | Completed | 11.17 | 0.00 | 15/Dec/2024 |
| 136 | SBM 2.0/2024-25/095/BUILDING/00026 | Construction of new community toilet at ward no.06 in Ambethkar nagar Panruti Municipality | 6450/2024/SBM-1_(1) | 14/Mar/2024 | 9 | 67 | 14/Mar/2024 | 9 | 18/Jun/2024 | 18/Jun/2024 | 270 days | 9 | 100 | completed | 7.28 | 0.00 | 15/Dec/2024 |
| 137 | SBM 2.0/2024-25/095/BUILDING/00027 | Construction of urinal block at ward no.06 Panruti bus stand in Panruti municipality | 6450/2024/SBM-1 (1) | 14/Mar/2024 | 1.6 | 68 | 14/Mar/2024 | 1.6 | 18/Jun/2024 | 18/Jun/2024 | 270 days | 1.6 | 100 | 1.42 | 88.58 | 16/Sep/2024 | |
| 138 | SBM 2.0/2024-25/095/SWM/00024 | Construction of 5TPD Material Recovery Facility Center At Ward No.24 Mani Nagar in Panruti Municipality | 2090/2021/A1 | 08/Mar/2024 | 42.5 | 375/2023-2024 | 08/Mar/2024 | 42.5 | 27/Jun/2024 | 27/Jun/2024 | 270 days | 42.5 | 100 | work Completed | 39.82 | 0.00 | 24/Dec/2024 |
| 139 | SBM 2.0/2024-25/095/UWM/00007 | DESIGN, CONSTRUCTION, SUPPLY, ERECTION, COMMISSIONING, 5.00 MLD CAPACITY SEWAGE TREATMENT PLANT (STP) WITH 10 YEARS OF OPERATION & MAINTENANCE IN PANRUTI MUNICIPALITY | Minutes of the 8th meeting of state high powered committee under Swachh Bharat Mission (u)2.0 | 24/Jul/2024 | 834 | 179-1/2024-25 | 12/Sep/2024 | 834 | 15/May/2025 | 15/May/2025 | 360 Days | 834 | 49 | Collection Tank Side Wall 4Th Lift Concrete Work Completed And Secondary Clarifier Tank , Filter Feed Tank , Chlorine contact tank, Sludge Thickener ,Sludge Drying Bed Pile Foundation Work out of 301Nos 242Nos completed. and foundation base Slab steel fabrication work in Progress |
192.59 | 0.00 | 10/May/2027 |
| 140 | SBM 2.0/2024-25/095/UWM/00008 | Interception and Diversion (I&D) works for Panruti Municipality | Minutes of the 8th meeting of state high powered committee under swachh bharat mission (u )2.0 | 24/Jul/2024 | 522 | 179/2024-25 | 12/Sep/2024 | 522 | 07/May/2025 | 07/May/2025 | 360 Days | 522 | 47 | 250Mm Hdpe Pipe – Out Of 600M Length Completed. 400 Hdpe M Pipe – Out Of 2400 M Length 1800M Line Laying Work Completed. Balance 600M Pipe Line Laying Work In Progress Out Of 3 Collection Well, 1Well Side Wall 3rd Lift Concrete Completed 4th lift Centering Work Progress Remainning 2 Collection Well 1 well Earth Work Completed 1 well to be Started | 436.4 | 0.00 | 02/May/2027 |
| 141 | SWACH BHAR/2021-22/095/SANITATION/00101 | Construction of New Community Toilet block at WD No. 30 Devaraj Nagar near RRC center in Panruti Municipality | 001/2022/DO1 | 22/Apr/2022 | 24 | 4/2021-2022 | 11/May/2022 | 24 | 03/Jun/2022 | 06/Jun/2022 | 270 days | 24 | 100 | 22.24 | 0.00 | 03/Dec/2022 | |
| 142 | SWACHH BHA/2021-22/095/SANITATION/00004 | Constuction 77 Nos Individual House Hold Latrine | 18856/3 | 13/Jul/2022 | 23.1 | 6391/2022/SBM-1 | 05/Jan/2023 | 7.19 | 23/Jan/2023 | 23/Jan/2023 | 270 days | 7.19 | 100 | 7.19 | 0.00 | 22/Jul/2023 | |
| 143 | SWACHH BHA/2022-23/095/SWM/00003 | Reclamation of Land through Bio mining of Legacy Waste in Panruti Municipality (Quantity of Legacy Waste in 14426 Cu.m) | 19009/2022/SBM-1 | 25/Nov/2022 | 97 | 125 | 15/Dec/2022 | 97 | 12/Jun/2023 | 12/Jun/2023 | 270 days | 97 | 100 | Completed | 82.51 | 85.06 | 03/Feb/2024 |
| Name of the Scheme : SFC ARREAR FUND | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 144 | SFC/2023-24/095/ROAD/00020 | Relaying of Road-095002R026-RAMAN STREET , 095003R065-DARGA VANDIMEDU MAIN STREET – 1 , | 1043/2023/b1_4 | 06/Jul/2023 | 18.5 | 3 | 07/Jul/2023 | 18.5 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 18.5 | 100 | 15.91 | 0.00 | 16/Sep/2023 | |
| 145 | SFC/2023-24/095/ROAD/00021 | Relaying of Road-095004R068-APPALU STREET , 095014R232-1ST CROSS IN EDAPALAYAM IN 2ND , 095014R233-1ST CROSS IN EDAPALAYAM IN 2ND , 095014R221-CROSS STREET-1 , | 1043/2023/b1_6 | 06/Jul/2023 | 17.5 | 5 | 07/Jul/2023 | 17.5 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 17.5 | 100 | 17.46 | 0.00 | 16/Sep/2023 | |
| 146 | SFC/2023-24/095/ROAD/00022 | Relaying of Road-095002R027-THROUPATHI AMMAN KOIL ST , 095003R063-DARGA VANDIMEDU CROSS STREET – 3 , | 1043/2023/b1_5 | 06/Jul/2023 | 17.5 | 4 | 07/Jul/2023 | 17.5 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 17.5 | 100 | 14.42 | 0.00 | 16/Sep/2023 | |
| 147 | SFC/2023-24/095/ROAD/00023 | Relaying of Road-095003R062-DARGA VANDIMEDU SOUTH CROSS STREET – 4 , 095005R076-SOMESWARAN KOIL STREET , 095006R090-RAILWAY FEEDER ROAD , | 1043/2023/B1_7 | 06/Jul/2023 | 19.6 | 6 | 07/Jul/2023 | 19.6 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 19.6 | 100 | 19.59 | 99.97 | 16/Sep/2023 | |
| 148 | SFC/2023-24/095/ROAD/00024 | Relaying of Road-095008R117-SAMIYAR DHARGA , 095016R270-MELAPALAYAM PATTAI UPTO RAMAR KOIL , | 1043/2023/b1_8 | 06/Jul/2023 | 19 | 7 | 07/Jul/2023 | 19 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 19 | 100 | 18.31 | 96.38 | 16/Sep/2023 | |
| 149 | SFC/2023-24/095/ROAD/00025 | Relaying of Road-095007R092-THIRUVALLUVAR NAGAR 4TH STREET , 095007R094-THIRUVALLUVAR NAGAR 3RD CROSS STREET , 095009R133-SARANARAYANA NAGAR 1ST COSS STREET , | 1043/2023/b1_10 | 06/Jul/2023 | 15 | 8 | 07/Jul/2023 | 15 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 15 | 100 | 15 | 100.00 | 16/Sep/2023 | |
| 150 | SFC/2023-24/095/ROAD/00026 | Relaying of Road-095017R301-THANDUPALAYAM COLONY , 095025R416-GANDHI NAGAR 1ST STREET , 095027R489-CROSS STREET 1 , | 1043/2023/b1_11 | 06/Jul/2023 | 12.9 | 9 | 07/Jul/2023 | 12.9 | 18/Jul/2023 | 18/Jul/2023 | 270 days | 12.9 | 100 | 12.9 | 100.00 | 16/Sep/2023 | |
| Name of the Scheme : SFC -SCHOOL IMPROVEMENT GRANT – INFRASTRUCTURE WORKS | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 151 | SFC-SCHOOL/2022-23/095/BUILDING/00045 | Construction of Two New Class Rooms Building to the ward no. 2, Vizhamangalam Municipal Primary School | 6002/2023/SS2 | 26/Oct/2023 | 66 | 6002/2022/SS2 | 01/Nov/2023 | 33 | 04/Dec/2023 | 04/Dec/2023 | 270 days | 33 | 100 | work completed | 21.88 | 0.00 | 01/Jun/2024 |
| 152 | SFC-SCHOOL/2022-23/095/BUILDING/00046 | Construction of Two New Class Rooms Building to the ward no. 33, Rasipalayam Municipal Primary School | 6002/2023/SS2 | 26/Oct/2023 | 66 | 6002/2022/ SS2 | 01/Nov/2023 | 33 | 04/Dec/2023 | 04/Dec/2023 | 270 days | 33 | 100 | completed | 16.74 | 0.00 | 01/Jun/2024 |
| 153 | SFC-SCHOOL/2024-25/095/BUILDING/00032 | Constrution of Two Class Building Central School at Seerankuppam Munipal Middle School In Panruti Municipality | 1 | 22/Jul/2024 | 31 | 2A | 22/Jul/2024 | 31 | 17/Oct/2024 | 17/Oct/2024 | 270 Days | 31 | 100 | completed | 31 | 100.00 | 14/Jul/2025 |
| 154 | SFC-SCHOOL/2024-25/095/BUILDING/00044 | Construction of Single Classroom With G+1 Building at Dharga Vandimedu Urudhu Municipal Primary School in Panruti Municipality | 21615/2024/SS2 | 22/Jul/2024 | 42 | 18 | 24/Jul/2024 | 42 | 17/Oct/2024 | 17/Oct/2024 | 270 Days | 42 | 100 | completed | 41.54 | 98.90 | 14/Jul/2025 |
| 155 | SFC-SCHOOL/2024-25/095/BUILDING/00045 | Construction of New Four Classroom Building to the ward No.12, Thiruvathigai T.N Pavadai Pillai Higher Secondary School in Panruti Municipality | 21615/2024/SS2 | 09/Sep/2024 | 70 | 29 | 10/Sep/2024 | 70 | 06/Nov/2024 | 06/Nov/2024 | 270 Days | 70 | 100 | completed | 69.49 | 99.27 | 03/Aug/2025 |
| Name of the Scheme : SFC -SCHOOL IMPROVEMENT GRANT-O&M WORKS | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 156 | SFCOANDM/2024-25/095/BUILDING/00005 | Reconstruction of Two Class Building in Central School at Arul Jothi Nagar , L.R Palayam Municipal Primary School in Panruti Municipality | 21616-1/2024/ss2 | 11/Nov/2024 | 31 | 18 | 11/Nov/2024 | 31 | 16/Dec/2024 | 16/Dec/2024 | 270 Days | 31 | 100 | completed | 30.88 | 99.62 | 12/Sep/2025 |
| 157 | SFCOANDM/2024-25/095/BUILDING/00006 | Re Construction of two Class Room Building in Central School at Panchavarnam Nagar Municipal Middle School in Panruti Municipality | 21616-2/2024/SS2 | 11/Nov/2024 | 31 | 19 | 11/Nov/2024 | 31 | 16/Dec/2024 | 16/Dec/2024 | 270 Days | 31 | 100 | completed | 30.88 | 99.62 | 12/Sep/2025 |
| 158 | SFCOANDM/2024-25/095/BUILDING/00011 | Construction of Anganwadi building at ward no.6, Ambethkar Nagar in Panruti Municipality. | 21616-3/2024/SS2 | 17/Mar/2025 | 15 | 33/2024-25 | 17/Mar/2025 | 15 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 15 | 100 | Work Completed | 13.31 | 0.00 | 12/Jan/2026 |
| 159 | SFCOANDM/2024-25/095/BUILDING/00012 | Construction of Anganwadi building at ward no.11, Chettipattarai Colony in Panruti Municipality. | 21616-4/2024/SS1 | 17/Mar/2025 | 15 | 34/2024-25 | 17/Mar/2025 | 15 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 15 | 100 | Work Completed | 11.25 | 0.00 | 12/Jan/2026 |
| 160 | SFCOANDM/2024-25/095/BUILDING/00013 | Construction of Anganwadi building at ward no.27, Gandhi Road (Panchavarnam Nagar) in Panruti Municipality. | 21616-5/2024/SS1 | 17/Mar/2025 | 15 | 35/2024-25 | 17/Mar/2025 | 15 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 15 | 100 | Work completed | 13.09 | 0.00 | 12/Jan/2026 |
| 161 | SFCOANDM/2024-25/095/BUILDING/00014 | Maintanance and Repairs Anganvadi at Gandhi Nagar Ward No.25 in Panruti Municipality. | 21616-6/2024/SS2 | 17/Mar/2025 | 4 | 36/2024-25 | 17/Mar/2025 | 4 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 4 | 100 | Work Completed | 4 | 100.00 | 12/Jan/2026 |
| 162 | SFCOANDM/2024-25/095/BUILDING/00015 | Maintanance and Repairs Anganvadi At Jawahar street in Panruti Municipality. | 21616-7/2024/SS2 | 17/Mar/2025 | 2.5 | 37/2024-25 | 17/Mar/2025 | 2.5 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 2.5 | 100 | Work Completed | 2.5 | 100.00 | 12/Jan/2026 |
| 163 | SFCOANDM/2024-25/095/BUILDING/00016 | Maintanance and Repairs Anganvadi At MELAPALAYAM-2 in Panruti Municipality. | 21616-8/2024/SS2 | 17/Mar/2025 | 2.5 | 38/2024-25 | 17/Mar/2025 | 2.5 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 2.5 | 100 | Work Completed | 2.5 | 100.00 | 12/Jan/2026 |
| 164 | SFCOANDM/2024-25/095/BUILDING/00017 | Maintanance and Repairs Anganvadi at Seerankuppam Street in Panruti Municipality. | 21616-9/2024/SS2 | 17/Mar/2025 | 2.5 | 39/2024-25 | 17/Mar/2025 | 2.5 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 2.5 | 100 | Work Completed | 2.5 | 100.00 | 12/Jan/2026 |
| 165 | SFCOANDM/2024-25/095/BUILDING/00018 | Maintanance and Repairs Anganvadi at V.Andikuppam Street in Panruti Municipality. | 21616-10/2024/SS2 | 17/Mar/2025 | 2.5 | 40/2024-25 | 17/Mar/2025 | 2.5 | 17/Apr/2025 | 17/Apr/2025 | 270 Days | 2.5 | 100 | Work completed | 2.5 | 100.00 | 12/Jan/2026 |
| 166 | SFCOANDM/2024-25/095/BUILDING/00033 | Repair and Maintenance of Municipal Primary School (Old Kacheri Street), Thiruvathigai in Panruti Municipality | 21616/2024/SS2 | 22/Jul/2024 | 8 | 3 | 22/Jul/2024 | 8 | 21/Aug/2024 | 21/Aug/2024 | 270 days | 8 | 100 | completed | 8 | 100.00 | 17/Feb/2025 |
| 167 | SFCOANDM/2024-25/095/BUILDING/00034 | Maintanance and Repairs School Buliding At Municipal Primary School in T.Rasapalayam Ward No : 33 in Panruti Municipality. | 21616/2024/ SS2 | 22/Jul/2024 | 10 | 2 | 22/Jul/2024 | 10 | 21/Aug/2024 | 21/Aug/2024 | 270 Days | 10 | 100 | completed | 10 | 100.00 | 18/May/2025 |
| 168 | SFCOANDM/2024-25/095/BUILDING/00035 | Maintenance and Repairs School Building at Municipal Middle School Seerankuppam Ward No:32 in Panruti Municipality. | 21616/2024/SS2, | 10/Sep/2024 | 8.1 | 5 | 10/Sep/2024 | 8.1 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 8.1 | 100 | completed | 8.03 | 99.16 | 11/Jul/2025 |
| 169 | SFCOANDM/2024-25/095/BUILDING/00036 | Maintenance and Repairs School Building At Municipal Middle School Malapalyam Ward No : 18 & 19 in Panruti Municipality. | 21616/2024/SS2. | 10/Sep/2024 | 10 | 6 | 10/Sep/2024 | 10 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 10 | 100 | completed | 10 | 100.00 | 11/Jul/2025 |
| 170 | SFCOANDM/2024-25/095/BUILDING/00037 | Maintenance and Repairs School Building At Municipal Primary School Urudhu Primary School Nandhanar Colony Ward No; 24 in Panruti Municipality. | 21616/ 2024/SS2 | 10/Sep/2024 | 10 | 7 | 10/Sep/2024 | 10 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 10 | 100 | Completed | 10 | 100.00 | 11/Jul/2025 |
| 171 | SFCOANDM/2024-25/095/BUILDING/00038 | Maintenance and Repairs School Building At L.R.Palayam Aruljothi Nagar Ward No; 01 in Panruti Municipality. | 21616/2024 /SS2 | 10/Sep/2024 | 13 | 8 | 10/Sep/2024 | 13 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 13 | 100 | work completed | 13 | 100.00 | 11/Jul/2025 |
| 172 | SFCOANDM/2024-25/095/BUILDING/00039 | Maintenance and Repairs School Building At T.N.P.P. Municipal Higher school, Thiruvathigai at Ward No: 12 in Panruti Municipality. | 21616 /2024/SS2 | 10/Sep/2024 | 7 | 9 | 10/Sep/2024 | 7 | 14/Oct/2024 | 14/Oct/2024 | 270 days | 7 | 100 | Completed | 7 | 100.00 | 12/Jan/2025 |
| 173 | SFCOANDM/2024-25/095/BUILDING/00040 | Maintenance and Repairs School Building At Panchavarnam Nagar, Gandhi Road Municipal Middle school Ward No: 27 in Panruti Municipality. | 21616/2024/SS2: | 10/Sep/2024 | 7 | 10 | 10/Sep/2024 | 7 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 7 | 100 | completed | 7 | 100.00 | 11/Jul/2025 |
| 174 | SFCOANDM/2024-25/095/BUILDING/00041 | Maintenance and Repairs School Building at Municipal Primary School Vizhamangalam Ward No; 02 in Panruti Municipality. | 21616/2024/SS2 | 10/Sep/2024 | 8 | 11 | 10/Sep/2024 | 8 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 8 | 100 | completed | 1.49 | 18.62 | 11/Jul/2025 |
| 175 | SFCOANDM/2024-25/095/BUILDING/00042 | Maintenance and Repairs School Building at Municipal Urudhu Primary School Dhargavandimedu Ward No: 03 in Panruti Municipality. | 21616/ 2024 /SS2 | 10/Sep/2024 | 10 | 12 | 10/Sep/2024 | 10 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 10 | 100 | completed | 10 | 100.00 | 11/Jul/2025 |
| 176 | SFCOANDM/2024-25/095/BUILDING/00043 | Maintenance and Repairs School Building At Municipal Primary School A.Andikuppam Ward No; 02 in Panruti Municipality. | 21616/2024/SS 2 | 10/Sep/2024 | 8 | 13 | 10/Sep/2024 | 8 | 14/Oct/2024 | 14/Oct/2024 | 270 Days | 8 | 100 | Completed | 8 | 100.00 | 11/Jul/2025 |
| 177 | SFCOANDM/2025-26/095/BUILDING/00026 | Construction of Anganwadi building at ward no 09, Railway colony ( Erikkarai ) in Panruti Municipality | 9732/2025/SS2 | 03/Apr/2025 | 15 | 1/2025-26 | 03/Apr/2025 | 15 | 28/Apr/2025 | 28/Apr/2025 | 270 Days | 15 | 100 | Work completed | 14.97 | 0.00 | 23/Jan/2026 |
| 178 | SFCOANDM/2025-26/095/BUILDING/00045 | Maintanance and Repairs Toilet and Maintanance of School Buliding At Municipal Primary school, old Kacheri street ( West side and North side buildings) Thiruvathigai Ward No : 12 in Panruti Municipality. | 9733/2025/SS2 | 25/Jul/2025 | 15 | 18/2025-2026 | 01/Aug/2025 | 15 | 29/Aug/2025 | 29/Aug/2025 | 90 Days | 15 | 100 | Completed | 15 | 100.00 | 27/Nov/2025 |
| 179 | SFCOANDM/2025-26/095/BUILDING/00046 | Maintanance and Repairs Toilet and Maintanance of School Buliding At Municipal Primary school, T.Rasapalayam, .(South side and West side buildings) T.Rasapalayam Ward No : 12 in Panruti Municipality. | 9733 /2025 /SS2 | 25/Jul/2025 | 15 | 19/2025-2026 | 01/Aug/2025 | 15 | 29/Aug/2025 | 29/Aug/2025 | 90 Days | 15 | 100 | Outer Painting work under Progress | 15 | 100.00 | 27/Nov/2025 |
| 180 | SFCOANDM/2025-26/095/BUILDING/00047 | Maintanance and Repairs Toilet and School Buliding At T.N.P.P. Municipal Hr,school,( west side buildings)Thiruvathigai Ward No : 12 in Panruti Municipality. | 9733/2025/ SS2 | 25/Jul/2025 | 11 | 20/2025-2026 | 01/Aug/2025 | 11 | 29/Aug/2025 | 29/Aug/2025 | 90 Days | 11 | 100 | Completed | 11 | 100.00 | 27/Nov/2025 |
| 181 | SFCOANDM/2025-26/095/BUILDING/00048 | Maintanance and Repairs Toilet and School Buliding At Municipal Middle school, Panchavarnam Nagar, Gandhi Road Ward No : 27 in Panruti Municipality. | 9733 /2025 / SS2 | 25/Jul/2025 | 11 | 21/2025-2026 | 01/Aug/2025 | 11 | 29/Aug/2025 | 29/Aug/2025 | 90 Days | 11 | 100 | completed | 11 | 100.00 | 27/Nov/2025 |
| 182 | SFCOANDM/2025-26/095/BUILDING/00049 | Maintanance and Repairs Toilet and Maintanance of School Buliding At Municipal Primary school, Vizhamangalam Ward No : 02 in Panruti Municipality. | 9733 / 2025/ SS2 | 25/Jul/2025 | 15 | 22/2025-2026 | 01/Aug/2025 | 15 | 29/Aug/2025 | 29/Aug/2025 | 90 Days | 15 | 100 | Completed | 15 | 100.00 | 27/Nov/2025 |
| 183 | SFCOANDM/2025-26/095/BUILDING/00050 | Maintanance and Repairs Toilet and School Buliding At Municipal Primary school, A.Andikuppam ( west side buildings) Ward No : 32 in Panruti Municipality. | 9733 / 2025 /SS2 | 25/Jul/2025 | 11 | 23/2025-2026 | 01/Aug/2025 | 11 | 29/Aug/2025 | 29/Aug/2025 | 90 Days | 11 | 100 | Completed | 11 | 100.00 | 27/Nov/2025 |
| Name of the Scheme : SPECIAL FUND FOR IMPROVEMENT OF ROADS | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 184 | SF-ROAD/2025-26/095/ROAD/00032 | Formation of New Road-Earthern to PaverBlock095009S025-SARANARAYANA NAGAR 2ND CROSS STREET , 095011R173-CHETTIPATTARAI COLONY RIGHT SIDE 4TH CROSS , 095024S049-EZHIL NAGAR 3 , 095024S050-EZHIL NAGAR 2 , 095024S051-EZHIL NAGAR 1 , 095032L015-PUTHU NAGAR 5TH CROSS , 095032L018-PUTHU NAGAR 8TH CROSS , 095032L020-PUTHU NAGAR 9TH CROSS , 095032R563-BURIAL GROUND ROAD 1ST STREET SOUTH , 095033R567-BURIAL GROUND , 095033R569-WEST SIDE EARTHERN ROAD CROSS STREET , 095033R571-EAST SIDE EARTHERN ROAD CROS | Minutes of the 8th meeting of the CPS monitoring committee to consider the special fund 02.04.25 | 02/Apr/2025 | 145 | 18484 /2023/DO1 | 07/Apr/2025 | 145 | 16/May/2025 | 16/May/2025 | 90 Days | 145 | 100 | Completed | 275.43 | 94.98 | 14/Aug/2025 |
| Name of the Scheme : SRP | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 185 | SRP/2020-21/095/ROAD/00005 | Providing BT road at ward no.28 Kalathu Medu, Mooppanar nagar and Muthaiya nagar streets | 20557/2018/E3 | 14/Dec/2020 | 450 | 157/2020-21 – 3 | 17/Dec/2020 | 50 | 25/Feb/2021 | 25/Feb/2021 | 270 days | 50 | 100 | Work completed | 45 | 0.00 | 11/Apr/2021 |
| 186 | SRP/2020-21/095/ROAD/00006 | Providing BT Road at ward No.18 Annamalai Layout , Ward. No 1 Burrial Ground road, W.No 27 Thattanchavadi Burrial ground and Rajeshwari nagar connecting road, Ward.No 26 Sakthi Nagar & Sattanathan Street,ward.No.3,4,5 Gandhi Road, Ward.No 3 Vizhamangalam Colony Burial Ground, Ward.No 27 Adhi Pillai street, Bharathamadha Street and ward No 19 Ragavendira Nagar, ward No 15 Muthukumaran Nagar, ward.33 Vallikandan Nagar and ward no.29, Rathinasamy Naga | 20557/2018/E3 | 14/Dec/2020 | 450 | 401/2020-21 – 2 | 17/Dec/2020 | 200 | 25/Feb/2021 | 25/Feb/2021 | 270 days | 200 | 100 | 171.85 | 85.93 | 25/Aug/2021 | |
| 187 | SRP/2020-21/095/ROAD/00007 | Providing BT Road at ward No.21 Police line 3rd street & Cross street, 4th street & Cross street, 5th street & Cross street and police line 6th street, ward No.17 Temple view garden, ward.No 28 Dhanlakshmi Nagar extn (kumaran Nagar), AMS Nagar, Vishvanathan Nagar Barathi Nagar and Sundarambal Nagar | 20557/2018/E3 | 14/Dec/2020 | 450 | 400/2020-21 – 1 | 17/Dec/2020 | 200 | 25/Feb/2021 | 25/Feb/2021 | 270 days | 200 | 100 | Work completed balance work cancelled | 78.7 | 0.00 | 25/Aug/2021 |
| Name of the Scheme : State Disaster Management | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 188 | STATE DISA/2021-22/095/BUILDING/00016 | Providing of Weathering course with pressed tiles at Bus Stand Pay and Use Toilet | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 67/2021-2022 – 16 | 27/Dec/2021 | 1.5 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 1.5 | 100 | 1.5 | 0.00 | 09/Feb/2022 | |
| 189 | STATE DISA/2021-22/095/BUILDING/00017 | Providing Weathering courseat with pressed tiles at Municipal Office Building | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 66/2021-2022 – 15 | 27/Dec/2021 | 5 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 5 | 100 | 5 | 0.00 | 09/Feb/2022 | |
| 190 | STATE DISA/2021-22/095/BUILDING/00052 | Providing Weathering courseat with pressed tiles at Ward no.28, Gandhi Road Municpal School Relief Center. | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 65/2021-2022 – 14 | 27/Dec/2021 | 7.3 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 7.3 | 100 | 6.87 | 94.15 | 09/Feb/2022 | |
| 191 | STATE DISA/2021-22/095/CULVERT/00026 | Reconstruction of culvert to Thiruvalluvar Nagar at Ward no.7 | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 60/2021-2022 – 5 | 27/Dec/2021 | 2 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 2 | 100 | 2 | 0.00 | 09/Feb/2022 | |
| 192 | STATE DISA/2021-22/095/CULVERT/00027 | Reconstruction of culvert to Melapalayam pattai at Ward no.16 | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 59/2021-2022 – 4 | 27/Dec/2021 | 1 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 1 | 100 | 1 | 0.00 | 09/Feb/2022 | |
| 193 | STATE DISA/2021-22/095/CULVERT/00028 | Reconstruction of culvert at Ward no.11 A.Mani Nagar | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 57/2021-2020 – 2 | 27/Dec/2021 | 3 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 3 | 100 | 3 | 0.00 | 09/Feb/2022 | |
| 194 | STATE DISA/2021-22/095/CULVERT/00053 | Reconstruction of culvert Kamaraj Nagar at Ward no.12 in Panruti Municipality | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 58/2021-2021` – 3 | 27/Dec/2021 | 0.7 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 0.7 | 100 | 0.7 | 0.00 | 09/Feb/2022 | |
| 195 | STATE DISA/2021-22/095/ROAD/00018 | Restoration of B.T.Road to VSP nagar main Street and Cross street (095016R279) | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 64/2021-2022 – 13 | 27/Dec/2021 | 6.4 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 6.4 | 100 | 6.4 | 0.00 | 09/Feb/2022 | |
| 196 | STATE DISA/2021-22/095/ROAD/00019 | Restoration of C.C.Road to VOC Nagar main Street and Cross street (095003R057) and Restoration of C.C.Road to Avayampalayam and Avaiputhu main Street and Cross street (095020R345) | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 50/2021-2022 – 12 | 27/Dec/2021 | 29 | 13/Jan/2022 | 13/Jan/2022 | 270 days | 29 | 100 | 29 | 0.00 | 14/Mar/2022 | |
| 197 | STATE DISA/2021-22/095/ROAD/00020 | Restoration of C.C.Road to Larapsa Dharga Street (095006S011) , Restoration of C.C.Road to Thiruvalluvar nagar main Street and Cross street (095007R096), Restoration of C.C.Road to Kuchipalayam main Street , Cross street and Kamabar street (095022R368) and Restoration of C.C.Road to Ambethgar Nagar main Street and Cross street (095006S015) | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 48/2021-2022 – 11 | 27/Dec/2021 | 35.7 | 13/Jan/2022 | 13/Jan/2022 | 270 days | 35.7 | 100 | 32.22 | 0.00 | 14/Mar/2022 | |
| 198 | STATE DISA/2021-22/095/ROAD/00021 | Restoration of C.C.Road to Bharathamadha street(095025R419), Restoration of C.C.Road to Dhanapal Street (095004R069), Restoration of C.C.Road to Police line 3rd cross Street (095019R339) and Restoration of C.C.Road to Panankattau Street (095004R071) | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 49/2021-2022 – 10 | 27/Dec/2021 | 31.5 | 13/Jan/2022 | 13/Jan/2022 | 270 days | 31.5 | 100 | 31.5 | 99.99 | 14/Mar/2022 | |
| 199 | STATE DISA/2021-22/095/ROAD/00022 | Restoration to BT surface to Chettipattarai Colony main street (unicode.095011R167) at ward.No.11 | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 63/2021-2022 – 9 | 27/Dec/2021 | 4.8 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 4.8 | 100 | 4.8 | 0.00 | 09/Feb/2022 | |
| 200 | STATE DISA/2021-22/095/ROAD/00023 | Restoration to BT surface to Raman Lakshmanan Nagar 1st Street (unicode.095001R019) ,Raman Lakshmanan Nagar 2nd Street (unicode.095001R020), Raman Lakshmanan Nagar 1st Cross Street (unicode.095001R018) and Raman Lakshmanan Nagar 2nd Cross Street (unicode.095001R017)at ward.No.1 | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 62/2021-2022 – 8 | 27/Dec/2021 | 6.4 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 6.4 | 100 | 6.4 | 0.00 | 09/Feb/2022 | |
| 201 | STATE DISA/2021-22/095/ROAD/00024 | Restoration to BT surface to from Link road to Palur Road (unicode.095016R249) at ward.16 | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 61/2021-2022 – 7 | 27/Dec/2021 | 7 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 7 | 100 | 7 | 0.00 | 09/Feb/2022 | |
| 202 | STATE DISA/2021-22/095/ROAD/00025 | Restoration to BT surface at Ward. No.28 & 29 (Link Road) Ayyanar Koil Pattai (from Sathyamurthy street to Diversion Road) (unicode.095027R496) at ward.No.27 | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 51/2021-2022 – 6 | 27/Dec/2021 | 30 | 13/Jan/2022 | 13/Jan/2022 | 270 days | 30 | 100 | 23.73 | 0.00 | 14/Mar/2022 | |
| 203 | STATE DISA/2021-22/095/WSIS/00029 | Replacement of damaged water supply pipe line ward.28 Panchavaranam nagar and 33 wards, 63mm UPVC 500meter, 80mm UPVC dia 750meter and 100mm UPVC dia 200 meter. | 31442/2021/E3 | 15/Dec/2021 | 180.3 | 56/2021-2022 – 1 | 27/Dec/2021 | 9 | 10/Jan/2022 | 10/Jan/2022 | 270 days | 7.9 | 0 | Work cancelled | 0 | 0.00 | 09/Feb/2022 |
| Name of the Scheme : State Urban Infrastructure Development Fund | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 204 | STATE URBA/2022-23/095/SL/00126 | Conversion of existing Street Light into Energy Efficient LED Light – 2106 Nos | Roc No.30522/2022/WB | 04/Nov/2022 | 239.74 | 547 | 07/Nov/2022 | 239.74 | 20/Feb/2023 | 20/Feb/2023 | 540 Days | 234.24 | 100 | Work completed | 213.21 | 88.93 | 13/Aug/2024 |
| Name of the Scheme : TURIP | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 205 | TURIP/2019-20/095/ROAD/00057 | Widening of Paver Block Surface to Link Road (from Kumbakonam Road to Cuddalore Road) and Indhira Gandhi Salai | 17349/2019/E3 | 16/Oct/2019 | 200 | 25039/2019/DO1 – 1 | 23/Oct/2019 | 200 | 31/Dec/2019 | 31/Dec/2019 | 270 days | 200 | 100 | 199 | 99.50 | 30/Sep/2021 | |
| 206 | TURIP/2020-21/095/ROAD/00056 | Providing Renewal BT Surface to W.No17 Veeranam road to from link road to Eluppai thoppu, W.No17 Nethaji nagar from Link road, W.No.10 Jaya Priya nagar, W.No15 MGR Nagar, W.No.21 Kamaraj nagar (EB Colony), W.No.27 Seelakara street, W.No.29 Sathyamoorthy street west side1 & II cross streets, W.No 30.VOC Street to Gedilam Head works, W.No 32 Irulankuppam south street, W.No.28Thidir Kuppam, W.No16 Burial ground road from Veerataneswarar koil street up to Melapalayam Burial Ground road, W.2 Vi | 9052/2020/E3 | 17/Jul/2020 | 200 | 25039/2019/DO1 | 22/Jul/2020 | 200 | 14/Oct/2020 | 14/Oct/2020 | 270 days | 200 | 0 | 190 | 0.00 | 12/Apr/2021 | |
| 207 | TURIP/2024-25/095/ROAD/00009 | Relaying of Road-Bituminous Road095007R102-RASI NAGAR 4TH CROSS STREET , 095021R355-EAST CROSS STREET-3 , 095021R364-CROSS STREET-3 , 095021R354-EAST CROSS STREET-4 , 095021R357-EAST CROSS STREET-1 , 095021R359-CROSS STREET-2 , 095021R365-CROSS STREET-1(R35) , 095021R358-CROSS STREET-3 , 095021R356-WEST CROSS STREET-1 , 095023R376-SOUTH CROSS STREET , 095027R456-THAYARAMMAL NAGAR MAIN STREET , 095027R493-CROSS STREET 1 , 095027R457-EAST CROSS STREET 5 , 095028R502-VOC STREET FROM LINK ROAD TO RI | 2459/2024/SS1 | 20/Jan/2025 | 100 | 18484/2023/DO1 | 21/Jan/2025 | 100 | 14/Mar/2025 | 14/Mar/2025 | 90 Days | 100 | 0 | 95.36 | 0.00 | 12/Jun/2025 | |
| 208 | TURIP/2024-25/095/ROAD/00010 | Relaying of Road-Bituminous Road095006R088-ERIKARAI AMIR JOHAN NAGAR , 095007R105-A PA SIVARAMAN NAGAR , 095007R103-RASI NAGAR 3RD CROSS STREET , 095007R106-RASI NAGAR 2ND CROSS STREET , 095007R110-A PA SIVARAMAN NAGAR 6TH CROSS STREET , 095007R104-RASI NAGAR 1ST CROSS STREET , 095013R213-ASHOK NAGAR MAIN STREET , 095013R204-THIRUVARANGAM NAGAR CROSS ROAD , 095018R315-ANNAI INDRA GANDHI SALAI(R35) , 095018R321-POLICE LINE 5TH STREET , | 2459 /2024/SS1 | 20/Jan/2025 | 100 | 18484/2023/DO1 | 21/Jan/2025 | 100 | 14/Mar/2025 | 14/Mar/2025 | 270 Days | 100 | 100 | Work Completed | 95.36 | 95.36 | 09/Dec/2025 |
| 209 | TURIP/2024-25/095/ROAD/00014 | Relaying of Road-Bituminous Road095014R218-WEST CROSS STREET-3 , 095014R217-WEST CROSS STREET-1 , 095014R220-MGR NAGAR , 095014R214-EAST CROSS STREET-1 , 095014R228-KARAVAKARA STREET , 095016R252-2ND CROSS STREET(VARATHARAJAPURAM) , 095016R279-V.S PANDURANAGAN NAGAR 1ST STREET , 095031R520-ANNAMALAI LAYOUT , 095014R216-WEST CROSS STREET-1 , 095016R251-1ST CROSS STREET(VARATHARAJAPURAM) , 095016R280-V.S PANDURANAGAN NAGAR 4TH STREET , 095016R281-V.S PANDURANAGAN NAGAR 2ND STREET , 095016R250-VARA | 2459/2024/SS1_1 | 01/Feb/2024 | 100 | 331/2024-25 | 02/Feb/2024 | 100 | 29/Feb/2024 | 29/Feb/2024 | 270 days | 100 | 100 | work completed | 81.07 | 0.00 | 29/May/2024 |
| 210 | TURIP/2024-25/095/ROAD/00015 | Relaying of Road-Bituminous Road095016R261-OSURAN AMMAN KOIL STREET , 095016R249-FROM LINK ROAD TO PALUR ROAD , 095016R278-V.S PANDURANAGAN NAGAR , 095016R265-NEHRU NAGAR MAIN STREET , 095016R276-BURIAL GROUND ROAD FROM PANDURANGAN , 095026R423-SARASWATHI NAGAR , 095026R431-CROSS STREET-1 , 095026R425-CROSS STREET-1 , 095026R432-CROSS STREET-2 , 095026R426-SARASWATHI NAGAR , 095026R433-CROSS STREET-3 , 095032R544-PUTHU NAGAR UPTO VEERANAM ROAD , 095011R167-CHETTIPATTARAI COLONY MAIN ROAD , | 2459/2024/SS1_2 | 01/Feb/2024 | 86 | 332/2024-25 | 02/Feb/2024 | 86 | 29/Feb/2024 | 29/Feb/2024 | 270 days | 86 | 100 | 85.99 | 99.98 | 29/May/2024 | |
| 211 | TURIP/2024-25/095/ROAD/00016 | Relaying of Road-Bituminous Road095002R041-VIZHAMANGALAM PATTAI ROAD , 095017R297-POLICE LINE 6TH STREET , 095024R387-RAJESWARI NAGAR MAIN ROAD , 095002R030-MANJINI NAGAR 1ST CROSS , 095002R031-MANJINI NAGAR-1 , 095002R032-MANJINI NAGAR-2 , 095023R377-NORTH CROSS STREET 1 , 095033R566-BURIAL GROUND , 095023R382-SATTANATHAN STREET , | 2459/2024/SS_3 | 01/Feb/2024 | 79 | 333/2024-25 | 02/Feb/2024 | 79 | 29/Feb/2024 | 29/Feb/2024 | 270 days | 79 | 100 | 66 | 83.54 | 29/May/2024 | |
| 212 | TURIP/2025-26/095/ROAD/00011 | Relaying of Road-Cement Concrete Road095006S011-LARAPSHA DARGA , 095006S012-AMBETHKAR NAGAR 2ND CROSS STREET , 095006L001-AMBETHKAR NAGAR 1ST CROSS STREET , 095006S013-AMBETHKAR NAGAR 3RD CROSS STREET , 095006S014-AMBETHKAR NAGAR 4TH CROSS STREET , 095006S015-AMBETHKAR NAGAR 5TH CROSS STREET , 095006R083-PTS MANI NAGAR 5TH STREET , 095006R084-PTS MANI NAGAR 1ST STREET , 095006R085-PTS MANI NAGAR 1ST STREET , 095006R086-PTS MANI NAGAR 3RD STREET , 095006R087-PTS MANI NAGAR 4TH STREET , 095006R089 | 396/2026/SS1- 7 | 06/Jan/2026 | 151 | 1042/2025-26 | 07/Jan/2026 | 151 | 06/Feb/2026 | 06/Feb/2026 | 120 Days | 151 | 90 | Out of 4.026Km length , 3.948Km concrete laying work completed.Balance 0.078Km concrete laying work in | 0 | 0.00 | 06/Jun/2026 |
| 213 | TURIP/2025-26/095/ROAD/00012 | Relaying of Road-Paver Block Road095030R519-LINK ROAD (FROM KUMBAKONAM ROAD TO CUDDALORE ROAD) , 095018R315-ANNAI INDRA GANDHI SALAI(R35) , 095018R314-ANNAI INDIRA GANDHI SALAI , | 396/2026/SS1-7 | 06/Jan/2026 | 185 | 1043/2025-26 | 07/Jan/2026 | 185 | 06/Feb/2026 | 06/Feb/2026 | 120 Days | 185 | 63 | Out Of 1.730Km 1.330Km Relaying Of Paver Block Work Completed Balance 0.400 Km Relaying Work Progress | 0 | 0.00 | 06/Jun/2026 |
| 214 | TURIP/2025-26/095/ROAD/00013 | Relaying of Road-Bituminous Road095027R496-LINK ROAD (FROM DIVERSION ROAD TO , | 396/2026/SS1 -7 | 06/Jan/2026 | 70.5 | 151A/2025-26 | 06/Jan/2026 | 70.5 | 06/Feb/2026 | 06/Feb/2026 | 120 Days | 70.5 | 100 | completed | 0 | 0.00 | 06/Jun/2026 |
| 215 | TURIP/2025-26/095/ROAD/00022 | Relaying of Road-Cement Concrete Road095032R543-PUTHU NAGAR UPTO BT ROAD , 095032L011-PUTHU NAGAR 1ST CROSS , 095032L012-PUTHU NAGAR 2ND CROSS , 095032L013-PUTHU NAGAR 3RD CROSS , 095032L014-PUTHU NAGAR 4TH CROSS , 095032L016-PUTHU NAGAR 6TH CROSS , 095032L017-PUTHU NAGAR 7TH CROSS , 095032L019-PUTHU NAGAR 9TH CROSS , 095032L021-PUTHU NAGAR 10TH CROSS , 095032L022-PUTHU NAGAR 11TH CROSS , 095032L023-PUTHU NAGAR 12TH CROSS , 095032L024-PUTHU NAGAR 13TH CROSS , 095032L025-PUTHU NAGAR 14TH CROSS , | 9730-1/2025/SS1 | 02/Apr/2025 | 83 | 552-1/2025/A1 | 04/Apr/2025 | 83 | 16/May/2025 | 16/May/2025 | 90 Days | 83 | 100 | completed | 83 | 100.00 | 14/Aug/2025 |
| 216 | TURIP/2025-26/095/ROAD/00023 | Relaying of Road-Cement Concrete Road095033R578-CROSS STREET 5 , 095033R579-CROSS STREET 4 , 095033R581-CROSS STREET 3 , 095033R565-T.RASAPALAYAM MAIN STREET , 095033R588-EAST PERUMAL KOIL THIDIRKUPPAM , 095033R574-T.RASAPALAYAM COLONY MAIN STREET – 2 , 095033R575-CROSS STREET 7 , 095033R576-KOIL CROSS STREET , 095033R577-CROSS STREET 6 , 095011R166-CHETTIPATTARAI COLONY MAIN ROAD , 095011R171-CHETTIPAPATARAI COLONY 1ST CROSS IN RIGHT SIDE , 095011R172-CHETTIPATTARAI COLONY RIGHT SIDE 4TH CROSS | 9730-2/2025/SS1 | 02/Apr/2025 | 99.3 | 552-2/2025/A1 | 04/Apr/2025 | 99.3 | 16/May/2025 | 16/May/2025 | 90 Days | 99.3 | 100 | Completed | 94.28 | 94.95 | 14/Aug/2025 |
| 217 | TURIP/2025-26/095/ROAD/00024 | Relaying of Road-Cement Concrete Road095010R143-4TH CROSS STREET , 095010R144-3RD CROSS STREET , 095010R145-2ND CROSS STREET , 095010R147-5TH CROSS STREET , 095010R148-PAKKIRIPALAYAM COLONY MAIN ROAD , 095010R150-2ND CROSS STREET , 095010R151-1ST CROSS STREET , 095010R152-3RDCROSS STREET , 095017R300-VIEERATALINGAM NAGAR-2 , 095017R302-THANDUPALAYAM 1ST CROSS STREET , 095017R303-VIEERATALINGAM NAGAR-1 , 095017R307-NETHAJI NAGAR 3RD CROSS STREET , 095017R308-NETHAJI NAGAR 1ST CROSS STREET , 095 | 9730-3/2025/SS1 | 02/Apr/2025 | 97 | 552-3/2025/A1 | 04/Apr/2025 | 97 | 16/May/2025 | 16/May/2025 | 90 Days | 97 | 100 | Completed | 91.95 | 94.79 | 14/Aug/2025 |
| 218 | TURIP/2025-26/095/ROAD/00025 | Relaying of Road-Cement Concrete Road095019R328-KAMARAJ NAGAR(NANDHA GOPAL) , 095019R329-2ND CROSS STREET , 095019R330-POLICE LINE 1ST STREET , 095019R331-KAMARAJ NAGAR EB COLONY 2ND CROSS , 095019S038-AMBEDKAR NAGAR , 095019R333-KAMARAJ NAGAR MAIN STREET , 095019R335-POLICE LINE 1ST STREET , 095019R336-POLICE LINE 2ND CROSS STREET , 095019R338-KAMARAJ NAGAR1ST CROSS STREET MLA , 095019R341-POLICE LINE 1ST STREET , 095019R322-KAMARAJ NAGAR , 095019R337-POLICE LINE 3RD STREET , 095018S035-INDIRA | 9730-4/2025/SS1 | 02/Apr/2025 | 82 | 552-4/2025/A1 | 04/Apr/2025 | 82 | 16/May/2025 | 16/May/2025 | 90 Days | 82 | 100 | Completed | 77.89 | 94.99 | 14/Aug/2025 |
| 219 | TURIP/2025-26/095/ROAD/00027 | Relaying of Road-Bituminous Road095001R009-KANISA PAKKAM ROAD , 095002R039-V.ANDIKUPPAM MAIN ROAD , 095002R029-VIZHAMANGALAM BURIAL GROUND ROAD , 095006R082-PTS MANI NAGAR MAIN STREET , 095006R088-ERIKARAI AMIR JOHAN NAGAR , 095009R129-PTS MANI NAGAR MAIN STREET , 095009R128-PTS MANI NAGAR 3RD STREET , 095009R130-PTS MANI NAGAR 2ND STREET , 095009R134-RAILWAY COLONY MAIN STREET-1 , 095009R132-SARANARAYANA NAGAR , 095010R161-ASHOK NAGAR SOUTH 1ST STREET , 095010R142-HOUSING BOARD MIDDLE STREET , | 9730-5/2025/SS1 | 02/Apr/2025 | 190 | 18484-1/2023/DO1 | 07/Apr/2025 | 190 | 16/May/2025 | 16/May/2025 | 90 Days | 190 | 100 | Completed | 190 | 100.00 | 14/Aug/2025 |
| 220 | TURIP/2025-26/095/ROAD/00028 | Relaying of Road-Bituminous Road095015R248-BURIAL GROUND ROAD , 095015R246-2ND CROSS (CHAKKARAPANI NAGAR ) , 095016R258-MELAPALAYAM MAIN STREET , 095016R260-MELAPALAYAM PATTAI UPTO VSP NAGAR , 095024R403-L.PILLAIYAR KOIL STREET , 095024R393-CROSS STREET 2 , 095024R398-CROSS STREET 4 , 095026R443-WEST CROSS STREET-1 , 095026R446-WEST CROSS STREET-5 , 095026R445-CROSS STREET-2 , 095026R434-VENGATTA NAGAR , 095026R448-WEST CROSS STREET , 095026R450-MUTHIAH NAGAR MAIN STREET , 095026R447-WEST CROSS | 9730-6/2025/SS1 | 02/Apr/2025 | 181 | 18484-2/2023/DO1 | 07/Apr/2025 | 181 | 16/May/2025 | 16/May/2025 | 90 Days | 181 | 100 | Completed | 181 | 100.00 | 14/Aug/2025 |
| 221 | TURIP/2025-26/095/ROAD/00029 | Relaying of Road-Bituminous Road095027R461-EAST CROSS STREET 5 , 095027R458-WEST CROSS STREET 2 , 095027R462-CROSS STREET 4 , 095027R465-CROSS STREET 1 (DEVAGI NAGAR) , 095027R466-DHANALAKSHMI NAGAR MAIN STREET , 095027R493-CROSS STREET 1 , 095027R457-EAST CROSS STREET 5 , 095028R501-SATHIYAMOORTHY MAIN STREET FROM BYEPASSVOC STREET FROM LINK ROAD TO RIVER , 095028R502-VOC STREET FROM LINK ROAD TO RIVER , 095029R509-WEST 2ND CROSS STREET , 095029R507-DEVARAJ NAGAR MAIN STREET , 095029R510-WEST 3 | 9730-7/2025/SS1 | 02/Apr/2025 | 167 | 18484-3/2023/DO1 | 07/Apr/2025 | 167 | 16/May/2025 | 16/May/2025 | 90 Days | 167 | 100 | completed | 167 | 100.00 | 14/Aug/2025 |
| 222 | TURIP/2025-26/095/ROAD/00030 | Relaying of Road-Bituminous Road095030R519-LINK ROAD (FROM KUMBAKONAM ROAD TO CUDDALORE ROAD) , 095033R583-CROSS STREET 1 , 095033R590-JAYAGAS OPP ROAD , 095033R584-JAYAGAS BACK SIDE BURIAL GROUND , | 9730-8/2025/SS1 | 02/Apr/2025 | 169 | 18484-4/2023/DO1 | 07/Apr/2025 | 169 | 16/May/2025 | 16/May/2025 | 90 Days | 169 | 100 | completed | 167 | 98.82 | 14/Aug/2025 |
| 223 | TURIP/2025-26/095/ROAD/00043 | Relaying of Road-Cement Concrete Road095004R067-OLD MARKET ROAD , 095005S010-JAWAHAR LANE – 1 , 095007R096-THIRUVALLUVAR NAGAR 2ND CROSS STREET , 095007R097-THIRUVALLUVAR NAGAR 1ST CROSS STREET , 095012R184-GOKULA STRET RIGHT , 095012R180-OIL MILL TO MOTTALINGAM STREET , 095013R195-VALKARAR STREET CROSS ST 2 , 095014R234-EDAPALAYAM 3RD CROSS STREET , 095014S029-2ND CROSS IN EDAPALAYAM IN 2ND , | 9730/2025/SS1 | 30/May/2025 | 83 | 96/2025-26 | 02/Jun/2025 | 83 | 22/Jul/2025 | 22/Jul/2025 | 90 Days | 83 | 100 | Completed | 77.52 | 93.40 | 20/Oct/2025 |
| 224 | TURIP/2025-26/095/ROAD/00044 | Relaying of Road-Cement Concrete Road095020R343-AVAYAMPALAYAM CROSS 1 , 095020R342-AVAYAMPALAYAM CROSS 2 , 095021R360-THIRU NAGAR MAIN STREET , 095023R374-PADAIVEETAMMAN KOIL STREET , 095023R380-THIRUKAMU STREET , 095028S062-VOC CROSS STREET 1 , 095028R500-MOHAMATHIYAR STREET , 095028S064-MOHAMATHIYAR LANE 1 , | 9730 /2025/SS1 | 30/May/2025 | 60.5 | 95/2025-26 | 02/Jun/2025 | 60.5 | 22/Jul/2025 | 22/Jul/2025 | 90 Days | 60.5 | 100 | Completed | 57.37 | 94.82 | 20/Oct/2025 |
| Name of the Scheme : WS Internal Plumbing | |||||||||||||||||
| Name of the Muncipality : PANRUTI | |||||||||||||||||
| 225 | WS INTERNA/2018-19/095/WS/00008 | Providing IP for Water Supply House Service Connection in Panruti Municipality | 13277/2018/WS1 | 19/Jun/2018 | 280 | 747A/2018-2019 – 1 | 11/Jan/2019 | 171.41 | 16/Sep/2019 | 16/Sep/2019 | 270 days | 171.41 | 30 | 1338 nos of WS HSC connection provided, This scheme is converted in to Amrut 2.0 | 36.18 | 0.00 | 16/Mar/2021 |
2. SWM
3. UGSS 2017-18 (Revolving fund of UIDSSMT)
4. Capital Grant Fund and O & M Fund
5. Solid Waste Management (SWM)
6. Solid Waste Management (SWM)
7. TURIP
8. IUDM
9. Solid Waste Management (SWM)
10.Revolving fund of UIDSSMT