Status as on 16/06/2026
| S.No | Project ID | Name of Work | AS Details | TS Details | Work Order Date | Agreement Date | Agreement Period | Agreement Value | Physical Progress in % | Stage of the Work | Payment Made so far |
Financial Progress in % | Target Date As Per Agreement | Probable Date of completion | Review Remarks | |||||
| AS Number | AS Date | AS Amount | TS Number | TS Date | TS Amount | |||||||||||||||
| Region Status | ||||||||||||||||||||
| Name of the Region : THANJAVUR | ||||||||||||||||||||
| Name of the Scheme : 15th CFC UnTied Grant | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 1 | 15THCFCUNT/2025-26/098/OTHERS/00027 | Providing Paver block Arrangement at Dargah Market Lane,Alangara Vasal,New Bazzar Lane,Dharga Kulam South Bank,Dharga Kulam Keelkarai,Dharga Kulam North Bank,Dharga Kulam melkarai and Thalaimattu Street in Nagore, Nagapattinam Municipality. | 34768/2025/EA-2 | 29/Sep/2025 | 125 | 18484/2023/DO1 | 03/Oct/2025 | 125 | 10/Oct/2025 | 10/Oct/2025 | 45 Days | 103.14 | 45 | Paver block laying 380 mtr completed out of 850 m. ( 4 Road Completed and 4 Road work under progress) | 0 | 0.00 | 24/Nov/2025 | |||
| Name of the Scheme : 15thCFC-Health | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 2 | 15THCFCUPC/2023-24/098/BUILDING/00055 | Construction of Urban Health Sub Centre Nagoor Pazhaiya Nambiyar at Nagapattinam Municipality. | 25875/2023/EA-2 | 16/Aug/2023 | 60 | 40 | 25/Oct/2023 | 30 | 20/Nov/2023 | 20/Nov/2023 | 1 Year | 24.88 | 91 | Tiles laying work is in progress | 14.32 | 0.00 | 20/Nov/2024 | |||
| 3 | 15THCFCUPC/2023-24/098/BUILDING/00013 | Construction of Additional Buildings for Government Hospital in GH Nagore. | 19731/2023/EA-2 | 19/Jan/2024 | 500 | 18484/2023 | 29/Jan/2024 | 500 | 22/Feb/2024 | 22/Feb/2024 | 540 Days | 493.53 | 68 | Ground Floor completed & First floor roof steel fabrication work is in progress. | 207.99 | 0.00 | 15/Aug/2025 | |||
| 4 | 15THCFCUPC/2023-24/098/BUILDING/00025 | Construction of New Urban Primary Health Centre at Marunthukothalam Road in Nagapattinam Municipality. | 22441/2023/EA 2 | 19/Nov/2024 | 120 | 18484/2023/DO1 | 28/Nov/2024 | 120 | 20/Dec/2024 | 20/Dec/2024 | 12 Months | 118.81 | 68 | First floor lintel Steel fabrication work is progress. | 143.19 | 0.00 | 20/Dec/2025 | |||
| Name of the Scheme : AMRUT 2.O | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 5 | AMRUT 2.O/2021-22/098/WSIS/00060 | Improvement of Water Supply distribution system in Nagapattinam Municipality | G.O. (Ms).No. 125 | 09/Sep/2022 | 6821 | 521/2021-22 | 12/Oct/2022 | 6821 | 16/Feb/2023 | 16/Feb/2023 | 927 Days | 6518.25 | 94 | FEEDER MAIN -0.765Km Pipe laying work is in progress in Nagapattinam, Nagore Highway D’ SYSTEM (HDPE & DI) Km – 4.34 Km Pipe laying work (As Per Site Condition) PUMPING MAIN from Headworks to Nagapattinam OHTs- 0.184 Km Pipe laying work (Line Extended to New TWAD Sump) HSC -15227 Nos HSC Work is in progress. (2675 HSC survey completed out of 24781 HSC) | 4862.82 | 0.00 | 31/Aug/2025 | |||
| 6 | AMRUT 2.0/2023-24/098/WS/00028 | Combined Water Supply Scheme to Nagapattinam Municipality | 9th SLTC meeting dated 5.9.2023 | 05/Sep/2023 | 24596 | 01 | 30/Oct/2023 | 24596 | 30/Jan/2024 | 30/Jan/2024 | 2 Year | 21882.65 | 97 | 3 Sumps completed, and other 1 sump Roof slap reinforcement work under progress, Pumping main out 7.585 Km, 6.035 Km completed further work under progress. | 8267.2 | 0.00 | 30/Jan/2026 | |||
| Name of the Scheme : General Fund | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 7 | GENERAL/2025-26/098/WS/00015 | Providing Manhole Raising in Kallukara street and ward no 26 in Nagapattinam Municipality | 426/2026/MA1 | 17/Feb/2026 | 9 | 35/AEE | 17/Feb/2026 | 4 | 13/Mar/2026 | 13/Mar/2026 | 2 Months | 3.29 | 57 | 4 nos works completed out of 6 nos of works. | 0 | 0.00 | 13/May/2026 | |||
| 8 | GENERAL/2025-26/098/SANITATION/00017 | Providing Toilet maintenance at ward no: 4, 11 and 33 in Nagapattinam Municipality. | 426/2026/MA1 | 17/Feb/2026 | 9 | 37/AEE | 17/Feb/2026 | 4 | 13/Mar/2026 | 13/Mar/2026 | 1 Months | 3.89 | 4 | Dismantling for flooring work is in progress. | 0 | 0.00 | 13/Apr/2026 | |||
| 9 | GENERAL/2025-26/098/OTHERS/00016 | Manufacturing, Supply & Fixing of retro-Reflective Road Name Sign board at V.I.P Nagar in nagore in Nagapattinam Municipality. | 426/2026/MA1 | 17/Feb/2026 | 9 | 36/AEE | 17/Feb/2026 | 0.5 | 13/Mar/2026 | 13/Mar/2026 | 1 Months | 0.47 | 5 | Earth work is in progress | 0 | 0.00 | 13/Apr/2026 | |||
| 10 | GENERAL/2025-26/098/CULVERT/00014 | Providing Pipe Culvert at Vannangulam (Ward no. 7) at Nagore in Nagapattinam | 426/2026/MA1 | 17/Feb/2026 | 9 | 38/AEE | 17/Feb/2026 | 0.5 | 13/Mar/2026 | 13/Mar/2026 | 1 Months | 0.49 | 6 | Site cleaning work is in progress. | 0 | 0.00 | 13/Apr/2026 | |||
| Name of the Scheme : Grants for Tourism Towns – Fixed Grant | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 11 | 6SFCGR/2024-25/098/BUILDING/00010 | Construction of Outdoor Stadium at Ward No: 30 Pazha Street in Nagapattinam Municipality. | 12709/2024/SS2 | 25/Feb/2026 | 100 | 31/AEE | 26/Feb/2026 | 25 | 13/Mar/2026 | 13/Mar/2026 | 6 Months | 20.12 | 3 | Site cleaning work is in progress. | 0 | 0.00 | 13/Sep/2026 | |||
| Name of the Scheme : Kalaignar Nagarpura Mempatu Thittam | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 12 | KNMT/2024-25/098/TW013/00021 | Construction of New Bus Stand @ IN Sellur Village at SF No: 160/2B2A,161/1B1A,160/5,159/6,159/2B,158/4,158/2B, in Nagapattinam Municipality. | G.O. (4D) No.20 | 19/Jul/2024 | 3040 | CE, Pro No.18484/2023/DO1 | 24/Jul/2024 | 3040 | 13/Sep/2024 | 13/Sep/2024 | 1 Year | 2531.48 | 53 | 1. South – West Portion : Roof Concrete Work Completed, 2. South – East Portion: Roof Concrete completed,3.North east:Roof slab Shuttering Work Started ,4.South east: Brickwork upto roof level work is in Progress. | 1733.86 | 0.00 | 13/Sep/2025 | |||
| Name of the Scheme : Namakku Naame Thittam | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 13 | NNT/2024-25/098/OTHERS/00016 | Providing and Installation of CCTV Camera arrangements in 1.Railway junction road, 2. Nethaji road, 3.Cooper street, 4.Pinpandaga street, 5.Puthu manai street, 6.Aaliya maraikayar street, 7. Kamaliya street, 8.Kamailiya street sandhu, 9.Yadhava north sandhu, 10.Pazha street, 11.Ya hussan palli street, 12.Veera pathra sami koil street, 13.Naanaiyakara street in Nagapattinam Municipality. | 1623/2022/E1 | 03/Mar/2025 | 33 | 01 | 03/Mar/2025 | 12 | 16/Apr/2025 | 16/Apr/2025 | 6 Months | 10.06 | 46 | Laying of Cable work completed and other works under progress. | 0 | 0.00 | 16/Oct/2025 | |||
| Name of the Scheme : O&M DEFICIT GRANT FUND | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 14 | CGF-OMDGF/2025-26/098/BUILDING/00022 | Construction of Community Hall Building at Yusuf Nainar street in Nagapattinam Municipality. | DMA, Chennai Proc. 9999/2025/SS2 | 30/May/2025 | 49.5 | 94/2025-26 | 02/Jun/2025 | 49.5 | 27/Jun/2025 | 27/Jun/2025 | 12 Months | 41.38 | 40 | Ground floor roof centering work is progress | 14.1 | 0.00 | 27/Jun/2026 | |||
| Name of the Scheme : SBM 2.0 | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 15 | SBM 2.0/2024-25/098/SWM/00001 | Providing composting solution for wet waste of capacity 10 TPD pre composter within built shredder required bio culture and 1000 pads/masks per capacity Electrical Incinerator. | 6450/2022/SBM1 | 25/Sep/2024 | 147.6 | 18484/2023/DO1 | 25/Oct/2024 | 147.6 | 23/Dec/2024 | 23/Dec/2024 | 1 Year | 128.24 | 82 | Civil work completed bin to be install work is in progress. | 44 | 0.00 | 23/Dec/2025 | |||
| 16 | SBM 2.0/2025-26/098/BUILDING/00006 | Construction of New Community Toilet at Nadaraja Pillai Street (Ward No.33) in Nagapattinam Municipality. | 288/2025/SBM2 | 11/Nov/2025 | 19.3 | 24/2025-26 AEE | 03/Dec/2025 | 9.65 | 19/Dec/2025 | 19/Dec/2025 | 6 Months | 8.05 | 30 | PCC for flooring work is progress | 0 | 0.00 | 19/Jun/2026 | |||
| Name of the Scheme : SFC (Incentive Fund) | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 17 | SFC INCENT/2024-25/098/BUILDING/00005 | Construction of Public Stage and compound wall at Avuri Thidal in Nagapattinam Municipality | 23045/2023/SS2 | 27/Nov/2024 | 66 | 1325/2024/E2 | 29/Nov/2024 | 66 | 29/Jan/2025 | 29/Jan/2025 | 1 Year | 53.61 | 68 | Inner Wall plastering work is progress (Expected date of Completion : 30.06.2026) | 32.6 | 0.00 | 29/Jan/2026 | |||
| Name of the Scheme : TURIP | ||||||||||||||||||||
| Name of the Muncipality : NAGAPATTINAM | ||||||||||||||||||||
| 18 | TURIP/2025-26/098/ROAD/00004 | Relaying of Road-Bituminous Road098024R341-MARAVADI STREET , 098024R339-ARIYANATTU STREET , 098023R322-SEMMARAKADAI SOUTH LANE , 098027S062-THANDAVARAIYAN PILLAI STREET , 098032S070-MALESWARAN NORTH VEETHI , 098025R348-VENGAIYAKADAI STREET , 098025R350-NOOL KADAI STREET , 098034R457-1ST LINE BEACH ROAD , 098013R158-BANGALOW CLUB ROAD , 098033R447-VEERAPATHIRA SAMY KOIL STREET , 098032R428-NADUVAR SOUTH MADAVILAGAM , 098032R436-NADUVAR SANNATHI , 098031R423-PERUMAL SOUTH MADAVILAGAM , 098031R419- | 401/2026/SS1-11 | 06/Jan/2026 | 635 | 18484/2023/DO1 – PKG 3 | 07/Jan/2026 | 179 | 04/Feb/2026 | 04/Feb/2026 | 4 Months | 146.59 | 45 | 11/16 Roads completed and 3/16 Nos of roads WMM work is progress and other 2/16 road section work is progress. | 0 | 0.00 | 04/Jun/2026 | |||
| 19 | TURIP/2025-26/098/ROAD/00003 | Relaying of Road-Bituminous Road098011R114-NORTH PALPANNAICHERRY NORTH LANE , 098013R170-CHOKANATHAR KOIL STREET , 098012R140-SOWRIYAR KOIL STREET , 098012R150-MARIAMMAN KOIL STREET , 098013R188-MUNICIPAL PETTAI , 098015R202-NELLUKADAI STREET , 098013R157-SABATHIYAR KOIL STREET , 098013R176-NEITHAL NAGAR , 098017R247-COOKES ROAD , 098016R216-SIVAN MELA VEETHI , 098020R283-PERUMAL MELAVADAMBOOKI , 098020R289-PERUMAL KEEL LANE , 098021R303-V.O.C. STREET , 098019R280-MARKET NORTHSIDE , | 401/2026/SS1-11 | 06/Jan/2026 | 635 | 18484/2023/DO1 – PKG 2 | 07/Jan/2026 | 192 | 04/Feb/2026 | 04/Feb/2026 | 4 Months | 156.63 | 81 | 13/14 Nos of roads completed & 1/14 Nos of road WMM work is progress. | 0 | 0.00 | 04/Jun/2026 | |||
| 20 | TURIP/2025-26/098/ROAD/00002 | Relaying of Road-Bituminous Road098003R023-SIVAN SOUTH STREET , 098007R058-JADAIYANA HAJIYAR STREET , 098006R048-THERUPALLI KULA STREET , 098004R033-KALPANDAGASALAI STREET , 098007R050-PEERODUM STREET , 098009R093-PERUMAL NADAR THOTTAM , 098002R011-PERUMAL KEELAVEETHI , 098002R017-VANNAN KULAM VADAKARAI , 098001S001-VETRILAIKARAN THIRUVASAL , 098010R098-MUDUKKU THAZHAI LANE , 098010R107-SAMBATHOTTAM , 098010R108-AMBETHKAR NAGAR MAIN ROAD , 098010S033-BANGALOW THOTTAM , 098011R113-NORTH PALPANNA | 401/2026/SS1-11 | 06/Jan/2026 | 635 | 18484/2023/DO1 – PKG 1 | 07/Jan/2026 | 184 | 04/Feb/2026 | 04/Feb/2026 | 4 Months | 150.14 | 34 | 5/15 Roads Completed. (3/15 Nos of road BM work is progress and other 7/15 nos of roads section work is progress). | 0 | 0.00 | 04/Jun/2026 | |||