i) The long stretch of Car Street rainwater into the town. This storm water comes with silt and silts the entire drainage of the town. Therefore in order to avoid present flooding of the town during rainy season, it is rainwater construction exclusive storm water during along the foot of Link to drainage outlets
ii) The end of this proposed channel has to be linked to Canal.
Existing Status
| Total Length of Storm Water Drains | 12.03 K.M. | ||
| Open Drain | 10.215 K.M | ||
| Closed Drain | 1.015 K.M | ||
| Kutcha | 0.800 K.M | ||
The information provided in the above table indicates that nearly 79% of road were provided with storm water drain.