Amrut Reforms

AMRUT 2016-17

Name of the scheme Name of the Work AS No.   & Date TS No.   & Date Revised Administrative Sanction  Amount Date of Tender Date of Work Order Present Stage of work Expenditure So far          :
AMRUT  (Atal  Mission for Rejenuation and Urban Transformation) 2016-17  SAAP-2 . Improvements to Water Supply Distribution System (Rezoning) in Kumbakonam Municipality     (Scheme No. AMRUT.II – 036 ) G.O.(Ms)No. 111, MA&WS (MC.2) Dept.  dated 25.10.2017 C.E., O/o.CMA Office Proc. 18281/2017/DO1 dt.13.11.17 (ER.No.279/2017-18) 5689.00 20-12-2017 01-03-2018 Work Completed. 5865.33
AMRUT  (Atal  Mission for Rejenuation and Urban Transformation) 2016-17  SAAP-2  UGSS  for uncovered areas (Scheme No. AMRUT.II – 037 ) G.O.(Ms)No. 111, MA&WS (MC.2) Dept.  dated 25.10.2017 C.E., O/o.CMA Office Proc. 18281/2017/DO1 dt.13.11.17 (ER.No. 280 /2017-18) 7060.00 20.12.2017 17.05.2018 Work Completed 4842.38