Sewerage
Government have accorded Administrative Sanction of Rs.1016.00 Lakh for implementing Under Ground Drainage system to Chinnamanur Municipality. Revised Administrative Sanction accorded for Rs.1452.00 Lakh for above scheme.
At present UGSS was completed in all aspects by TWAD Board and trial run was started since 01.04.2012.
Out of targeted 4650 House service connections, 6230 connections were given so for. Out of targeted 3.99 MLD for ultimate capacity, so far 3.70 MLD inflow in the STP.
Entire public toilets have already been linked in the existing under ground drainage system. For covering private house holds, a sum of Rs.0.25 lakh litre expected per month and over flows. To collect the over flow in private toilets, necessary arrangements have been made in the inlet chamber in the existing STP site under septage management plan