Water Supply

 

Source Palar Bed
Location Veppur
Distance 3 K.M.
Year of Commissioning 1978, 2008
Installed capacity 4.10 MLD
Designed up to ultimate with population
Head works infiltration well 5 Nos
Gallery Well
Collection Well 1 No
No. of Over Head Tanks with Capacity
1. Anna nagar 5.00 Lakhs Litre
2. K M L Park 2.75 Lakhs Litre
3. Kaspa 3.00 Lakhs Litre
4. Thoppukana 3.00 Lakhs Litre
5. TNHB-I 2.50 Lakhs Litre
6. TNHB-II 4.00 Lakhs Litre
7. Boopathy Nagar 4.00 Lakhs Litre
Total 24.25 Lakhs Litre
No. of Distribution Zone 7 Nos.
Length of Pumping Main 12.50 K.M.
Total Distribution Main 46.20 K.M.
Total No. of Public Fountain 199 Nos.
Motors Details Veppur Head Works
30 HP Submersible – 6
75 HP Submersible – 2
Generator (KVA)
Pumping Details  
Head works 4.73 MLD
Local Sources (CWSS) 0.75 MLD
Total 5.48 MLD
Total No. of House Service Connections
Domestic  7468 Nos.
Non Domestic     154 Nos.
Industrial     –
Total  7622 Nos.