Name of the ULB | Name of the Project | Name of the scheme (AMRUT/ UIDSSMT/KFW etc) | Year | Project executed by TWAD/ULB/ others | Date of work order | Target date of completion as per agreement | % of Physical Progress | Project cost(Rs. In lakh) | Expenditure incurred(Rs. In lakh) | work status |
Arani | Water Supply Improvement Scheme | UIDSSMT | 2011-12 | TWAD | 17.12.2016 | 17.12.2017 | 100% | 3626.2 | 3399.28 | Work Completed |
Progress of Solid Waste Management- Biomining | ||||||||||||
Name of the ULB | SHPC Sanctioned | Location of Dump yard | Area to be reclaimed (Acre) | Quantity of Volume in Cu.M | Estimate Amount(Rs. In lakh) | AS Date | TS Date | Tender Date | Agreement Date | Work order Date | Name of Third party verification Agency | Expenditure incurred |
Arani | 4th SHPC | Velapadi | 1.82 | 16650 | 110 | 24.07.2018 | 31.7.2018 | 17.8.2018 | 16.11.2018 | 16.11.2018 | Anna University | 54.35 |
Waste Management- Micro Composting Centres | ||||||||||||
Name of the ULB | SHPC Sanctioned | No.of MCCs Sanctioned | Estimate Amount(Rs In lakh) | AS Date | TS Date | Tender Date | Agreement Date | Work order Date | Target date of Completion as per agreement | No.of MCCs Completed and Put into use | Expenditure incurred | Present Stage of MCCs under Construction |
Arani | 4th SHPC | 5 | 218 | 28.03.2018 | 10.04.2018 | 03.05.2018 | 15.05.2018 | 15.05.2018 | 15.11.2018 | 5 | 117 | Completed |
Tamilnadu Urban Road Infrastructure Programme 2016 -17 to 2019-20 | ||||||||||
Name of the Municipality | Year | Amount alloted(Rs In laks) | Estimate Amount(Rs In laks) | Length in Km | Work Order Date | Financial Progress | Present Stage & Probable Date of Completion | |||
Completed | Progress | To be commenced | Expenditure | |||||||
Arani | 2016-17 | 200.00 | 200.00 | 5.380 | 17.11.2016 | 12 | 0 | 0 | 195.43 | Completed |
2017-18 | 100.00 | 100.00 | 2.208 | 05.12.2018 | 8 | 0 | 0 | 61.64 | Completed | |
2018-19 | 100.00 | 100.00 | 2.208 | 16.11.2018 | 8 | 0 | 0 | 88.45 | Completed | |
2019-20 | 500.00 | 500.00 | 9.100 | 22.11.2019 | 3 | 30 | 0 | 0.00 | 31.12.2020 |
14CFC | |||||||||||||||
Name of the ULB | Types of Road | Total No of Road works takenup | Total Length in Km | Estimate Amount(Rs .In lakh) | Date of AS | Date of TS | Tender date | Work order date | Progress | Completed | |||||
BT | CC | Paver Block | |||||||||||||
Nos. | KM | Nos. | KM | Nos. | KM | ||||||||||
Arani | 6 | 2.580 | 0 | 0.000 | 1 | 0.450 | 7 | 3.030 | 197.65 | 6.01.2020 | 7.01.2020 | 28.01.2020 | 03.02.2020 | 4 | 3 |
IUDM 2018 -19 to 2019-20 | ||||||||
Name of the ULB | Name of the sector | Estimate cost(Rs .in lakh) | Amount alloted(Rs .in lakh) | Length in Kms | Work order Date | No of works taken up | Completed | Expenditure(Rs .in lakh) |
Arani | Roads (2018-19) |
999.50 | 999.50 | 18.305 | 27.2.2019 | 40(5pkgs) | Completed | 911.00 |