1. SOLID WASTE MANAGEMENT (SWM) – 2017-18
Name of the Work : Construction of Micro Compost Centre.
AS No. : The CMA, Chennai Roc.No. 4235/2018/P3 Dated: 07.02.2018
- Estimate Amount : Rs.95.00 Lakhs
- No.of Works Taken up : 2 Nos
- Date of Tender : 28.09.2017
- Date of Work Order : 03.10.2017
- Present Stage of Work : Works Completed
- Expenditure So far : Rs.94.17 Lakhs
2. SOLID WASTE MANAGEMENT (SWM) – 2017-18
Name of the Work : Purchase of Light Commercial Vehicle 2.0 cum capacity with box Tipper BS4 – 9 Nos
AS No. : The CMA, Chennai Roc.No. 4235/2018/B3 dated: 07.02.2018
- Estimate Amount : Rs.50.40 Lakhs
- No. of Works Taken up : 1 No.
- Date of Tender : 15.03.2018
- Date of Work Order : 23.04.2018
- Present Stage of Work : Completed 9 Nos of Vehicles Received
- Expenditure So far : Rs.49.52 Lakhs
3. SOLID WASTE MANAGEMENT (SWM) – 2018-19
Name of the Work : Purchase of Battery Operated Vehicle – 9 Nos
AS No. : The CMA, Chennai Roc.No. 38984/2014/P1 dated: 24.09.2018
- Estimate Amount : Rs.16.20 Lakhs
- Date of Tender : 12.10.2018
- Date of Work Order : 31.10.2018
- Present Stage of Work : Completed 9 Nos of Vehicles Received
- Expenditure So far : Rs.16.15 Lakhs
4. SOLID WASTE MANAGEMENT (SWM) – 2018-19
Name of the Work : Removal of the legacy waste of 27000 Cu.m through Bio-Mining Process to reclaim the existing dump yard located at Anakaputhur EB colony in Anakaputhur Municipality
AS No. : The CMA, Chennai Roc.No. 22866/2018/P3 dated: 23.08.2018
- Estimate Amount : Rs.178.00 Lakhs
- Date of Tender : 03.12.2018
- Date of Work Order : 07.12.2018
- Present Stage of Work : 26,000 Cu.m Reclaimed
- Expenditure So far : Rs.61.43 Lakhs
5. TURIP – 2018-19
Name of the work : Providing B.T. Road & Cement Concrete Road
AS No. : The CMA, Chennai Roc.No. 12981/2018/E3 dated: 09.07.2018
- Estimate Amount : Rs.500.00 Lakhs
- No. of Package taken up : 3 Nos.
- Date of Tender : 28.09.2018
- Date of Work Order : 05.11.2018
- Present Stage of Work : Completed
- Expenditure So far : Rs.368.00 Lakhs
6. IUDM – 2018-19
Name of the work : Construction of Storm Water Drain
AS No. : G.O.(Ms) No.12 MAWS (MA-2) Dept., dated: 29.01.2019
- Estimate Amount : Rs.114.00 Lakhs
- No. of Package taken up : 2 Nos.
- Date of Tender : 19.02.2019
- Date of Work Order : 06.03.2019
- Present Stage of Work : Completed
- Expenditure So far : Rs. 58.75 Lakhs