1. SBM – BIO MINING – 2018-19 | ||
Name of the work : Revamping of Dump site through Bio mining to Recover the land at Tharvazhi and Bethlegam Compost Yard | ||
AS No: G.O. (MS) No.36 dt.22.02.2019 of the MA&WS Dept. | ||
Estimate Amount | : | Rs.750.00 Lakhs |
Date of Tender | : | 14.11.2019 |
Date of Work Order | : | 12.02.2020 |
Present Stage of work | : | Out of 114721 legacy waste 109428 cum have been processed balance work under progress |
Expenditure So far | : | Rs.125.87 Lakhs |
SCHOOL IMPROVEMENT GRANT | ||||||||||||||
For the year of 2022-23 | ||||||||||||||
(Rs.In Lakhs) | ||||||||||||||
Sl. No |
Dis
trict |
ULB Name | Name of Work | Work Order Date | Estimate Amount | Work Progress | Physical Progress | Expenditure (in Cr) | %Expenditure | |||||
Taken Up | Completed | Pending | To be started | Stage of Work | Percent % | |||||||||
1 | Thirupattur | Ambur | Construction 2 number of class room in Ground floor and First floor (2 class room) at Sannankuppam Municipal Middle School. | 07.12.2023 | 70 | 1 | – | 0 | 0.00 | P.C.C. 1:4:8 and steel fabrication for grade beam work under progress | 25% | – | – | |
Construction 2 number of class room in Ground floor and First floor (2 class room) at Bethlegam Municipal Middle School. | 07.12.2023 | 70 | 1 | – | 0 | 0.00 | Column raising work and Brick work for first floor under progress | 40% | ||||||
Construction 2 number of class room in Ground floor and First floor (2 class room) at Kaspa B Municipal Middle School. | 07.12.2023 | 70 | 1 | – | 0 | 0.00 | Parapet wall and Plastering work under Progress | 60% | ||||||
Construction 2 number of class room in Ground floor and First floor (2 class room) at Govindapuram Municipal Middle School. | 07.12.2023 | 70 | 1 | – | 0 | 0.00 | Plastering work for ground floor under progress | 45% | – | – |
AMRUT 2.0 | |||||||||||||
AMRUT 2.0 (for the periods 2022-23 and 2023-24 separately) | |||||||||||||
For the year of 2022-23 | |||||||||||||
1 | Thirupattur | Ambur | NIL | ||||||||||
For the year of 2023-24 | |||||||||||||
(Rs.In Lakhs) | |||||||||||||
Sl. No |
Dis
trict |
ULB Name | Name of Work | Work Type | Estimate Amount | Work Progress | Physical Progress | Expenditure (in Cr) | %Expenditure | ||||
Work Order Date | Taken Up | Completed | Pending | Stage of Work | Percent % | ||||||||
1 | Thirupattur | Ambur | Rejuvenation of Palathu kulam at Madhakadduppu Road Wd no 33 in Ambur Municipality | 20 | 07.02.2024 | 1 | – | 0 | Work Completed | 100% | Fund Not Received | – | |
Ambur | Rejuvenation of Eallaiamman Kovil Kulam at kaspa-A Ward no 12 TS No C22-47 in Ambur Municipality | 10 | 07.02.2024 | 1 | – | 0 | Side Wall Work Under Progress | 95% | – |
MUNICIPALITES – ROAD WORKS PROGRESS 2024-25 | ||||||||||||||
VELLORE REGION | ||||||||||||||
Sl.
No |
Name of the Municipality | Name of the Scheme | Details of Progress | Remarks | ||||||||||
Sanctioned Length in Km | Estimate Amt (Rs in Cr) | No. of Package | Work order Date | No of works taken up | completed Nos | Completed Length in KM | Progress | Non Started | Fund Released to ULB (Rs. in Cr) |
Expenditure (Rs. in Cr) | ||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | |
1 | Ambur | TURIP 24-25 | 13.26 | 6.23 | 16 | 04.03.2024 | 112 | 58 | 7.50 | 54 | – | 3.38 | 0.62 | – |
KNMT 24-25 | 3.250 | 2.33 | 7 | 04.03.2024 | 18 | 12 | 1.10 | 8 | – | 0 | 0 | Fund Not Received | ||
15th CFC 24-25 | 5.78 | 2.77 | 12 | 04.03.2024 | 54 | 40 | 2.80 | 16 | – | 0 | 0.52 | Fund Not Received | ||
TOTAL | 22.290 | 11.330 | 35.000 | 184.000 | 110.000 | 11.400 | 78.000 | 0.000 | 3.380 | 1.140 | – |
THIRUPATHUR DISTRICT AMBUR MUNICIPALITY SBM 2.0 2022-2023 & 2023-24 |
||||||||
AMBUR MUNICIPALITY | ||||||||
S.
No |
Name of Scheme | Name of Work | Estimate Amount (in Lakhs) |
As Date | Ts Date | Tender Called | Work Order Date | Stage ofwork |
2 | SBM 2.0 ( 2023-24) | CONSTRUCTION OF COMMUNITY TOILET AT SANTRORKUPPAM ERI KARAI IN AMBUR MUNICIPALITY | 18.00 | 11.03.2024 | 12.03.2024 | 14.06.2024 | 08.06.2024 | Work order will be issued on 18.06.2024, Work to be started |
CONSTRUCTION OF COMMUNITY TOILET AT NATHISEELAPURAM AREA IN AMBUR | 18.00 | 11.03.2024 | 12.03.2024 | 14.06.2024 | 08.06.2024 | Work order will be issued on 18.06.2024. Work to be started | ||
SBM 2.0 ( 2023-24) | CONSTRUCTION OF COMMUNITY TOILET AT PNR NAGAR AREA IN AMBUR MUNICIPALITY | 12.00 | 11.03.2024 | 12.03.2024 | 14.06.2024 | 08.06.2024 | Work order will be issued on 18.06.2024. Work to be started | |
CONSTRUCTION OF COMMUNITY TOILET AT KAMBIKOLLAI PARK AREA IN AMBUR MUNICIPALITY | 12.00 | 11.03.2024 | 12.03.2024 | 10.06.2024 | 08.06.2024 | Work order will be issued on 18.06.2024. Work to be started | ||
CONSTRUCTION OF URINALS AT BUS STAND IN AMBUR MUNCIPALITY | 0.64 | 11.03.2024 | 12.03.2024 | 19.06.2024 | 01.07.2024 | Work order will be issued on 01.07.2024, Work to be started | ||
3 | SBM 2.0 ( 2023-24) | CONSTRUCTION OF 5TPD MATERIALS RECOVERY FACILITY CENTRE @ THARVAZHI COMPOST YARD | 42.50 | 07.03.2024 | 08.03.2024 | 10.06.2024 | 18.06.2024 | Work order will be issued on 18.06.2024. Work to be started |
CONSTRUCTION OF 5TPD MATERIAL RECOVERY FACILITY CENTRE AT REDDY THOPPU COMPOST YARD IN AMBUR MUNICIPALITY | 42.50 | 07.03.2024 | 08.03.2024 | 10.06.2024 | 18.06.2024 | Work order will be issued on 18.06.2024. Work to be started |